| Version | 1.0 |
|---|---|
| Date | 15 March |
| Open item | Owner | By when |
|---|---|---|
| Online booking go-live | IT (Aine (IT Lead)'s successor) | Week 4 after opening |
| Paint touch-ups, corridor | Arash (Contractor) | Week 31 |
Four weeks of joint support: project team on site Mondays and Thursdays, same-day response to issues. Ends in week 34.
From the date above, the operations owner is responsible for running the result and for the benefits plan.
Letters and symbols: IT Information technology