Airline app, three teams 42 questions 5 phases
Skylane: a Scrum Master case study Skylane is an airline's mobile app: booking, check-in and boarding passes. Three Scrum Teams work on it at the same time, and every team has its own habits. You're the Scrum Master of the Check-in team, and you quickly find that most problems sit between the teams, not inside them.
What this case study tests
Several teams, one product Dependencies Shared Definition of Done Scaling
You're the Scrum Master. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Anton (Scrum Master) You, Check-in team Adaeze (Product Owner) One Product Owner for the whole app Amaya (Developer) Check-in, backend Axel (Developer) Check-in, app screens Ayumi (Developer) Check-in, testing Ansgar (Scrum Master) Booking team Stakeholders
Amadou (Airport Operations Manager) Gates and boarding Annika (Frequent flyer) Flies twice a week Skylane
Getting started Three teams, one app
Question 1 of 42 Choose 1
Alma (VP Digital) Each team should have its own Product Owner and its own backlog. Easier to manage.
What does the Scrum Guide say about several teams on one product? Each team needs its own Product Owner and its own backlog Incorrect. That splits the product. Teams would optimise their part, not the whole.They share one Product Goal, backlog and Product Owner Correct. Right. Multiple Scrum Teams working on the same product share these.Only the biggest team gets a Product Owner of its own Incorrect. One Product Owner serves the product, whatever the number of teams.
Learn it on Day 25: A team that runs itself
Check answer
Question 2 of 42 Choose 1
Adaeze (Product Owner) I'm one person with three teams. I can't be in every refinement.
How can you serve Adaeze (Product Owner)? Help her find techniques, such as joint refinement Correct. Right. You serve the Product Owner with techniques and facilitation.Write the backlog items for her, to save her time Incorrect. Making items clear is the Product Owner's accountability, with the Developers.Tell the teams to decide the priorities themselves Incorrect. The Product Owner orders the Product Backlog.
Learn it on Day 2: Who talks to whom
Check answer
Question 3 of 42 True or false
Amaya (Developer) Is the Definition of Done per team? Booking's is much looser than ours.
True or false: multiple Scrum Teams on one product must share a Definition of Done. True Correct. Correct. If several teams work on a product, they must mutually define and comply with the same Definition of Done.False Incorrect. One product, one Definition of Done, so every Increment means the same thing.
Learn it on Day 5: Team agreements
Check answer
Question 4 of 42 Choose 2
Ansgar (Scrum Master) Our teams never talk until something breaks. Should we do something about that?
Which two ideas help? Make cross-team dependencies visible and agree them Correct. Correct. Visible dependencies can be planned (Common practice).Let each team find the others' changes at release time Incorrect. That's when it's most expensive to find out.Have Developers from all teams meet about shared work Correct. Correct. Many multi-team setups do this (Common practice; not in the Guide).Forbid the teams from touching each other's code Incorrect. That creates bottlenecks and hand-offs.
Learn it on Day 11: A skill the team lacks
Check answer
Question 5 of 42 Choose 1
Alma (VP Digital) Anton, you're responsible for making the Check-in team hit its numbers.
What is your accountability as Scrum Master? Making sure the team hits the targets that management sets Incorrect. The Scrum Master isn't a target-setter or manager.Assigning everyone's tasks each day, so nothing is ever forgotten Incorrect. The Developers decide who does what.The Scrum Team's effectiveness, by helping it use Scrum well Correct. Right. The Scrum Master is accountable for the Scrum Team's effectiveness.
Learn it on Day 1: A new team
Check answer
Question 6 of 42 Choose 1
Axel (Developer) Booking uses three-week Sprints, we use two. Is that a problem?
What do you suggest? Tell the teams it's forbidden to use different lengths Incorrect. The Guide doesn't say that. It's a practical choice.Make all three teams use the same two-week Sprints from tomorrow Incorrect. You help them decide; you don't impose.Raise it with the teams and PO: a shared cadence helps integrate Correct. Right. The Guide doesn't require it, but aligned Sprints are common practice for multi-team products.
Learn it on Day 5: Team agreements
Check answer
Question 7 of 42 Choose 1
Annika (Frequent flyer) I just want my boarding pass to work offline at the gate.
Who decides where this goes in the Product Backlog? Adaeze (Product Owner), who orders it Correct. Correct. She orders the single Product Backlog for the whole app.The team that likes the idea the most Incorrect. Teams can suggest; the Product Owner orders.Alma (VP Digital), the senior sponsor Incorrect. She can try to convince the Product Owner, but she doesn't order the backlog.
Learn it on Day 4: Transparency first
Check answer
Question 8 of 42 Choose 1
Amadou (Airport Operations Manager) Airport gates need two months' notice of any change to boarding passes.
