Music festival production45 questions5 phases

Stagecrew: a Scrum Master case study

A riverside music festival is three months away, and the date can't move. The production team plans stages, the festival app, signage and the visitor experience, while artists, sponsors and the city keep changing their minds. You're the Scrum Master, helping the team decide where short Sprints help, and where a fixed plan is simply the right tool.

What this case study tests
When Scrum fitsFixed datesSponsors vs visitorsSafety and pace

You're the Scrum Master. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Ari (Scrum Master)You
Athena (Product Owner)Festival experience lead
Angus (Developer)Stage and site production
Alina (Developer)Festival app and tickets
Amon (Developer)Signage and visitor flow
Stakeholders
Astra (Festival Director)Sponsor
Arlo (Sponsor Manager)The drinks brand
Adebayo (City Events Officer)Safety and permits
Anja (Festival-goer)Comes every year
Stagecrew

Getting started

A date that cannot move

Question 1 of 45

Choose 1
Astra (Festival Director)
The stage build is a fixed sequence with fixed suppliers. Do we really run it in Sprints?

What is a good answer?

Learn it on Day 1: A new team

Question 2 of 45

Choose 1
Athena (Product Owner)
With a fixed festival date, what's our Product Goal?

Which is the best Product Goal?

Learn it on Day 3: Coach the vision

Question 3 of 45

Choose 2
Angus (Developer)
So who decides what gets built first: Astra, the sponsors, or you?

Which two statements are true?

Learn it on Day 4: Transparency first

Question 4 of 45

Choose 1
Adebayo (City Events Officer)
Safety plans need city approval six weeks before the festival.

What do you do with this?

Learn it on Day 2: Who talks to whom

Question 5 of 45

Choose 1
Amon (Developer)
When is a sign really done?

What do you help the team agree?

Learn it on Day 5: Team agreements

Question 6 of 45

True or false
Astra (Festival Director)
Three months left. Should we use one-month Sprints?

True or false: shorter Sprints give more chances to inspect and adapt before the festival.

Learn it on Day 5: Team agreements

Question 7 of 45

Choose 1
Athena (Product Owner)
Can you write the Product Goal? Astra wants it by tonight.

What do you do?

Learn it on Day 3: Coach the vision

Question 8 of 45

Choose 1
Alina (Developer)
We all report to different managers. Are we one team?

What do you explain?

Learn it on Day 1: A new team

Question 9 of 45

Choose 1
Astra (Festival Director)
The date can't move, so let's make one full plan and stick to it.

Where does an empirical approach help?

Learn it on Day 16: Learning from real users

Question 10 of 45

Choose 1
Astra (Festival Director)
The app team, the sign makers and the site crew all work separately, and visitors still get lost.

What would help?

Learn it on Day 9: Let the team solve it
Stagecrew

Sprint 1

Goal: visitors can buy tickets and see the line-up in the app

Question 11 of 45

Choose 1
Astra (Festival Director)
Do tickets, the map, the line-up and food ordering this Sprint.

Who selects how much work fits in the Sprint?

Learn it on Day 6: Sprint 1 Planning

Question 12 of 45

Choose 1
Ari (Scrum Master)
Planning keeps sliding into artist gossip. It's hour three.

What do you do?

Learn it on Day 6: Sprint 1 Planning

Question 13 of 45

Choose 1
Angus (Developer)
At the Daily Scrum we each tell Athena what we did yesterday.

What do you coach?

Learn it on Day 7: The first impediment

Question 14 of 45

Choose 1
Alina (Developer)
The ticket supplier hasn't sent the API keys. A week now.

What do you do?

Learn it on Day 7: The first impediment

Question 15 of 45

Choose 1
Arlo (Sponsor Manager)
Our drinks logo must be on every screen of the app. This week.

What do you suggest?

Learn it on Day 8: Protect the Sprint

Question 16 of 45

Choose 1
Astra (Festival Director)
If the headliner cancels, I'll cancel the Sprint.

Who can cancel a Sprint?

Learn it on Day 8: Protect the Sprint

Question 17 of 45

Choose 1
Amon (Developer)
Alina wants to skip testing the map on a cheap phone.

What do you do?

Learn it on Day 9: Let the team solve it

Question 18 of 45

Choose 1
Astra (Festival Director)
At the Review I'll approve or reject each feature.

How do you set up the Sprint Review?

Learn it on Day 10: Review and Retrospective

Question 19 of 45

Choose 1
Angus (Developer)
Artists keep changing their set times. Is Sprint Planning even worth it?

What do you say?

Learn it on Day 6: Sprint 1 Planning
Stagecrew

Sprint 2

Goal: visitors find their way around the site

Question 20 of 45

Choose 1
Anja (Festival-goer)
(testing the map) I couldn't find the toilets. That's the only thing I care about.

What happens with this feedback?

Learn it on Day 10: Review and Retrospective

Question 21 of 45

Choose 1
Ari (Scrum Master)
In the Retrospective, everyone blames the artists for changing plans.

