← End-stage report: explanationFilled-in example Blank template
Day in the RoleEnd-stage reportStage gate: continue, with conditions, or stop
Version1.0
Date15 March
Pre-project
◆
Initiating
◆
Planning
◆
Executing
◆
Monitoring
◆
Closing

◆ = stage gate. Circle the gate this report is for.

Stage performance against baselines

AreaBaselineActual or forecastStatus
TimeOpening week 30Week 30 (online booking +4 weeks)RAG
Cost€4.2M€4.1M to €4.13MRAG
Scope6 deliverables6, plus 3 approved changesRAG
QualityAccepted to criteriaAccepted with 6 minor defectsRAG

Business case check

QuestionAnswer
Still needed?Yes: waiting times keep rising
Still affordable?Yes: about €4.2M, inside the approved funding
Benefits still achievable?Yes: online booking benefits a month later
PaybackAbout 7.1 years (was 7)

Risks going forward

  • Licence inspection (slot booked, week 28)
  • Staff training complete in time
  • Online booking go-live after opening

Lessons from this stage

  • Book every external inspection as early as possible
  • Watch supplier backlogs as triggers
  • The drawing revision log works

Next stage

Handover and opening: licence, mock clinic day, opening in week 30, contract closure and the benefits plan.

Board decision

GoGo with conditionsStop
Conditions
The licence result must be in before the opening event is announced.
Sponsor
Signature
Date

Letters and symbols: R · A · G Red, amber, green: status lights · ◆ A milestone or decision point · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · End-stage reportIllustrative example · not a real project or organisation · dayintherole.com