Day in the RoleCommunication planWho needs what, how, and how often
Version1.0
Date15 March

Who hears what

AudienceWhat they needHowHow oftenFrom
Atticus (Sponsor)Progress, risks, decisions neededOne-page status by emailWeekly, FridayAnnelise (Project Manager)
Project boardProgress against baselines, exceptionsMeeting and reportMonthlyAnnelise (Project Manager)
Project teamActions, blockers, next weekMonday meetingWeeklyAya (Project Coordinator)
ResidentsNews, dates, how to registerNewsletter and council websiteMonthlyAya (Project Coordinator)
Health authority inspectorDesign and building progressReview meetingAt milestonesAntonia (Compliance Lead)
SuppliersDates, changes, acceptanceProgress meetingFortnightlyAnnelise (Project Manager)

The weekly rhythm

MonTeam meeting
TueBoard (1st Tue)
WedSupplier meeting (fortnightly)
Thu
FriStatus to Atticus (Sponsor)Residents' update (last Fri)

Write each regular meeting or report on its day. Note how often (weekly, fortnightly, monthly).

Escalation: how bad news travels

Anything that threatens a milestone or a tolerance: same day to Annelise (Project Manager), within two days to Atticus (Sponsor) with options.

Channels

With n people there are n × (n − 1) ÷ 2 possible channels.

People12
Channels66

Letters and symbols: ÷ × Divided by, multiplied by

Day in the Role · Communication planIllustrative example · not a real project or organisation · dayintherole.com