Day in the RoleWork packageWork order: one piece of work, handed over
Version1.0
Date15 March
Work package4.1
NameHiring
Handed toAdaugo (HR and Training Lead)
Handed over byAnnelise (Project Manager)

What to deliver

Accepted when

Contracts signed, checks complete, start dates agreed before week 23.

StartWeek 11
FinishWeek 22
EffortAbout 40 days of HR time

Tolerances

Time±2 weeks
Cost±€5,000

Inside these limits the owner decides; beyond them, escalate before acting.

Constraints

Offers sent within 48 hours of the final interview.

Reporting

Short update every Monday; escalate at once if two weeks behind or a key role can't be filled.

Owner accepts the work
Signature
Date
Project manager
Signature
Date
✂Closing stub
Accepted on
Checked by
Closed

Letters and symbols: HR Human resources · ± Plus or minus: the allowed range either side

Day in the Role · Work packageIllustrative example · not a real project or organisation · dayintherole.com