← Work breakdown structure: explanationFilled-in example Blank template
Day in the RoleWork breakdown structureThe whole scope, broken into pieces
Version1.0
Date15 March
1 · ProjectRiverside Health Centre
1Building
1.1 Design
1.2 Asbestos removal
1.3 Structural repairs
1.4 Fit-out
2Equipment
2.1 Clinical equipment
2.2 Furniture
2.3 Installation
3Booking system
3.1 Purchase
3.2 Setup
3.3 Integration
3.4 Testing
4People
4.1 Hiring
4.2 Training
4.3 Rotas
5Licence and opening
5.1 Licence
5.2 Mock clinic day
5.3 Opening event
6Project management
6.1 Planning
6.2 Reporting
6.3 Closure

Rule of thumb: every box is a deliverable (a noun), the boxes under a parent add up to exactly the parent, and project management has its own branch.

WBS dictionary (key work packages)

CodeDescrip­tionAccepted whenEstimate
1.4Fit-out: rooms, floors, ventilation to infection-control standardBuilding-control sign-off€1.4M · 8 weeks
3.2Setup: appointment types, opening hours, staff rotas in the system50 test bookings succeed€40k · 4 weeks

Letters and symbols: WBS Work breakdown structure · €k Thousands of euros (€150k = €150,000) · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Work breakdown structureIllustrative example · not a real project or organisation · dayintherole.com