Day in the RoleStatement of workContract schedule: what the supplier delivers
Version1.0
Date15 March
ReferenceRHC-SOW-01
SupplierThe building contractor (selected by tender)

This statement of work forms part of the contract between Day in the Role (the buyer) and the supplier named above.

1. Background

The council is converting the Riverside warehouse into a community health clinic that must open in month 7.

2. Scope of work

The supplier will:

Not included:

3. Deliverables and dates

Delive­rableDue
Site cleared of asbestosWeek 11
Structure repairedWeek 17
Fit-out completeWeek 25
Handover documentsWeek 26

4. Acceptance

Building-control sign-off and a joint inspection with the council's compliance lead.

5. Contract type and price

Fixed priceTime and materials (with a cap)Cost-reimbursable plus fee
Price€3,000,000

6. Payment milestones

Payment due whenShare of price
On start10%
Site cleared, accepted30%
Structure repaired, accepted30%
Fit-out accepted20%
6 months without defects10%

7. Changes

Changes to scope, dates or price are agreed in writing by both parties before work on them starts.

For the buyer
Signature
Date
For the supplier
Signature
Date

Letters and symbols: IT Information technology · RHC Riverside Health Centre (used as a reference prefix, like RHC-SOW-01)

Day in the Role · Statement of workIllustrative example · not a real project or organisation · dayintherole.com