← Quality audit report: explanationFilled-in example Blank template
Day in the RoleQuality audit reportAre the project's processes working?
Version1.0
Date15 March
ScopeChange control, risk management and document control, weeks 14 to 24
AuditorAdeline (Portfolio Manager)

Findings

FindingSeverityEvidence
Approved changes not always reflected in plans (2 of 5)
MajorMinorObservation
CR-05 and CR-07 records
Two risks without review dates
MajorMinorObservation
Risk register
Issue log well used and up to date
MajorMinorObservation
Issue log

Corrective actions (fix the process, not just the instance)

ActionOwnerBy when
Post-approval checklist for every changeAnnelise (Project Manager)This week
Review dates for all risksAya (Project Coordinator)Friday
Follow-up checkRe-check in four weeks
Auditor
Signature
Date
Project manager
Signature
Date

Letters and symbols: CR Change request (CR-07 = change request number 7)

Day in the Role · Quality audit reportIllustrative example · not a real project or organisation · dayintherole.com