Protect the Sprint
A stakeholder goes around the Product Owner, and you use a calm moment to coach about Sprint cancellation.
Sprint Goal: Shoppers can sign in, find products and fill a cart.
Team
Aaron (Scrum Master) Adrian (Developer)
Stakeholders
Amelia (Marketing Lead)
How the day goes
- 09:00Daily Scrum
- 11:00Amelia (Marketing) finds you
- 15:00Support refinement
Situation 1 of 3
11:00 · Amelia (Marketing) finds youAmelia (Marketing Lead)
Aaron, quick one: can the team add a summer campaign banner this week? It's small! Anna (Product Owner) is in a meeting.
What do you do?
During the Sprint, nothing is added that endangers the Sprint Goal. New requests go to the Product Owner and the Product Backlog.
Situation 2 of 3
15:00 · Support refinementAaron (Scrum Master)
Quick coaching question: what if Adam (CEO) dropped grocery delivery tomorrow, and our Sprint Goal made no sense any more?
Anna (Product Owner) asks you who would decide. What is the answer?
Only the Product Owner can cancel a Sprint, and only if the Sprint Goal becomes obsolete.
Situation 3 of 3
15:00 · Support refinementAdrian (Developer)
Refinement keeps running over. We spent an hour arguing about button colours.
How do you help?
Help refinement stay focused on making the next items ready. The Guide doesn't timebox it; teams often do (Common practice).
Rules and common practice
The rules behind today. Scrum Guide official rules · Agile Manifesto the values behind them · EBM Guide measuring value · Common practice not in the Guide, but widely used.
Scrum Guide
During the Sprint
- No changes are made that would endanger the Sprint Goal. Quality does not decrease.
- Scope may be clarified and renegotiated with the Product Owner as more is learned.
Scrum Guide
Cancelling a Sprint
- A Sprint could be cancelled if the Sprint Goal becomes obsolete.
- Only the Product Owner has the authority to cancel the Sprint.
Scrum Guide
Refinement
- An ongoing activity to add details, such as a description, order and size. Its attributes often vary with the domain of work.
Common practice
Timeboxing refinement
- The Guide gives refinement no timebox. Many teams keep a regular, limited slot so it stays focused.
Sources: The Scrum Guide (November 2020), Ken Schwaber & Jeff Sutherland, CC BY-SA 4.0 · All sources
Day 8 complete
3 situations today.
Your responsibility todayProtecting the Sprint Goal
Technique you usedRedirecting requests, coaching questions
Key points to remember
- During the Sprint, nothing is added that endangers the Sprint Goal. New requests go to the Product Owner and the Product Backlog.
- Only the Product Owner can cancel a Sprint, and only if the Sprint Goal becomes obsolete.
- Help refinement stay focused on making the next items ready. The Guide doesn't timebox it; teams often do (Common practice).