Music festival production 45 questions 5 phases
Stagecrew: a Scrum Master case study A riverside music festival is three months away, and the date can't move. The production team plans stages, the festival app, signage and the visitor experience, while artists, sponsors and the city keep changing their minds. You're the Scrum Master, helping the team decide where short Sprints help, and where a fixed plan is simply the right tool.
What this case study tests
When Scrum fits Fixed dates Sponsors vs visitors Safety and pace
You're the Scrum Master. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Athena (Product Owner) Festival experience lead Angus (Developer) Stage and site production Alina (Developer) Festival app and tickets Amon (Developer) Signage and visitor flow Stakeholders
Astra (Festival Director) Sponsor Arlo (Sponsor Manager) The drinks brand Adebayo (City Events Officer) Safety and permits Anja (Festival-goer) Comes every year Stagecrew
Getting started A date that cannot move
Question 1 of 45 Choose 1
Astra (Festival Director) The stage build is a fixed sequence with fixed suppliers. Do we really run it in Sprints?
What is a good answer? Run everything in Sprints, stage build included, or it isn't really Scrum Incorrect. Scrum fits complex work; it doesn't replace every plan in an organisation.Use Sprints for the uncertain work, and a plan where it's predictable Correct. Right. Scrum is for complex work; some parts of a festival are simply a known sequence.Scrum can't help a festival at all, since the date is fixed Incorrect. The visitor experience is full of uncertainty Scrum handles well.
Learn it on Day 1: A new team
Check answer
Question 2 of 45 Choose 1
Athena (Product Owner) With a fixed festival date, what's our Product Goal?
Which is the best Product Goal? “Visitors move easily, find things, and feel safe all weekend.” Correct. Right. It describes a future state and guides choices.“Build the stages, the app and all the signs on time, to budget.” Incorrect. That's a list of work, not a goal.“Be the best riverside festival the city has ever had.” Incorrect. Too vague to guide decisions.
Learn it on Day 3: Coach the vision
Check answer
Question 3 of 45 Choose 2
Angus (Developer) So who decides what gets built first: Astra, the sponsors, or you?
Which two statements are true? Athena (Product Owner) orders the Product Backlog Correct. Correct.Sponsors order the parts of it that they pay for Incorrect. They can try to convince the Product Owner.The organisation respects the Product Owner's decisions Correct. Correct.The Scrum Master breaks any ties between people Incorrect. You facilitate; the Product Owner decides.
Learn it on Day 4: Transparency first
Check answer
Question 4 of 45 Choose 1
Adebayo (City Events Officer) Safety plans need city approval six weeks before the festival.
What do you do with this? Leave the deadline until the last month, when plans are firm Incorrect. Then it's too late.Skip the city's approval and hope it's not checked on the day Incorrect. Illegal and unsafe.Make the deadline visible to Athena and the team now Correct. Right. Spot constraints early.
Learn it on Day 2: Who talks to whom
Check answer
Question 5 of 45 Choose 1
Amon (Developer) When is a sign really done?
What do you help the team agree? Done when the sign has been printed and put up Incorrect. Printed isn't tested.Done when Amon, who designed the sign, is happy with it Incorrect. Quality must be shared.A Definition of Done: walk-tested, readable, safe Correct. Right.
Learn it on Day 5: Team agreements
Check answer
Question 6 of 45 True or false
Astra (Festival Director) Three months left. Should we use one-month Sprints?
True or false: shorter Sprints give more chances to inspect and adapt before the festival. True Correct. Correct. With little time, one- or two-week Sprints give more learning cycles.False Incorrect. More Sprints mean more feedback.
Learn it on Day 5: Team agreements
Check answer
Question 7 of 45 Choose 1
Athena (Product Owner) Can you write the Product Goal? Astra wants it by tonight.
What do you do? Facilitate a short session so Athena can shape and own it Correct. Right.Write the goal for her tonight, since she's so busy Incorrect. The Product Goal is the Product Owner's accountability.Let the festival director write it for the team herself Incorrect. The Product Owner develops it.
Learn it on Day 3: Coach the vision
Check answer
Question 8 of 45 Choose 1
Alina (Developer) We all report to different managers. Are we one team?
