| Version | 1.0 |
|---|---|
| Date | 15 March |
Write lessons when they happen, good and bad. Ask “why” about the process, not “who”. Apply them while the project is still running.
| When | Type | What happened | Why | What we will do | Applied? |
|---|---|---|---|---|---|
| Week 9 | KeepImprove | Fit-out started in a certified area during asbestos removal | Checked with compliance first | Always check partial starts with the safety lead | ✓ |
| Week 14 | KeepImprove | Lead nurse lost to a slow offer | Contract took 3 weeks | Offers within 48 hours | ✓ |
| Week 18 | KeepImprove | Wrong ducts in three rooms | Revised drawing never reached the subcontractor | Drawing revision log confirmed by each trade | ✓ |
| Week 19 | KeepImprove | Delivery window agreed with shop owners | Listened before explaining | Meet affected neighbours before works start | ✓ |
| Week 21 | KeepImprove | Integration knowledge held by one person | No pairing on critical systems | Pair on every critical system | In progress |