City bike-sharing launch 43 questions 5 phases
Spokeshare: a Scrum Master case study Spokeshare is launching 300 shared bikes across the city. The team includes a mechanic, a logistics planner and a designer, and none of them has heard of Scrum. Docking stations need city permits, bikes arrive from a supplier on another continent, and the mayor has announced a launch date. You're the Scrum Master.
What this case study tests
Increments without software Supplier delays Safety in the DoD City barriers
You're the Scrum Master. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Akira (Product Owner) Runs the service for the operator Andrzej (Developer) Mechanic, bikes and docks Aisling (Developer) Logistics and station planning Antoine (Developer) Designer: signs, stations and the rider app Stakeholders
Alessia (Managing Director) Sponsor Abraham (City Transport Officer) Permits for stations Arturo (Supplier Account Manager) Bikes and spare parts Aoife (Commuter) Test rider Spokeshare
Getting started Scrum without software
Question 1 of 43 True or false
Andrzej (Developer) I fix bikes. Isn't Scrum for programmers?
True or false: Scrum can only be used for software. True Incorrect. Scrum is a framework for complex work of any kind.False Correct. Correct. It helps teams create value in complex work, including physical products and services.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 2 of 43 Choose 1
Alessia (Managing Director) The mayor announced launch on 1 June. Plan every station and every bike until then.
What do you explain to Alessia (Managing Director)? Scrum can't work with a fixed date, so drop the date Incorrect. A fixed date is a constraint; Scrum helps deliver the most value before it.Keep the date fixed, but plan in Sprints and adapt Correct. Right. Empiricism: plan, inspect real results, adapt.Promise everything will be ready on the launch day Incorrect. A promise without evidence becomes a broken promise.
Learn it on Day 3: Coach the vision
Check answer
Question 3 of 43 Choose 1
Akira (Product Owner) What's an Increment when we build bike stations, not software?
Which answer fits best? A usable step, like a working station real riders can use Correct. Right. An Increment must be usable.Only the full city-wide launch counts as an Increment here Incorrect. That gives no feedback until the end.A detailed document describing all the planned stations Incorrect. Documents aren't usable value for riders.
Learn it on Day 15: Is it really done?
Check answer
Question 4 of 43 Choose 2
Aisling (Developer) We all work in different departments. Are we really one team?
Which two statements are true? It's cross-functional, with the skills to create value Correct. Correct.Each person reports to their department head for the work Incorrect. Within the Scrum Team there is no hierarchy.It's self-managing: it decides who does what and how Correct. Correct.The mechanic should only ever do mechanic tasks Incorrect. Specialists are welcome, but the team shares one goal.
Learn it on Day 1: A new team
Check answer
Question 5 of 43 Choose 1
Abraham (City Transport Officer) Each station permit takes eight weeks. No exceptions.
What do you do? Start building now, without waiting for permits Incorrect. That breaks the law and the trust of the city.Ignore it until the first station is actually ready Incorrect. Then it blocks the team for eight weeks.Make the lead time visible and talk with the city Correct. Right. Spot impediments early and build a working relationship with the people involved.
Learn it on Day 2: Who talks to whom
Check answer
Question 6 of 43 Choose 1
Andrzej (Developer) What does “Done” mean for a station?
What do you help the team agree? Done when the mechanic says the station is ready to use Incorrect. Quality must be shared and transparent.Done when the bikes have arrived and been unpacked from the supplier Incorrect. Arriving isn't usable.A Definition of Done: installed, safety checked, rider-tested Correct. Right. It makes “done” the same for everyone.
Learn it on Day 5: Team agreements
Check answer
Question 7 of 43 Choose 1
Akira (Product Owner) Can you write our Product Goal? I'm not a writer.
What do you do? Facilitate a session; Akira develops and owns the goal Correct. Right.Write the goal for him, as he's new to the Product Owner role Incorrect. The Product Goal is the Product Owner's accountability.Copy another city's bike-share goal, word for word Incorrect. It should fit this product.
Learn it on Day 3: Coach the vision
Check answer
Question 8 of 43 Choose 1
Alessia (Managing Director) Sprints of one month seem long for us. Can they be shorter?
