← Handover certificate: explanationFilled-in example Blank template
Day in the RoleHandover certificateFrom project to operations
Version1.0
Date15 March
What is handed over
Riverside Health Centre: building, equipment, booking system and team
DateOpening day, week 30
From the projectAnnelise (Project Manager)
→
To operationsAmani (Clinical Lead)

Transferred

Building manuals and warranties
Equipment certificates
Booking system admin access and guide
Training records
Licence
Supplier contacts
Benefits management plan

Still open, with new owners

Open itemOwnerBy when
Online booking go-liveIT (Aine (IT Lead)'s successor)Week 4 after opening
Paint touch-ups, corridorArash (Contractor)Week 31

Support after handover

Four weeks of joint support: project team on site Mondays and Thursdays, same-day response to issues. Ends in week 34.

From the date above, the operations owner is responsible for running the result and for the benefits plan.

Project manager
Signature
Date
Operations owner
Signature
Date

Letters and symbols: IT Information technology

Day in the Role · Handover certificateIllustrative example · not a real project or organisation · dayintherole.com