← Supplier performance review: explanationFilled-in example Blank template
Day in the RoleSupplier performance reviewScored on evidence, improved together
Version1.0
Date15 March
SupplierBuilding contractor
ContractRHC-SOW-01
PeriodMonth 4

Scores

MeasureScore (circle one)Evidence
Time12345Two weeks behind (damp in north wall)
Quality12345Ventilation defect in rooms 4 to 6
Safety12345No incidents; asbestos removal certified
Communication12345Cabling completion not shared
Cost12345One claim, settled at €20,000

1 = well below what was agreed · 3 = as agreed · 5 = well above. Every score needs evidence.

Average3.4 of 5

What went well

  • Excellent safety record
  • Quick response to the asbestos condition

Overall

Performing wellImprovement neededFormal warning

Improvements agreed

ActionOwnerBy when
Recovery plan with weekly checkpointsArash (Contractor)Friday
Drawing revision log, confirmed by each tradeArash (Contractor)Next week
Weekly coordination meeting attendanceArash (Contractor)Ongoing
For the buyer
Signature
Date
For the supplier
Signature
Date

Letters and symbols: RHC Riverside Health Centre (used as a reference prefix, like RHC-SOW-01)