Which statement is true? Sprints must be exactly one month long, never shorter Incorrect. One month is the maximum.Sprints are a month or less; shorter ones teach faster Correct. Correct.Sprints can be any length the team wants, even a quarter Incorrect. They're one month or less, and fixed.
Learn it on Day 5: Team agreements
Check answer
Spokeshare
Sprint 1 Goal: one pilot station works for ten test riders
Question 9 of 43 Choose 1
Alessia (Managing Director) Build five pilot stations this Sprint, not one.
Who selects how much work fits in the Sprint? The Developers, after discussing value with Akira Correct. Right. A forecast the team believes in.Alessia (Managing Director), as the sponsor of the work Incorrect. Stakeholders don't set the workload.The supplier, who knows when the bikes will be delivered Incorrect. Not in the Scrum Team.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 10 of 43 Choose 1
Aisling (Developer) I'll just tell everyone what to do each morning, it's faster.
What do you coach? Let her do it: she's the managing director here Incorrect. One person directing others isn't self-management.The Scrum Master should give the day's instructions Incorrect. You don't assign work.The Developers plan the next day together, as a team Correct. Right. It's their event.
Learn it on Day 7: The first impediment
Check answer
Question 11 of 43 Choose 1
Arturo (Supplier Account Manager) The pilot bikes are stuck in customs. Two weeks, maybe three.
What do you do? Tell the team to wait until the bikes clear customs Incorrect. Waiting wastes the Sprint.Work with the supplier and Akira to find what customs needs Correct. Right. You cause the removal of impediments.Buy some bikes from a local shop, to keep the Sprint going Incorrect. Not your decision, and maybe against the contract.
Learn it on Day 7: The first impediment
Check answer
Question 12 of 43 Choose 2
Andrzej (Developer) While we wait for bikes, what do we even do?
Which two ideas fit? The Developers adapt their plan, testing with a borrowed bike Correct. Correct. The Sprint Backlog can change; the Sprint Goal stays.Stop working on the station until the bikes arrive Incorrect. The team can still move toward the Sprint Goal.Talk with Akira (Product Owner) if the goal is at risk Correct. Correct. Scope can be renegotiated with the Product Owner.Change the Sprint Goal quietly, without telling anyone Incorrect. That breaks transparency.
Learn it on Day 7: The first impediment
Check answer
Question 13 of 43 Choose 1
Alessia (Managing Director) Can the team also design the mayor's launch poster this week?
What do you suggest? Ask Antoine (Developer) to squeeze it in this week Incorrect. That bypasses the Product Owner.Bring it to Akira to weigh in the Product Backlog Correct. Right. New work goes through the Product Owner.Refuse all requests from the director during Sprints Incorrect. Requests are fine; the Product Owner decides.
Learn it on Day 8: Protect the Sprint
Check answer
Question 14 of 43 True or false
Abraham (City Transport Officer) If the city changes the station rules, will you cancel the Sprint?
True or false: only the Product Owner can cancel a Sprint. True Correct. Correct, if the Sprint Goal becomes obsolete.False Incorrect. Only the Product Owner has that authority.
Learn it on Day 8: Protect the Sprint
Check answer
Question 15 of 43 Choose 1
Antoine (Developer) Andrzej wants to skip the safety check on the pilot dock to save a day.
What do you do? Back Antoine: the check is in the Definition of Done Correct. Right. Developers hold each other to the Definition of Done.Let it go: it's only a small pilot with ten riders Incorrect. Real riders use pilots too.Do the safety check yourself later, to save time Incorrect. Not your role.
Learn it on Day 9: Let the team solve it
Check answer
Question 16 of 43 Choose 1
Alessia (Managing Director) The Review is my chance to approve the station. I'll bring the board.
How do you set up the Sprint Review? A board presentation with photos and a summary of the station Incorrect. Inspect the real thing.Skip it this time, as the station isn't perfect yet Incorrect. Feedback on imperfect work is the point.Invite stakeholders to try the station and discuss next steps Correct. Right. A working session, not a sign-off.
Learn it on Day 10: Review and Retrospective
Check answer
Question 17 of 43 Choose 1
Andrzej (Developer) I'm a mechanic, not a software person. What do we actually do in Sprint Planning?
