Impediment board

A visible list of what is blocking the team, who is on it and its status.

Common practice
5 steps
Used by Scrum Master

What it is

A visible list of everything blocking the team, with who's handling it and its status.

When to use it

From the first Sprint, so blockers never disappear into chat messages.

Why it works

Blockers hidden in people's heads stay unsolved. Making them visible gets them owned and removed.

Do

  • Escalate with a clear ask, not just a complaint.

Don't

  • A list that grows and is never cleared.

Step by step

  1. Create the board Columns: New, Being handled, Waiting, Solved.
  2. Add blockers as soon as they appear One card each, with impact.
  3. Give each an owner Often the person best placed to remove it.
  4. Review daily or weekly Escalate what's stuck.
  5. Look for patterns Repeated blockers point to a deeper problem.
Also called: Blocker logPrint the blank template ↗

Worked example

The situation. A project team waiting on approvals.

  1. Five blockers were approvals from the same department.
  2. The project manager agreed a weekly approval slot with them.

The result. Approval waits dropped from 8 days to 3.

Impediment log Print blank
BlockerImpactOwnerStatusRaisedSolved

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

API keys, the test tool and the map licence all sit on Aaron (Scrum Master)'s board under “IT and purchasing”. The pattern leads to the fast path for small tools.

Questions people ask

Who removes impediments?

Whoever can; in projects often the project manager, in Scrum teams often the Scrum Master.