Estimation · cheat sheet

#NoEstimates

Split work into similar small items and forecast by counting how many get Done, instead of estimating each one.

Common practice
5 steps
Used by Product Owner

What it is

An approach where a team stops estimating each item and instead splits work into similar small pieces, then forecasts by counting how many pieces it finishes.

When to use it

With a stable team that already splits work small. Less useful when items vary a lot in size.

Why it works

If items are all small and similar, counting them predicts as well as estimating them, and saves the time spent estimating.

Do

  • It needs consistent splitting; it doesn't work with a mix of tiny and huge items.

Don't

  • Calling it “no planning”: it still needs a well-split, ordered backlog.

Step by step

  1. Split work into small, similar pieces Aim for items that each take a few days at most.
  2. Count what gets finished Track items finished per week.
  3. Forecast with ranges Use the history: at 6 to 9 items a week, 40 items take about 5 to 7 weeks.
  4. Keep splitting big things Anything that looks much bigger than usual gets split before it starts.
  5. Check the forecast often Update it every week as real data comes in.
Also called: Counting items, throughput forecastingPrint the blank template ↗

Worked example

The situation. A support team improving its help centre has 45 articles to rewrite.

  1. Each article is about the same size.
  2. They finish 8 to 11 a week.
  3. Forecast: 4 to 6 weeks.

The result. They finished in 5 weeks and never held an estimation meeting.

Throughput tracker Print blank
WeekItems finishedItems leftForecast weeks left (range)

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Product Owner uses it

By Sprint 3 every Basketly item is one to three days of work. The team finishes 4 to 6 items a Sprint, so Anna (Product Owner) forecasts the remaining 10 items as two to three Sprints.

Questions people ask

Does this mean no planning?

No. It replaces item-by-item estimates with counting and forecasting.