Day in the RoleRisk management planHow this project handles risk
Version1.0
Date15 March

Risk appetite by area

AreaRisk appetiteWhat it means in practice
Patient safety
LowModerateHigh
No avoidable risk to patients is accepted
Legal compliance
LowModerateHigh
Every obligation met before opening
Cost
LowModerateHigh
Within contingency; reserve with sponsor approval
Schedule
LowModerateHigh
± 2 weeks per stage
Opening-day extras
LowModerateHigh
Nice to have; can be dropped

Roles and review rhythm

Risk owners update their risks weekly. The project manager reviews the register weekly; the board reviews the top 10 monthly.

Reserves

Contingency €150k, used by the project manager for identified risks and logged. Management reserve €300k, used only with the sponsor's approval.

When we put numbers on risk

Expected value for decisions over €25k; schedule simulation before each stage gate.

Sponsor
Signature
Date

Letters and symbols: ± Plus or minus: the allowed range either side · €k Thousands of euros (€150k = €150,000)

Day in the Role · Risk management planIllustrative example · not a real project or organisation · dayintherole.com