What do you explain? Each person follows their own manager's plan for it Incorrect. Then there's no shared goal.No hierarchy: one shared goal, decided together Correct. Right.The Scrum Master acts as the team's line manager Incorrect. You serve the team; you don't manage it.
Learn it on Day 1: A new team
Check answer
Question 9 of 45 Choose 1
Astra (Festival Director) The date can't move, so let's make one full plan and stick to it.
Where does an empirical approach help? A fixed plan for what's certain, Sprints for what changes Correct. Right. Use a fixed plan for the date, stages and permits, and short Sprints with transparent progress for the app and visitor experience, so the team learns and adjusts empirically.One fixed plan for everything, from start to finish Incorrect. Changing artist and sponsor demands will break it.Sprints for everything, including the permits and stages Incorrect. Some work is simply fixed and suits a plan.
Learn it on Day 16: Learning from real users
Check answer
Question 10 of 45 Choose 1
Astra (Festival Director) The app team, the sign makers and the site crew all work separately, and visitors still get lost.
What would help? Keep the teams separate, and add more meetings between them Incorrect. Meetings don't fix split ownership.One team around the visitor's journey, all skills together Correct. Right. A cross-functional team with app, signage and site people together makes wayfinding work as one; visitors experience the whole journey, not each team's part.Let the app team decide everything about wayfinding Incorrect. Signs and site layout matter just as much.
Learn it on Day 9: Let the team solve it
Check answer
Stagecrew
Sprint 1 Goal: visitors can buy tickets and see the line-up in the app
Question 11 of 45 Choose 1
Astra (Festival Director) Do tickets, the map, the line-up and food ordering this Sprint.
Who selects how much work fits in the Sprint? The Developers, after Athena explains the value Correct. Right.The Festival Director, who runs the whole festival Incorrect. Stakeholders share needs.The main sponsor, who pays for a large part of it Incorrect. Not in the Scrum Team.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 12 of 45 Choose 1
Ari (Scrum Master) Planning keeps sliding into artist gossip. It's hour three.
What do you do? Let it run on: people enjoy the discussion, and it bonds them Incorrect. Events are timeboxed.Draw up the plan yourself afterwards and send it round Incorrect. Then it isn't theirs.Hold the timebox and help them agree a goal and a start Correct. Right.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 13 of 45 Choose 1
Angus (Developer) At the Daily Scrum we each tell Athena what we did yesterday.
What do you coach? That's fine: the Product Owner needs the daily updates Incorrect. It turns into a status meeting.It's for the Developers to plan together toward the goal Correct. Right. Not a report to the Product Owner.Stop having it, since Athena gets updates anyway Incorrect. The team still needs to plan daily.
Learn it on Day 7: The first impediment
Check answer
Question 14 of 45 Choose 1
Alina (Developer) The ticket supplier hasn't sent the API keys. A week now.
What do you do? Build a ticket system from scratch to stop waiting Incorrect. Not your call, and huge.Chase the supplier with Athena, and agree a date Correct. Right. You cause the removal of impediments.Wait for the supplier to come back with a date Incorrect. The Sprint suffers.
Learn it on Day 7: The first impediment
Check answer
Question 15 of 45 Choose 1
Arlo (Sponsor Manager) Our drinks logo must be on every screen of the app. This week.
What do you suggest? Bring it to Athena, who can weigh it in the backlog Correct. Right.Alina (Developer) adds it quietly to the Sprint Incorrect. That bypasses the Product Owner.Tell him sponsors have no say at all in the festival app Incorrect. They can try to convince the Product Owner.
Learn it on Day 8: Protect the Sprint
Check answer
Question 16 of 45 Choose 1
Astra (Festival Director) If the headliner cancels, I'll cancel the Sprint.
Who can cancel a Sprint? The Festival Director, who runs the whole event Incorrect. She can inform the decision.The headline artist's agent, who sets the dates Incorrect. Not in the Scrum Team.Only Athena, as Product Owner, if the goal's obsolete Correct. Correct.
Learn it on Day 8: Protect the Sprint
Check answer
Question 17 of 45 Choose 1
Amon (Developer) Alina wants to skip testing the map on a cheap phone.
