← Control plan: explanationFilled-in example Blank template
Day in the RoleControl planKeeping the gains
Version1.0
Date15 March
ProcessRoutine appointment booking
Process ownerAurelie (Practice Nurse Manager)
Review date

Measures

MeasureDefi­nition and sampleHow oftenOwnerLimits or targetChart
Waiting timeFirst request to appointment offered, calendar days; 5 random requests a dayDailyAstrid (Data Analyst)Xbar 1.85 to 6.86; R up to 9.41Xbar-R
Daily average waitAll routine requests booked that dayDailyAstrid (Data Analyst)2.76 to 5.56; CUSUM h = 2.2I-MR and CUSUM
Not offered within 7 daysShare of the day's requestsDailyAlma (Reception Team Lead)Upper limit by day (about 0.21)P chart
Missed appointmentsOut of 50 checked a dayDaily for 3 months, then weeklyAlma (Reception Team Lead)Up to 9.8 of 50NP chart
Booking errorsErrors per bookingDailyAlma (Reception Team Lead)Upper limit by day (about 0.12)U chart
8 am answer time12 calls, minutesMonthlyAlma (Reception Team Lead)1.38 to 3.39Xbar-S

Response plan

SignalFirst actionWho actsWho to tell
Doctor off at short noticeBook cover from the listAurelie (Practice Nurse Manager)Doctors' team
Booking system downPaper booking sheets; enter laterAlma (Reception Team Lead)IT, Aurelie
CUSUM or EWMA signalCheck locum sessions and the rotaAurelie (Practice Nurse Manager)Atticus (Sponsor) if not fixed in a week
Point outside any limitFind the cause the same day; record itMeasure ownerAurelie

Lean controls

Signals: a point outside a limit, 8 in a row on one side of the centre line, 6 in a row rising or falling. Record every signal, its cause and the action.

Process owner
Signature
Date
Project leader
Signature
Date

Letters and symbols: CUSUM Cumulative sum chart: adds up differences from the target to catch small shifts · EWMA Exponentially weighted moving average chart · I-MR Individuals and moving range chart · IT Information technology · MR Moving range: the difference between one value and the previous one · NP Number defective: an NP chart counts the items failing in a fixed-size sample

Day in the Role · Control planIllustrative example · not a real project or organisation · dayintherole.com