Story points
A unit for how big a piece of work is compared with other pieces, not how many hours it takes.
What it is
Story points measure how big a piece of work is compared with other pieces, not how many hours it takes. Size includes effort, complexity and uncertainty together.
A team picks a reference item, gives it a number, and sizes everything else relative to it.
When to use it
When the Developers want to compare the size of backlog items quickly and use their own history to forecast. Skip it if the team finds it creates more debate than value; the Scrum Guide doesn't require any estimation unit.
Why it works
People are poor at predicting hours but fairly good at comparing: “this is about twice that”. Relative sizes, combined with the team's own history, give more reliable forecasts than hour estimates.
Do
- Never turn points back into hours or use them as targets.
- Points aren't comparable between teams; each team's scale is its own.
Don't
- Turning points back into hours, or into a target.
- Comparing points between teams: each team's scale is its own.
- The Product Owner or a manager estimating for the Developers.
Step by step
- Choose a reference item A small, well-understood piece of work the whole team knows. Give it 2 or 3, so smaller items still fit below it.
- Use a coarse scale Often 1, 2, 3, 5, 8, 13. The growing gaps stop debates about tiny differences.
- Compare, don't calculate For each new item ask: about the same as the reference, twice as big, much bigger?
- Only the people doing the work estimate Others explain and answer questions.
- Track what gets finished The points of finished work per period become the team's own pace (velocity) for forecasting.
- Re-size when you learn If an item turns out much bigger, split it rather than changing history.