What do you do? Let it go: most visitors have new phones anyway, these days Incorrect. Many don't.Test it yourself on an old phone later on, to save time Incorrect. Not your role.Back Amon: if it's in the Definition of Done, it's needed Correct. Right.
Learn it on Day 9: Let the team solve it
Check answer
Question 18 of 45 Choose 1
Astra (Festival Director) At the Review I'll approve or reject each feature.
How do you set up the Sprint Review? A working session where stakeholders use the app Correct. Right.A formal sign-off of each feature by the festival director Incorrect. Not a gate.Skip it this time, since time before the festival is short Incorrect. With little time, feedback matters more.
Learn it on Day 10: Review and Retrospective
Check answer
Question 19 of 45 Choose 1
Angus (Developer) Artists keep changing their set times. Is Sprint Planning even worth it?
What do you say? No: plan once a month instead, to save everyone time Incorrect. Longer cycles mean slower reactions.Hold Sprint Planning every day, as things keep changing so fast Incorrect. The Daily Scrum adjusts the plan; Sprint Planning sets the goal.Yes: it sets a short goal; changes go to the next Sprint Correct. Right. Sprint Planning sets a goal for a short period; plan what's known now and keep items small. Short Sprints are how you plan when things keep changing.
Learn it on Day 6: Sprint 1 Planning
Check answer
Stagecrew
Sprint 2 Goal: visitors find their way around the site
Question 20 of 45 Choose 1
Anja (Festival-goer) (testing the map) I couldn't find the toilets. That's the only thing I care about.
What happens with this feedback? Keep it for next year's festival planning Incorrect. Use it now.Athena uses it to adapt the Product Backlog Correct. Right.Ignore it: testers always complain about something Incorrect. Real users show what matters.
Learn it on Day 10: Review and Retrospective
Check answer
Question 21 of 45 Choose 1
Ari (Scrum Master) In the Retrospective, everyone blames the artists for changing plans.
What do you do? Help them see what they control and pick one change Correct. Right.Agree with them, and finish the meeting early to save time Incorrect. Nothing changes.Invite the artists in to explain themselves to the team Incorrect. It's the Scrum Team's event.
Learn it on Day 10: Review and Retrospective
Check answer
Question 22 of 45 Choose 1
Amon (Developer) Nobody here knows crowd-flow planning.
What do you encourage? Guess the crowd numbers from last year's ticket sales Incorrect. Unsafe.Hand all the crowd planning over to the city Incorrect. The team stays dependent.Pair with the city's crowd-safety expert to learn Correct. Right.
Learn it on Day 11: A skill the team lacks
Check answer
Question 23 of 45 Choose 1
Astra (Festival Director) (to Angus) Move the main stage 20 metres left. I like the view.
What do you do? Angus moves it: she's the festival director Incorrect. That bypasses the Product Owner and maybe safety.Thank her and suggest she brings it to Athena Correct. Right.Tell her to stay away from the crew's work on site Incorrect. Collaboration is fine.
Learn it on Day 12: The CEO at the desk
Check answer
Question 24 of 45 Choose 1
Alina (Developer) “Visitors can find things.” Which things? On which screens?
How do you help? Write the items yourself tonight, to save everyone time Incorrect. Not your accountability.Help the team and Athena make items clear together Correct. Right.Let Alina guess what's meant and adjust later Incorrect. Rework.
Learn it on Day 13: Waiting for answers
Check answer
Question 25 of 45 Choose 1
Arlo (Sponsor Manager) Will the sponsor zone be in the app by the festival? Yes or no.
How do you help Athena (Product Owner) answer? Forecast a range from what's finished, with risks Correct. Right.Promise yes, so the sponsor can relax and plan the zone Incorrect. A promise without evidence.Refuse to answer until all of the sponsor work is done Incorrect. Sponsors need to plan.
Learn it on Day 14: Dates and promises
Check answer
Question 26 of 45 True or false
Alina (Developer) The map is Done on Tuesday. Can visitors get it before the Review?
True or false: an Increment can be released before the end of the Sprint. True Correct. Correct.False Incorrect. The Review isn't a release gate.
Learn it on Day 15: Is it really done?
