← Scope statement: explanationFilled-in example Blank template
Day in the RoleScope statementWhat is in, what is out, how it will be accepted
Version1.0
Date15 March
Project objective

Residents of Riverside get everyday care within 15 minutes of home; GP waiting time under 1 week within a year of opening.

IN What we will deliver

Delive­rableAccepted when
Converted buildingBuilding-control sign-off; joint inspection passed
Clinical equipmentInstalled, tested and certified on site
Booking system50 test bookings succeed online and by phone
30 staff hired and trainedAll roles filled; training records complete
Licence to operateGranted by the health authority
OpeningFirst patients seen; residents informed

OUT Not in this project

  • Emergency care
  • Hospital beds
  • Pharmacy (possible later)
  • Café
  • Dental care

Constraints

  • Budget €4.2M
  • Opening in month 7
  • Health authority licence rules

Assumptions

  • Survey findings are complete
  • Regional funding per patient unchanged
Sponsor
Signature
Date
Senior user
Signature
Date

Letters and symbols: GP General practitioner: a family doctor · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Scope statementIllustrative example · not a real project or organisation · dayintherole.com