| Version | 1.0 |
|---|---|
| Date | 15 March |
| Score | Likelihood | Impact (time or cost) |
|---|---|---|
| 5 | Over 70% | Over 1 month late or over €150k |
| 4 | 50 to 70% | 2 to 4 weeks or €75k to €150k |
| 3 | 30 to 50% | 1 to 2 weeks or €25k to €75k |
| 2 | 10 to 30% | Under 1 week or under €25k |
| 1 | Under 10% | Hardly noticeable |
Agree your own scales with the team before scoring. Score = likelihood × impact.
| ID | Risk or opportunity | L | I | Score | Owner | Strategy | Response actions |
|---|---|---|---|---|---|---|---|
| R1 | Equipment takes 14 weeks; opening could slip | 4 | 3 | 12 | Aya (Project Coordinator) | Reduce | Order early with cancellation clause |
| R2 | Old structure needs more repair; costs rise | 3 | 4 | 12 | Annelise (Project Manager) | Reduce | Survey done; contingency €150k |
| R3 | Not enough nurses hired in time | 3 | 4 | 12 | Adaugo (HR Lead) | Reduce | Start hiring month 3; agency backup |
| R4 | Equipment prices rise 15% before ordering | 4 | 3 | 12 | Alder (Procurement) | Transfer | Fixed-price contract signed now |
| R5 | Licence refused over ventilation | 2 | 5 | 10 | Antonia (Compliance Lead) | Reduce | Inspector reviews design in month 2 |
| R6 | Opportunity: digital health grant pays €80k | 3 | 2 | 6 | Aine (IT Lead) | Enhance | Application by week 6 |
Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.
Letters and symbols: HR Human resources · ID Identifier: a reference number or code · IT Information technology · L · I Likelihood and impact (risk scores) · ÷ × Divided by, multiplied by · €k Thousands of euros (€150k = €150,000)