#NoEstimates
Split work into similar small items and forecast by counting how many get Done, instead of estimating each one.
What it is
An approach where a team stops estimating each item and instead splits work into similar small pieces, then forecasts by counting how many pieces it finishes.
When to use it
With a stable team that already splits work small. Less useful when items vary a lot in size.
Why it works
If items are all small and similar, counting them predicts as well as estimating them, and saves the time spent estimating.
Do
- It needs consistent splitting; it doesn't work with a mix of tiny and huge items.
Don't
- Calling it “no planning”: it still needs a well-split, ordered backlog.
Step by step
- Split work into small, similar pieces Aim for items that each take a few days at most.
- Count what gets finished Track items finished per week.
- Forecast with ranges Use the history: at 6 to 9 items a week, 40 items take about 5 to 7 weeks.
- Keep splitting big things Anything that looks much bigger than usual gets split before it starts.
- Check the forecast often Update it every week as real data comes in.