| Version | 1.0 |
|---|---|
| Date | 15 March |
Might happen. Write the cause, then the effect. Likelihood (L) and impact (I): H, M or L.
| ID | Risk (cause → effect) | L | I | Owner | Response | Status |
|---|---|---|---|---|---|---|
| R1 | Equipment takes 14 weeks, so opening could slip | H | M | Aya (Project Coordinator) | Order early with a cancellation clause (approved) | Open |
| R2 | Old structure needs more repair than expected, costs rise | M | H | Annelise (Project Manager) | €40k survey before works; contingency held by sponsor | Open |
| R3 | Not enough nurses hired in time | M | H | Adaugo (HR Lead) | Start hiring in month 3, agency backup | Open |
Treated as true without proof. Check each one by a date; if it fails, it becomes an issue.
| ID | Assumption | Check by | Status |
|---|---|---|---|
| A1 | Warehouse purchase completes in month 1 | Kick-off | Failed: see I1 |
| A2 | Regional funding per patient stays at today's rate | Month 3 | Open |
Happening now. Each needs an owner, an action and a due date.
| ID | Issue | Priority | Owner | Action | Due |
|---|---|---|---|---|---|
| I1 | Purchase completes in month 2, not month 1 | High | Annelise (Project Manager) | Re-plan works, options to Atticus (Sponsor) | Friday |
What we need from others, or others need from us.
| ID | Dependency | From or to whom | Needed by | Status |
|---|---|---|---|---|
| D1 | Licence inspection needs the finished building | Health authority | Month 6 | Planned |
| D2 | Network cabling before booking system install | Building contractor | Month 4 | Open |
Letters and symbols: HR Human resources · ID Identifier: a reference number or code · RAID Risks, Assumptions, Issues, Dependencies · L · I Likelihood and impact (risk scores) · €k Thousands of euros (€150k = €150,000)