What do you do with this? Ignore it until a scanner change is actually planned by a team Incorrect. A known constraint should be visible early.Make sure Adaeze and the teams know, so it shapes planning Correct. Right. Transparency about constraints lets the teams plan for them.Promise Amadou that nothing will change at the gates Incorrect. Not yours to promise, and not true.
Learn it on Day 2: Who talks to whom
Check answer
Question 9 of 42 Choose 1
Alma (VP Digital) Let's organise by layer: one team builds the app screens, one the servers, one does all the testing. It's tidier.
What do you advise? Keep each team able to deliver whole features, end to end Correct. Right. Cross-functional feature teams can finish a whole feature such as check-in; layer teams must hand work to each other and can't finish anything alone.Split them by layer, since specialists work faster together Incorrect. Each specialist may be faster, but nothing is finished until all three line up.Let each team work alone, without coordinating with others Incorrect. Teams on one product still have to integrate their work.
Learn it on Day 9: Let the team solve it
Check answer
Skylane
Sprint 1 Goal: travellers can check in on the app
Question 10 of 42 Choose 1
Adaeze (Product Owner) Should each team have its own Sprint Goal, or one shared?
Which statement is true? Each team has a Sprint Goal, all serving the one Product Goal Correct. Correct.Teams don't need Sprint Goals if they share a Product Goal Incorrect. Every Sprint has a Sprint Goal.Only the Product Owner's own team needs a Sprint Goal of its own Incorrect. Every Scrum Team creates one in Sprint Planning.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 11 of 42 Choose 1
Amaya (Developer) We can't finish check-in without Booking's new API. They didn't plan it this Sprint.
What do you do first? Tell Amaya to build Booking's API herself, quietly, this week Incorrect. Hidden work across teams causes conflicts and surprises.Cancel the Sprint, since the check-in work can't be finished now Incorrect. Only the Product Owner can, and only if the Sprint Goal is obsolete.Talk with Ansgar and Adaeze to make the dependency visible Correct. Right. Removing impediments between teams is part of your job.
Learn it on Day 7: The first impediment
Check answer
Question 12 of 42 Choose 1
Anton (Scrum Master) Planning ran four hours because we waited for answers from the other teams.
What could help next time? Drop the timebox whenever other teams are involved in planning Incorrect. Events stay timeboxed.Refine cross-team items together before Sprint Planning Correct. Right. Refinement prepares items; known dependencies make planning shorter (Common practice).Plan the other teams' work for them as well, to save time Incorrect. Each team plans its own work.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 13 of 42 True or false
Axel (Developer) Every morning I report to you what I did. That's the Daily Scrum, right?
True or false: the Daily Scrum is a status report to the Scrum Master. True Incorrect. It's the Developers' event to inspect progress toward the Sprint Goal and adapt their plan.False Correct. Correct. The Scrum Master makes sure it happens, but it belongs to the Developers.
Learn it on Day 7: The first impediment
Check answer
Question 14 of 42 Choose 1
Alma (VP Digital) Can Axel quickly help Booking with their screens this week? They're behind.
What do you suggest? Send Axel (Developer) over without telling anyone Incorrect. That endangers your Sprint Goal and hides the change.Bring it to Adaeze and both teams to decide together Correct. Right. Self-managing teams decide; the Product Owner weighs the value.Refuse any help between teams, to protect your Sprint Incorrect. Helping each other is good when it's transparent and agreed.
Learn it on Day 8: Protect the Sprint
Check answer
Question 15 of 42 Choose 1
Ayumi (Developer) Axel merged without running the shared test suite to save time.
What do you do? Back Ayumi: the shared Definition of Done applies Correct. Right. Developers hold each other accountable to the Definition of Done.Let it go this time: it's only one small merge Incorrect. In a shared codebase, one shortcut can break three teams.Report Axel (Developer) to Alma (VP Digital) Incorrect. The team handles it first.
Learn it on Day 9: Let the team solve it
Check answer
Question 16 of 42 Choose 2
Ansgar (Scrum Master) Shall we run one Sprint Review for the whole app instead of three?
Which two statements are true? A joint Review shows stakeholders the whole product Correct. Correct. Many multi-team products do this (Common practice).The Review is a working session to inspect and adapt Correct. Correct, from the Scrum Guide.The Review is where management signs off each team Incorrect. It's not a sign-off gate.Stakeholders should only see slides, not the app Incorrect. Show working product.
Learn it on Day 10: Review and Retrospective
Check answer
Question 17 of 42 Choose 1
Annika (Frequent flyer) Check-in works, but the boarding pass doesn't appear until I restart the app.
