| Version | 1.0 |
|---|---|
| Date | 15 March |
Scope statement v1.0 and WBS (6 deliverables)
Opening in week 30 (month 7); critical path through the building works
€4.2M including €150k contingency; €300k reserve held by the sponsor
| Area | How we manage it | Detail in |
|---|---|---|
| Risk | Weekly review; board monthly | Risk register |
| Quality | Checks at each building phase; mock clinic day | Scope statement |
| Buying | Fixed price for works; capped T&M for investigations | Statement of work |
| Communication | Weekly status, monthly board and residents' update | Communication plan |
| Stakeholders | Engagement plan per key person | Stakeholder register |
| Resources | Time agreed with line managers | RACI chart |
Letters and symbols: RACI Responsible (does the work), Accountable (owns the result), Consulted (asked before), Informed (told after) · T&M Time and materials: paying for hours worked and materials used · WBS Work breakdown structure · €k Thousands of euros (€150k = €150,000) · €M Millions of euros (€4.2M = €4,200,000)