← Business case: explanationFilled-in example Blank template
Day in the RoleBusiness caseBusiness case report
Version1.0
Date15 March
Decision requested

Approve €4.2M to convert the Riverside warehouse into a community health clinic, opening in 7 months.

Executive summary

Residents of Riverside travel 40 minutes for basic care and wait 3 weeks for a GP. Converting the empty warehouse into a 24-room clinic is the only option that fits the budget, meets demand and opens by next autumn.

Investment€4.2M
Running cost€1.9M / year
Payback≈ 7 years
OpeningMonth 7

1. Why we need this

2. Options considered

OptionOutcome of the com­parison
Do nothingNot chosen: waiting times keep growing
Renovate old clinicNot chosen: too small for demand
Convert warehouseRecommended: right size, fits budget and time
Build newNot chosen: €7.5M and 18 months

3. Benefits

BenefitTodayTargetBy whenOwner
Travel time to care40 minUnder 15 minOpeningAtticus (Sponsor)
GP waiting time3 weeksUnder 1 weekYear 1Amani (Clinical Lead)
Minor emergency visits100%−20%Year 1Amani (Clinical Lead)

4. Main risks

RiskLike­lihood (L/M/H)Impact (L/M/H)Response
Old building structureMHStructural survey before purchase
Equipment lead times (14 weeks)HMOrder in month 1
Not enough staff hired in timeMHStart hiring in month 3

5. Approval

ApprovedApproved with conditionsNot approved
Conditions or comments
Sponsor
Signature
Date
Funding body
Signature
Date

Letters and symbols: GP General practitioner: a family doctor · H / M / L High, medium, low · €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Business caseIllustrative example · not a real project or organisation · dayintherole.com