How do you explain it? It's where the Scrum Master hands out each person's tasks Incorrect. The Developers plan their own work.It's mostly for software teams, so we can skip it Incorrect. Any team doing complex work can plan this way.It sets why this Sprint matters, what to do, and how Correct. Right. Sprint Planning answers why (the Sprint Goal), what can be done and how; everyone who does the work plans it together, for bikes as for software.
Learn it on Day 6: Sprint 1 Planning
Check answer
Spokeshare
Sprint 2 Goal: riders can unlock a bike with the app
Question 18 of 43 Choose 1
Aoife (Commuter) (at the Review) The unlock button is too small with gloves on.
What happens with this feedback? Note it for the final launch, and move on with the plan Incorrect. Use feedback right away.Ignore it: gloves are each mechanic's own problem Incorrect. Real use is what matters.It goes into the Product Backlog for Akira to order Correct. Right. The Review shapes what comes next.
Learn it on Day 10: Review and Retrospective
Check answer
Question 19 of 43 Choose 1
Ava (Scrum Master) In the Retrospective the mechanic and the designer argue about whose fault the delay was.
What helps? Keep it about the process, and pick one improvement Correct. Right. Blame-free Retrospectives lead to real change.Decide whose fault it was, so it's settled for good Incorrect. Judging blocks openness.Cancel the Retrospective until tempers cool down Incorrect. Every Sprint ends with one.
Learn it on Day 10: Review and Retrospective
Check answer
Question 20 of 43 Choose 1
Aisling (Developer) Nobody here knows how bike-share apps talk to locks.
What do you encourage? Leave the lock integration entirely to the supplier Incorrect. The team stays dependent.Pair with the supplier's engineer so the skill stays Correct. Right. Coach cross-functionality.Drop the app and use simple keys instead, to save time Incorrect. That's a product decision for Akira (Product Owner).
Learn it on Day 11: A skill the team lacks
Check answer
Question 21 of 43 Choose 1
Alessia (Managing Director) (to Antoine) Make the app green, it's our brand colour. Do it today.
What do you do? Thank her and suggest raising it with Akira Correct. Right. Redirect politely, every time.Let Antoine do it: she's the director Incorrect. That bypasses the Product Owner.Tell her to leave the team's workshop Incorrect. Collaboration is fine.
Learn it on Day 12: The CEO at the desk
Check answer
Question 22 of 43 Choose 1
Andrzej (Developer) The stories just say “riders unlock bikes”. Which bikes? What if the battery is flat?
How do you help? Write the details yourself, to save everyone time Incorrect. Not your accountability.Let Andrzej (Developer) guess what's really needed Incorrect. Guessing leads to rework.Help the team and Akira clarify items together Correct. Right.
Learn it on Day 13: Waiting for answers
Check answer
Question 23 of 43 Choose 1
Alessia (Managing Director) The mayor wants to know: will all 300 bikes be out on 1 June?
How do you help Akira (Product Owner) answer? Promise yes, to keep the mayor's office happy and on side Incorrect. A promise without evidence becomes a broken promise.Help him forecast a range from stations actually finished Correct. Right. Evidence, updated every Sprint.Say the team will only know on 1 June itself, not before Incorrect. Stakeholders need to plan.
Learn it on Day 14: Dates and promises
Check answer
Question 24 of 43 Choose 1
Akira (Product Owner) Station 3 is Done. Can riders use it before the Review?
Which statement is true? No: releases only happen at the Sprint Review itself Incorrect. The Review is not a release gate.Yes: an Increment can go out before the Sprint ends Correct. Correct. The Review isn't a gate.Only after all 300 bikes are ready to go out together Incorrect. That delays value and feedback.
Learn it on Day 15: Is it really done?
Check answer
Question 25 of 43 Choose 1
Antoine (Developer) Our Retrospectives feel the same every time.
What could help? Check last Sprint's improvement, and try a new format Correct. Right. Keep Retrospectives useful.Skip them for a while until the team's energy returns Incorrect. Every Sprint has a Retrospective.Only the Scrum Master talks, to keep things short Incorrect. It's the team's event.
Learn it on Day 15: Is it really done?
Check answer
Question 26 of 43 True or false
Aisling (Developer) Our Daily Scrum at the depot has turned into a 40-minute repair discussion.
