← Benefits review: explanationFilled-in example Blank template
Day in the RoleBenefits reviewIs the investment paying off?
Version1.0
Date15 March
Review pointMonth 6 after opening

Progress from baseline to target

GP waiting time (weeks)
311.5
AchievedOn the wayNot happening
Travel time to care (minutes)
401512
AchievedOn the wayNot happening
Minor emergency visits (% change)
0-20-12
AchievedOn the wayNot happening

Left: baseline before the project. Right: target. Marker: today’s measurement.

Causes and actions

BenefitCauseActionOwner
GP waiting time15% of appointments are no-showsText reminders the day beforeAmani (Clinical Lead)
Minor emergency visitsResidents don't know about evening slotsAwareness campaignAzadeh (Community Council)

Overall

The project delivered what was approved, on time and under budget. Benefits are partly realised, with clear actions. Next review: month 12.

Sponsor
Signature
Date

Letters and symbols: GP General practitioner: a family doctor

Day in the Role · Benefits reviewIllustrative example · not a real project or organisation · dayintherole.com