What do you do?

Learn it on Day 10: Review and Retrospective

Question 22 of 45

Choose 1
Amon (Developer)
Nobody here knows crowd-flow planning.

What do you encourage?

Learn it on Day 11: A skill the team lacks

Question 23 of 45

Choose 1
Astra (Festival Director)
(to Angus) Move the main stage 20 metres left. I like the view.

What do you do?

Learn it on Day 12: The CEO at the desk

Question 24 of 45

Choose 1
Alina (Developer)
“Visitors can find things.” Which things? On which screens?

How do you help?

Learn it on Day 13: Waiting for answers

Question 25 of 45

Choose 1
Arlo (Sponsor Manager)
Will the sponsor zone be in the app by the festival? Yes or no.

How do you help Athena (Product Owner) answer?

Learn it on Day 14: Dates and promises

Question 26 of 45

True or false
Alina (Developer)
The map is Done on Tuesday. Can visitors get it before the Review?

True or false: an Increment can be released before the end of the Sprint.

Learn it on Day 15: Is it really done?

Question 27 of 45

Choose 1
Angus (Developer)
Our Daily Scrum on site takes 40 minutes; we end up solving rigging problems.

What do you suggest?

Learn it on Day 13: Waiting for answers

Question 28 of 45

Choose 1
Alina (Developer)
“Visitors order food without queuing” sounds like a whole app on its own.

How should the team refine it?

Learn it on Day 4: Transparency first
Stagecrew

Sprint 3

Goal: visitors order food without queuing

Question 29 of 45

Choose 1
Arlo (Sponsor Manager)
Measure the app by number of downloads.

What do you suggest instead?

Learn it on Day 16: Learning from real users

Question 30 of 45

Choose 1
Adebayo (City Events Officer)
Food stalls need both fire safety and health permits. Each office waits for the other.

What do you do?

Learn it on Day 17: A blocker above the team

Question 31 of 45

Choose 1
Ari (Scrum Master)
Every year the same permit tangle happens.

What do you do after this one is solved?

Learn it on Day 17: A blocker above the team

Question 32 of 45

Choose 1
Arlo (Sponsor Manager)
Athena moved my bar away from the main stage. Ari, get it moved back.

What do you do?

Learn it on Day 18: Facilitating a clash

Question 33 of 45

Choose 1
Alina (Developer)
We hard-coded the food menus to go faster. Every change now needs a new app release.

What do you advise?

Learn it on Day 19: Making debt visible

Question 34 of 45

Choose 2
Amon (Developer)
Add “checked by a wheelchair user” to our Definition of Done?

Which two statements are true?

Learn it on Day 19: Making debt visible

Question 35 of 45

Choose 1
Angus (Developer)
Amon keeps moving signs onto my cable routes!

The Retrospective gets heated. What do you do?

Learn it on Day 20: Conflict in the Retro

Question 36 of 45

True or false
Athena (Product Owner)
Do I belong in the Retrospective?

True or false: the Product Owner takes part in the Sprint Retrospective.

Learn it on Day 20: Conflict in the Retro

Question 37 of 45

Choose 1
Amon (Developer)
Three sponsors want their logos added this week. We're about to miss our Sprint Goal.

How do you help the team?

Learn it on Day 12: The CEO at the desk
Stagecrew

Festival week and beyond

Goal: a safe, easy weekend for 20,000 visitors

Question 38 of 45

Choose 1
Astra (Festival Director)
Festival week: everyone works 16-hour days.

What do you and Athena (Product Owner) say?

Learn it on Day 22: Sustainable pace

Question 39 of 45

Choose 1
Astra (Festival Director)
Our winter market should use Scrum too. Send them your board.

What do you advise?

Learn it on Day 23: Scrum beyond the team

Question 40 of 45

Choose 1
Alina (Developer)
Food ordering works, but payments fail on one phone brand. Gates open tomorrow.

What happens to food ordering?

Learn it on Day 24: Hold the line on Done

Question 41 of 45

Choose 1
Angus (Developer)
We all agree a plan in the meeting, then everyone does something different.

What do you introduce?

Learn it on Day 13: Waiting for answers

Technique: Kanban board

Question 42 of 45

Choose 1
Athena (Product Owner)
The sponsor, the city and the director each pull us in different directions.

How do you help Athena (Product Owner)?

Learn it on Day 2: Who talks to whom

Technique: Stakeholder map (power and interest)

Question 43 of 45

True or false
Arlo (Sponsor Manager)
Can I join your Daily Scrum during festival week to keep an eye on the sponsor zone?

True or false: the Daily Scrum is an event for the Developers.

Learn it on Day 7: The first impediment

Question 44 of 45

Choose 1
Alina (Developer)
Ticket sync failed again during the test. Third time.

What do you facilitate?

Learn it on Day 17: A blocker above the team

Technique: 5 Whys

Question 45 of 45

Choose 1
Athena (Product Owner)
Did Scrum fit everything we did?

Which statement is true?

Learn it on Day 1: A new team