True or false: the Daily Scrum is a 15-minute event. True Correct. Correct. Detailed discussions happen afterwards, with the people who need them.False Incorrect. The Daily Scrum is timeboxed to 15 minutes.
Learn it on Day 13: Waiting for answers
Check answer
Question 27 of 43 Choose 2
Alessia (Managing Director) Abraham from the city keeps phoning the mechanics directly with requests.
Which two responses fit? Welcome the talks, but new work goes through Akira Correct. Correct. Collaboration yes; one person orders the work.Forbid the city from talking to the team directly Incorrect. Collaboration with stakeholders is valuable.Help Akira set up a regular check-in with the city Correct. Correct. Facilitating stakeholder collaboration serves the Product Owner.Let the mechanics take any request that sounds urgent Incorrect. Then the team loses focus on the Sprint Goal.
Learn it on Day 2: Who talks to whom
Check answer
Question 28 of 43 Choose 1
Aisling (Developer) “20 stations in the city centre” is on the backlog, but each station needs a permit, power and a supplier delivery.
How do you help the team prepare it? Help split it into smaller items, ordered by lead time Correct. Right. Refinement into permits, site preparation and installation per area brings long lead times to light, so permits start early.Take all 20 stations into one big Sprint, to get it done Incorrect. One item that big can't be finished or tracked.Wait for the permits to arrive before thinking about it Incorrect. Waiting wastes the lead time.
Learn it on Day 4: Transparency first
Check answer
Spokeshare
Sprint 3 Goal: 20 stations in the city centre
Question 29 of 43 Choose 1
Alessia (Managing Director) I'll measure the team by how many bolts and docks they install.
What do you suggest instead? The hours each mechanic logs at the depot every week Incorrect. That says nothing about value.The number of meetings held with the city each month Incorrect. Even less.Outcomes: rides per day and rider satisfaction Correct. Right. Measure value, not output.
Learn it on Day 16: Learning from real users
Check answer
Question 30 of 43 Choose 1
Abraham (City Transport Officer) Twelve permits are stuck between Transport and Planning. They each say it's the other.
What do you do? Build the stations anyway, and apply for the permits later Incorrect. Illegal and harmful to trust.Wait for the city departments to agree among themselves Incorrect. The barrier stays.Get Transport, Planning and Akira together on the impact Correct. Right. Remove barriers between stakeholders and the team.
Learn it on Day 17: A blocker above the team
Check answer
Question 31 of 43 Choose 1
Aisling (Developer) Every new permit takes eight weeks. We'll hit this again.
What do you do after the permits are approved? Work with the city on a standard, faster permit route Correct. Right. Fix the cause.Nothing more: the permits are approved now, so that's it Incorrect. It will come back.Complain in the local press about the city's delays Incorrect. That damages the relationship.
Learn it on Day 17: A blocker above the team
Check answer
Question 32 of 43 Choose 1
Abraham (City Transport Officer) Akira won't put a station near city hall. Ava, persuade him.
What do you do? Persuade Akira on Abraham's behalf, to help the city out Incorrect. That undermines the Product Owner.Stay neutral and help Abraham explain the value to Akira Correct. Right. You facilitate; the Product Owner decides.Tell Abraham that product decisions aren't his business Incorrect. He's an important stakeholder.
Learn it on Day 18: Facilitating a clash
Check answer
Question 33 of 43 Choose 1
Andrzej (Developer) To go faster we used cheaper bolts. Now docks wobble and need fixing every week.
What do you advise? Make the problem and its cost visible to Akira in the backlog Correct. Right. Quality debt exists outside software too.Fix the docks quietly at night, without telling anyone at all Incorrect. Hidden work breaks transparency.Leave it until after the launch, when the team has more time Incorrect. It gets worse and less safe.
Learn it on Day 19: Making debt visible
Check answer
Question 34 of 43 Choose 2
Antoine (Developer) Shall we add “tested in rain” to our Definition of Done?
Which two statements are true? The team may make its Definition of Done stricter Correct. Correct.That's a fitting topic for the Retrospective Correct. Correct.Only Alessia can change it, as the sponsor Incorrect. It belongs to the Scrum Team.It never changes once the team has agreed it Incorrect. It should evolve.
Learn it on Day 19: Making debt visible
Check answer
Question 35 of 43 Choose 1
Aisling (Developer) Andrzej keeps moving my station plans without asking.
