Strategy and planning · cheat sheet

Release planning

Decide what makes a release valuable enough to ship, and forecast roughly when it can happen.

Common practice
5 steps
Used by Product Owner

What it is

Deciding which features or results go out in which release, and roughly when, based on value, capacity and dependencies.

When to use it

When the business needs to plan launches, marketing or support. Scrum itself allows releasing any time an Increment is valuable.

Why it works

It sets expectations for stakeholders and helps the team focus on a usable whole rather than scattered pieces.

Do

  • Release goals beat feature lists: they let you swap items without breaking the promise.

Don't

  • Waiting for “everything” before releasing.
  • Treating the forecast as a fixed promise.

Step by step

  1. Set the release goal What should users be able to do after it?
  2. Pick the items that serve the goal In order of value.
  3. Check capacity Use the team's pace or throughput.
  4. Check dependencies Other teams, suppliers, approvals.
  5. Set a target with a range Update as work progresses.
Also called: Release forecastPrint the blank template ↗

Worked example

The situation. A booking app's first release.

  1. Goal: customers can book and pay for a table.
  2. Items: search, book, pay, confirmation email.
  3. Pace: about 20 points a fortnight; about 6 weeks.

The result. Stakeholders knew what was coming and when, with the range updated every fortnight.

Release plan Print blank
ReleaseGoalItems includedTarget (range)Depen­dencies

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Product Owner uses it

v1.0 = shoppers can buy end to end. The burn-up shows it is likely after Sprint 2. Anna (Product Owner) releases then, not after all features.

Questions people ask

Fixed date or fixed scope?

Usually one is fixed and the other flexible; say which.