Day 6 of 25Week 1 · Sprint 1MondaySprint

Sprint 1 Planning

Facilitate the first Sprint Planning: a Sprint Goal, a realistic forecast, and an event that ends on time.

Sprint Goal: Shoppers can sign in, find products and fill a cart.
Team
Aaron (Scrum Master) Anna (Product Owner)
Stakeholders
Adam (CEO)
Same day, other role: see Day 6 as the Product Owner (Sprint 1 Planning) →
Techniques today Timeboxing
Documents today Sprint Backlog
How the day goes
  1. 08:30Prepare the room and the timebox
  2. 09:00Facilitate Sprint Planning; Adam (CEO) looks in
  3. 12:00Check the plan is the team's own

Situation 1 of 3

09:00 · Facilitate Sprint Planning; Adam (CEO) looks in
Adam (CEO)product sponsor
Aaron, push them a bit. If you set the target at login, browse, cart AND checkout, they'll rise to it.

What do you tell Adam (CEO)?

The Developers choose how much work fits in the Sprint. Pressure from outside doesn't change their capacity.

Situation 2 of 3

12:00 · Check the plan is the team's own
Aaron (Scrum Master)
We're three hours into Sprint Planning and still debating. People are getting tired.

The timebox for a one-week Sprint is about two hours. What do you do?

Sprint Planning is timeboxed (up to eight hours for a one-month Sprint, usually less for shorter ones). Keeping the timebox is part of your job.

Situation 3 of 3

12:00 · Check the plan is the team's own
Anna (Product Owner)
The team chose login, browse and add-to-cart. Do we really need a Sprint Goal on top of the list?

What do you say to Anna (Product Owner)?

Every Sprint has one Sprint Goal, created by the whole Scrum Team. It is the commitment for the Sprint Backlog.

Rules and common practice

The rules behind today. Scrum Guide official rules · Agile Manifesto the values behind them · EBM Guide measuring value · Common practice not in the Guide, but widely used.

Scrum Guide

Sprint Planning

  • Three topics: why is this Sprint valuable, what can be Done this Sprint, and how will the chosen work get done.
  • Timeboxed to a maximum of eight hours for a one-month Sprint; usually shorter for shorter Sprints.
Scrum Guide

The Sprint Goal

  • The single objective for the Sprint, created by the whole Scrum Team. The commitment for the Sprint Backlog.
  • It gives flexibility in the exact work needed to achieve it.
Scrum Guide

Who chooses how much

  • The Developers select items from the Product Backlog to include in the Sprint.
  • The more they know about their past performance, capacity and Definition of Done, the more confident their forecast.
Scrum Guide

Events within the timebox

  • The Scrum Master ensures all Scrum events take place and are positive, productive and kept within the timebox.

Sources: The Scrum Guide (November 2020), Ken Schwaber & Jeff Sutherland, CC BY-SA 4.0 · All sources

Day 6 complete

3 situations today.

Your responsibility todayEnsuring events are productive and timeboxed
Technique you usedTimeboxing, facilitating the Sprint Goal
Key points to remember
  • The Developers choose how much work fits in the Sprint. Pressure from outside doesn't change their capacity.
  • Sprint Planning is timeboxed (up to eight hours for a one-month Sprint, usually less for shorter ones). Keeping the timebox is part of your job.
  • Every Sprint has one Sprint Goal, created by the whole Scrum Team. It is the commitment for the Sprint Backlog.