← Benefits sign-off: explanationFilled-in example Blank template
Day in the RoleBenefits sign-offBenefits measured and confirmed
Version1.0
Date15 March

Benefit lines

BenefitMethod agreed in DefineBeforeAfterValue a year
Missed appointments12,700 × change in missed share × €1515.7%8.3%€14,100
Repeat callsCalls × €1.2011,2502,813€10,125
Emergency visits (avoided cost)Visits × €120208104€12,480

Costs

CostOne-offA year
Team time€14,000€0
System changes€3,000€0
Training€1,500€0
Cover sessions€0within existing budget

Result

€36,705 a year (€24,225 clinic savings, €12,480 avoided health-system cost). One-off cost €18,500; payback about 9 months on the clinic's own savings. Check again at 12 months.

Measure each line with the method agreed in Define. Show cash savings and avoided costs separately. Include the running costs of the new process.

Finance
Signature
Date
Sponsor
Signature
Date

Letters and symbols: ÷ × Divided by, multiplied by

Day in the Role · Benefits sign-offIllustrative example · not a real project or organisation · dayintherole.com