Check answer
Question 27 of 45 Choose 1
Angus (Developer) Our Daily Scrum on site takes 40 minutes; we end up solving rigging problems.
What do you suggest? Make it longer, so the rigging talk fits in Incorrect. Not its purpose.Drop it entirely during the busy site build Incorrect. That's when coordination matters most.Keep it to 15 minutes; rigging talk happens after Correct. Right.
Learn it on Day 13: Waiting for answers
Check answer
Question 28 of 45 Choose 1
Alina (Developer) “Visitors order food without queuing” sounds like a whole app on its own.
How should the team refine it? Refine it into a small first test at one food stand Correct. Right. Refinement into a small first step, such as pre-ordering at one stand, lets the team learn before a big build; it suits a date that can't move.Build the full ordering app for every stall now Incorrect. It may not be ready, or wanted, in time.Drop it from the festival this year, to save effort Incorrect. It may be valuable; test it small first.
Learn it on Day 4: Transparency first
Check answer
Stagecrew
Sprint 3 Goal: visitors order food without queuing
Question 29 of 45 Choose 1
Arlo (Sponsor Manager) Measure the app by number of downloads.
What do you suggest instead? Hours worked by the team each week on the app Incorrect. Not value.Number of features released in the app each Sprint Incorrect. Output, not value.Outcomes: queue times, and visitor satisfaction Correct. Right.
Learn it on Day 16: Learning from real users
Check answer
Question 30 of 45 Choose 1
Adebayo (City Events Officer) Food stalls need both fire safety and health permits. Each office waits for the other.
What do you do? Bring both offices and Athena together on it Correct. Right.Open the stalls anyway and sort the permit later Incorrect. Unsafe and illegal.Wait for the two offices to agree on their own Incorrect. The festival date won't.
Learn it on Day 17: A blocker above the team
Check answer
Question 31 of 45 Choose 1
Ari (Scrum Master) Every year the same permit tangle happens.
What do you do after this one is solved? Nothing more: this permit is solved, so move on Incorrect. It will return.Work with the city on a combined permit route Correct. Right. Fix the cause.Complain to the press about the city's delays Incorrect. Damages the relationship.
Learn it on Day 17: A blocker above the team
Check answer
Question 32 of 45 Choose 1
Arlo (Sponsor Manager) Athena moved my bar away from the main stage. Ari, get it moved back.
What do you do? Stay neutral and help Arlo explain the value to Athena Correct. Right.Get the stage moved back, since the sponsor pays Incorrect. That undermines the Product Owner.Tell him sponsors don't decide the festival layout Incorrect. They're important stakeholders.
Learn it on Day 18: Facilitating a clash
Check answer
Question 33 of 45 Choose 1
Alina (Developer) We hard-coded the food menus to go faster. Every change now needs a new app release.
What do you advise? Hide it until after the festival is over, then fix it Incorrect. Menus will change during it.Blame the fixed deadline, and move on to the next item Incorrect. Blame doesn't fix it.Make the debt and its cost visible to Athena Correct. Right.
Learn it on Day 19: Making debt visible
Check answer
Question 34 of 45 Choose 2
Amon (Developer) Add “checked by a wheelchair user” to our Definition of Done?
Which two statements are true? The team can make its Definition of Done stronger Correct. Correct.This is a good one to decide in the Retrospective Correct. Correct.Only Astra can change it, as the director Incorrect. It belongs to the Scrum Team.It can't change this close to the festival Incorrect. It can change whenever the team learns.
Learn it on Day 19: Making debt visible
Check answer
Question 35 of 45 Choose 1
Angus (Developer) Amon keeps moving signs onto my cable routes!
The Retrospective gets heated. What do you do? Take Angus's side: his job is the bigger one Incorrect. Taking sides blocks resolution.Keep it about the cable routes, and agree a rule Correct. Right.Avoid the topic and move on quickly to the next Incorrect. It grows.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 36 of 45 True or false
Athena (Product Owner) Do I belong in the Retrospective?
Question 37 of 45 Choose 1
Amon (Developer) Three sponsors want their logos added this week. We're about to miss our Sprint Goal.
