← Readiness checklist: explanationFilled-in example Blank template
Day in the RoleReadiness checklistReady to go live?
Version1.0
Date15 March
Go-liveMonday, week 30

Readiness by area

AreaStatus noteCriticalReady?Fallback if not ready
BuildingAccepted, defects listedRAG
LicenceGranted after two conditions closedRAG
Staff30 hired and trainedRAG
Phone bookingSecond line added after rehearsalRAG
Online bookingIntegration 3 weeks lateRAGPhone booking for the first 4 weeks
Supplies and courierCourier moved to 15:30RAG
CommunicationOpening announced, newsletter sentRAG

Every critical item must be green, or have a fallback everyone accepts.

Rehearsal findings

FindingFixOwnerRe-tested
Phone queue too long at peakSecond receptionist 08:00 to 11:00Amani (Clinical Lead)✓
Lab samples missed the courierPick-up moved to 15:30Aya (Project Coordinator)✓

Decision

GoGo with fallbacksNo-go
Sponsor
Signature
Date
Operations owner
Signature
Date

Letters and symbols: R · A · G Red, amber, green: status lights

Day in the Role · Readiness checklistIllustrative example · not a real project or organisation · dayintherole.com