The Retrospective gets heated. What do you do? Take Aisling's side, since she's clearly in the right Incorrect. Taking sides blocks resolution.Move on quickly to the next topic on the board Incorrect. Avoided conflict grows.Keep it about the plans, and help them agree a rule Correct. Right.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 36 of 43 True or false
Akira (Product Owner) Should I come to the Retrospective, or is it just for the builders?
True or false: the Product Owner is part of the Scrum Team and joins the Retrospective. True Correct. Correct.False Incorrect. The Retrospective is for the whole Scrum Team.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 37 of 43 Choose 1
Antoine (Developer) The supplier has sent bikes with the wrong locks again. The team wants to tell Arturo (Supplier Account Manager) exactly what they think of him.
How should the team handle it? Send an angry email so the supplier sees how serious it is Incorrect. It may feel good, but it rarely gets bikes delivered faster.With respect and firmness: agree a fix and a date with Arturo Correct. Right. Describe the problem and its impact, and keep the team's commitment to the launch by planning around the delay; respectful, clear conversations get faster fixes.Say nothing, and refit all the locks themselves again Incorrect. The supplier needs to know, or it will happen again.
Learn it on Day 12: The CEO at the desk
Check answer
Spokeshare
Sprint 4 and beyond Goal: the full city network is live
Question 38 of 43 Choose 1
Alessia (Managing Director) Launch is in two weeks. Everyone works weekends until then.
What do you and Akira (Product Owner) say? Agree: it's only two weeks of weekend work Incorrect. Fatigue causes mistakes, especially with safety.Keep a sustainable pace and adjust the scope Correct. Right. Scope is the lever. Tired mechanics make unsafe bikes.Refuse to discuss any weekend work at all Incorrect. Offer the scope lever.
Learn it on Day 22: Sustainable pace
Check answer
Question 39 of 43 Choose 1
Alessia (Managing Director) Our scooter division wants to use Scrum too. Send them your board.
What do you advise? Send them a copy of the team's board and templates Incorrect. Copying forms doesn't copy understanding.Meet them, explain the why, and plan step by step Correct. Right. Serve the organisation, don't copy templates.Say Scrum only works for the bike team, not scooters Incorrect. It works for complex work in general.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 40 of 43 Choose 1
Andrzej (Developer) The last ten docks work, but the payment screen on two of them freezes. Launch is tomorrow.
What happens to those two docks? They aren't Done, so those two wait for now Correct. Right.Open them anyway, since riders are waiting for them Incorrect. Undone work isn't released.Delay the whole launch until both are fixed Incorrect. The rest is Done and valuable.
Learn it on Day 24: Hold the line on Done
Check answer
Question 41 of 43 Choose 1
Akira (Product Owner) The mechanic and the designer argue every planning session and the others go quiet.
What helps everyone contribute? Let them argue it out until one side wins Incorrect. Others stay silent and ideas are lost.You decide the plan yourself to save time Incorrect. The Developers plan their work.1-2-4-All: alone, then pairs, fours, then share Correct. Right. Quiet ideas surface before the loudest voices take over.
Learn it on Day 3: Coach the vision Technique: 1-2-4-All
Check answer
Question 42 of 43 Choose 1
Aisling (Developer) Docks keep failing in the rain. We fix one thing, another fails.
How do you look at all possible causes? Blame the supplier and ask them for a full refund Incorrect. Blame skips the other causes.Replace all the docks with a new, sturdier model Incorrect. Expensive and may not fix the cause.A fishbone diagram of causes, then check each Correct. Right. They find cheap seals and no rain test; “tested in rain” joins the Definition of Done.
Learn it on Day 24: Hold the line on Done Technique: Fishbone diagram
Check answer
Question 43 of 43 Choose 1
Antoine (Developer) Andrzej never listens to me. I'm tired of it.
In your one-on-one, what do you do first? Listen fully, summarise it, and ask before suggesting Correct. Right. Feeling heard is the first step to working it out.Tell him what to do straight away, to help him quickly Incorrect. Advice before understanding rarely lands.Defend Andrzej, who isn't there to explain himself Incorrect. That makes Antoine stop talking.
Learn it on Day 18: Facilitating a clash Technique: Active listening
Check answer