← Exception report: explanationFilled-in example Blank template
Day in the RoleException reportA tolerance will be exceeded: options for the board
Version1.0
Date15 March
ExceptionA forecast is beyond tolerance. The board must decide.
ReferenceEX-01
DateWeek 23
AreaTime (online booking)

What happened

The council's patient records system needs a security upgrade before the booking system can connect. Integration will be three weeks late.

Tolerance and forecast

Time (weeks)
-2+2
+3 weeks for online booking
Cost (€ thousands)
-25+25
Within tolerance: about +€10k against the stage plan

Shaded band: agreed tolerance. Marker: current forecast.

Impact

Online booking not ready for opening in week 30. Online users' benefits start later. No effect on the building or licence.

Options

OptionCostTimeRisk
A. Open with phone booking; online from week 4 after opening€0On timeLow
B. Delay opening by 3 weeks€0+3 weeksPublic promise broken
C. Pay for an extra vendor team€40,000May still slipMedium

Recommendation

ABC
Why
Opens on time at no cost; phone booking was already planned as the back-up.

Board decision

Approved option A

Sponsor
Signature
Date

Letters and symbols: €k Thousands of euros (€150k = €150,000)

Day in the Role · Exception reportIllustrative example · not a real project or organisation · dayintherole.com