Day in the RoleReadiness checklistReady to go live?
Go-liveMonday, week 30
Readiness by area
| Area | Status note | Critical | Ready? | Fallback if not ready |
|---|
| Building | Accepted, defects listed | | RAG | |
|---|
| Licence | Granted after two conditions closed | | RAG | |
|---|
| Staff | 30 hired and trained | | RAG | |
|---|
| Phone booking | Second line added after rehearsal | | RAG | |
|---|
| Online booking | Integration 3 weeks late | | RAG | Phone booking for the first 4 weeks |
|---|
| Supplies and courier | Courier moved to 15:30 | | RAG | |
|---|
| Communication | Opening announced, newsletter sent | | RAG | |
|---|
Every critical item must be green, or have a fallback everyone accepts.
Rehearsal findings
| Finding | Fix | Owner | Re-tested |
|---|
| Phone queue too long at peak | Second receptionist 08:00 to 11:00 | Amani (Clinical Lead) | ✓ |
| Lab samples missed the courier | Pick-up moved to 15:30 | Aya (Project Coordinator) | ✓ |
Decision
GoGo with fallbacksNo-go
Letters and symbols: R · A · G Red, amber, green: status lights