Day in the RoleProject management planThe plan on a page
Version1.0
Date15 March
Scope baseline

Scope statement v1.0 and WBS (6 deliverables)

Schedule baseline

Opening in week 30 (month 7); critical path through the building works

Cost baseline

€4.2M including €150k contingency; €300k reserve held by the sponsor

Management approach per area

AreaHow we manage itDetail in
RiskWeekly review; board monthlyRisk register
QualityChecks at each building phase; mock clinic dayScope statement
BuyingFixed price for works; capped T&M for investigationsStatement of work
CommunicationWeekly status, monthly board and residents' updateCommunication plan
StakeholdersEngagement plan per key personStakeholder register
ResourcesTime agreed with line managersRACI chart

Change control

1Request logged
2Impact assessed (scope, time, cost, risk)
3Decided within tolerance or by the board
4Plans and baselines updated
5Everyone informed
Tolerances
Annelise (Project Manager): up to €25k and 2 weeks per stage. Beyond that: the board.
Sponsor
Signature
Date
Senior user
Signature
Date

Letters and symbols: RACI Responsible (does the work), Accountable (owns the result), Consulted (asked before), Informed (told after) · T&M Time and materials: paying for hours worked and materials used · WBS Work breakdown structure · €k Thousands of euros (€150k = €150,000) · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Project management planIllustrative example · not a real project or organisation · dayintherole.com