Day in the RoleProject closure reportThe final account of the project
Version1.0
Date15 March

Objectives and results

ObjectiveResultStatus
Clinic open in month 7Yes: opened week 30RAG
Care within 15 minutes for RiversideYes: 12 minutes on averageRAG
GP waiting under 1 week within a yearOn the way: 1.5 weeks; reviewed at month 12RAG

Baselines and actuals

Cost (€M)
Baseline4.2
Actual4.16
Time (weeks)
Baseline30
Actual30
Scope
6 deliverables plus 4 approved changes; online booking 4 weeks after opening

Funds

Approved funding €4,500,000
Spent €4,160,000
Returned €340,000

Open items after closure

ItemOwner and date
Online booking go-liveIT, week 4 after opening
Retention releaseProcurement, month 6
Benefits reviewsAtticus (Sponsor), months 6 and 12

Board closure

The board confirms the project is complete and formally closed. Records are archived.

Sponsor
Signature
Date
Senior user
Signature
Date

Letters and symbols: GP General practitioner: a family doctor · IT Information technology · R · A · G Red, amber, green: status lights

Day in the Role · Project closure reportIllustrative example · not a real project or organisation · dayintherole.com