How do you help the team? Do everything by working nights all this week Incorrect. Unsustainable, and mistakes follow.Keep focus on the goal; raise requests with Athena Correct. Right. The team keeps its focus on the Sprint Goal and discusses the requests with openness; its commitment is to the goal, and Athena decides what waits.Ignore the sponsors until after the festival is over Incorrect. They matter; their requests go through the Product Owner.
Learn it on Day 12: The CEO at the desk
Check answer
Stagecrew
Festival week and beyond Goal: a safe, easy weekend for 20,000 visitors
Question 38 of 45 Choose 1
Astra (Festival Director) Festival week: everyone works 16-hour days.
What do you and Athena (Product Owner) say? Everyone works 16-hour days until it's all done, just this week Incorrect. Fatigue is a safety risk.Agree sustainable shifts; decide with Athena what drops Correct. Right. Exhausted crews cause accidents.Refuse to talk about any longer shifts at all, on principle Incorrect. Find a workable plan together.
Learn it on Day 22: Sustainable pace
Check answer
Question 39 of 45 Choose 1
Astra (Festival Director) Our winter market should use Scrum too. Send them your board.
What do you advise? Meet them, and explain where Scrum helps and doesn't Correct. Right.Send them the board and the team's rules to copy Incorrect. Copying forms doesn't copy understanding.Say Scrum only really works for festival production Incorrect. It works for complex work.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 40 of 45 Choose 1
Alina (Developer) Food ordering works, but payments fail on one phone brand. Gates open tomorrow.
What happens to food ordering? Release it: few visitors have that phone Incorrect. Undone work isn't released.Pull the whole app until that part is fixed Incorrect. The rest is Done and valuable.It isn't Done; Athena decides what goes live Correct. Right. Only Done work is released.
Learn it on Day 24: Hold the line on Done
Check answer
Question 41 of 45 Choose 1
Angus (Developer) We all agree a plan in the meeting, then everyone does something different.
What do you introduce? Longer meetings, so everyone is fully in the loop Incorrect. The problem isn't meeting length.A crew boss who assigns everyone's tasks Incorrect. The Developers self-manage.A visible board for the crew's work, used daily Correct. Right. Seeing the work makes coordination real.
Learn it on Day 13: Waiting for answers Technique: Kanban board
Check answer
Question 42 of 45 Choose 1
Athena (Product Owner) The sponsor, the city and the director each pull us in different directions.
How do you help Athena (Product Owner)? Offer a stakeholder map and help her plan engagement Correct. Right. You serve the Product Owner with techniques; she decides.Handle all the stakeholders for her yourself, from now on Incorrect. That takes over her accountability.Tell her to ignore the sponsor's requests this year Incorrect. Sponsors matter; they just go through her.
Learn it on Day 2: Who talks to whom Technique: Stakeholder map (power and interest)
Check answer
Question 43 of 45 True or false
Arlo (Sponsor Manager) Can I join your Daily Scrum during festival week to keep an eye on the sponsor zone?
True or false: the Daily Scrum is an event for the Developers. True Correct. Correct. Stakeholders see progress in the Sprint Backlog and the Sprint Review.False Incorrect. It's the Developers' daily planning event.
Learn it on Day 7: The first impediment
Check answer
Question 44 of 45 Choose 1
Alina (Developer) Ticket sync failed again during the test. Third time.
What do you facilitate? Blame the ticket supplier and ask for a refund Incorrect. Blame skips the part you can fix.5 Whys with the team until a process cause appears Correct. Right. Why failed? Supplier changed their API. Why unnoticed? No check before each test. Fix: an automatic check.Restart the system and hope it holds this time Incorrect. Hope isn't a fix.
Learn it on Day 17: A blocker above the team Technique: 5 Whys
Check answer
Question 45 of 45 Choose 1
Athena (Product Owner) Did Scrum fit everything we did?
Which statement is true? Scrum helped where things were uncertain; plans did the rest Correct. Right. Use the right tool for each kind of work.Scrum should replace every single plan next time round Incorrect. Not for predictable sequences.Scrum didn't help at all, given the fixed festival date Incorrect. The visitor experience improved every Sprint.
Learn it on Day 1: A new team
Check answer