← Risk register: explanationFilled-in example Blank template
Day in the RoleRisk registerRanked risks and opportunities, with responses
Version1.0
Date15 March

Heat map

Likelihood →
5
4
R1 R4
3
R6
R2 R3
2
R5
1
12345
Impact →

Scoring scales

ScoreLikelihoodImpact (time or cost)
5Over 70%Over 1 month late or over €150k
450 to 70%2 to 4 weeks or €75k to €150k
330 to 50%1 to 2 weeks or €25k to €75k
210 to 30%Under 1 week or under €25k
1Under 10%Hardly noticeable

Agree your own scales with the team before scoring. Score = likelihood × impact.

Register

IDRisk or oppor­tunityLIScoreOwnerStrategyResponse actions
R1Equipment takes 14 weeks; opening could slip4312Aya (Project Coordinator)ReduceOrder early with cancellation clause
R2Old structure needs more repair; costs rise3412Annelise (Project Manager)ReduceSurvey done; contingency €150k
R3Not enough nurses hired in time3412Adaugo (HR Lead)ReduceStart hiring month 3; agency backup
R4Equipment prices rise 15% before ordering4312Alder (Procurement)TransferFixed-price contract signed now
R5Licence refused over ventilation2510Antonia (Compliance Lead)ReduceInspector reviews design in month 2
R6Opportunity: digital health grant pays €80k326Aine (IT Lead)EnhanceApplication by week 6

Strategies for threats: avoid · transfer · reduce · accept. For opportunities: exploit · enhance · share · accept.

Letters and symbols: HR Human resources · ID Identifier: a reference number or code · IT Information technology · L · I Likelihood and impact (risk scores) · ÷ × Divided by, multiplied by · €k Thousands of euros (€150k = €150,000)

Day in the Role · Risk registerIllustrative example · not a real project or organisation · dayintherole.com