Ayumi (Developer) says it fails the Definition of Done. What happens? Show it as done, and fix it quietly in the next Sprint Incorrect. That breaks transparency.Release it with a warning to travellers about restarting Incorrect. Undone work isn't released.It isn't in the Increment; it returns to the backlog Correct. Right. Only Done work is part of the Increment.
Learn it on Day 10: Review and Retrospective
Check answer
Skylane
Sprint 2 Goal: boarding passes work offline at the gate
Question 18 of 42 Choose 1
Amaya (Developer) None of us has built offline storage on phones. Booking has one person who has.
What do you encourage? Borrow their specialist quietly for a week or so, as a favour Incorrect. That disrupts their Sprint and hides the dependency.Skip offline support for this release, and add it later Incorrect. Not your decision; it's the Product Owner's, and the team can learn.Agree it openly with Booking and Adaeze, so they can pair Correct. Right. Grow the skill inside the team, with the dependency visible.
Learn it on Day 11: A skill the team lacks
Check answer
Question 19 of 42 Choose 1
Alma (VP Digital) (at the team's desks) Axel, add a seat-upgrade banner today. I'll tell Adaeze later.
What do you do? Thank Alma and suggest she brings it to Adaeze first Correct. Right. Redirect politely; the Product Owner orders the work.Let Axel do it straight away: she's the VP, after all Incorrect. That bypasses the Product Owner and risks the Sprint Goal.Tell Alma (VP Digital) she can't come to the team area Incorrect. The issue is who decides work, not who talks to whom.
Learn it on Day 12: The CEO at the desk
Check answer
Question 20 of 42 Choose 1
Ayumi (Developer) The stories say “make offline work”. Work how? For which screens?
How do you help? Write the acceptance criteria yourself, quickly, for Ayumi Incorrect. Not yours to write.Help the team and Adaeze clarify items together in refinement Correct. Right. You help the team understand the need for clear and concise Product Backlog items.Tell Ayumi (Developer) to test whatever she thinks right Incorrect. Then nobody agrees what Done means for the item.
Learn it on Day 13: Waiting for answers
Check answer
Question 21 of 42 Choose 1
Alma (VP Digital) The marketing campaign is booked for the 1st of next month. Will offline boarding passes be ready?
How do you help Adaeze (Product Owner) answer? Help her forecast a range from what the teams have finished Correct. Right. Forecasts come from evidence, and are updated each Sprint.Promise yes, so marketing can go ahead with its campaign Incorrect. A promise without evidence becomes a broken promise.Say that Scrum doesn't allow forecasts of release dates at all Incorrect. Forecasting is fine; it just stays empirical.
Learn it on Day 14: Dates and promises
Check answer
Question 22 of 42 True or false
Axel (Developer) Can we release offline boarding passes on Wednesday, before the Review?
True or false: an Increment may be released before the end of the Sprint. True Correct. Correct. The Sprint Review is not a gate to releasing value.False Incorrect. Increments can be delivered to stakeholders before the Sprint ends.
Learn it on Day 15: Is it really done?
Check answer
Question 23 of 42 Choose 1
Ansgar (Scrum Master) Booking wants a joint Retrospective about how our teams work together.
What do you think? Replace each team's own Retrospective with it Incorrect. Each Scrum Team still inspects its own way of working.Not allowed: Scrum has only team Retrospectives Incorrect. The Guide doesn't forbid extra cooperation.Good idea, in addition to each team's own one Correct. Right. Cross-team improvement helps the whole product (Common practice); each team still has its Sprint Retrospective.
Learn it on Day 15: Is it really done?
Check answer
Question 24 of 42 Choose 1
Amaya (Developer) Our Daily Scrum is fine, but the cross-team sync takes 45 minutes and nobody knows why we have it.
What do you suggest? Make it longer, so that everything is covered across the teams Incorrect. Longer isn't better.Ask the Developers what they need from it, and keep that Correct. Right. Practices beyond Scrum should earn their place.Replace your own team's Daily Scrum with the cross-team sync Incorrect. Each team keeps its own Daily Scrum.
Learn it on Day 13: Waiting for answers
Check answer
Question 25 of 42 Choose 1
Alma (VP Digital) I'll compare the three teams' velocity and reward the fastest.
What do you advise? Do it: competition between the teams is healthy and motivating Incorrect. Teams would inflate estimates and stop helping each other.Look at outcomes for travellers instead, like gate queues Correct. Right. Velocity isn't comparable across teams and isn't value (Common practice).Compare story points per developer across all three teams Incorrect. Even worse: it targets individuals.
Learn it on Day 16: Learning from real users
Check answer
Skylane
Sprint 3 Goal: gate staff can scan passes faster
Question 26 of 42 Choose 1
Amadou (Airport Operations Manager) The airport won't give your teams test scanners. Security rules. It's been a month.
What do you do? Get airport security, Amadou and Adaeze together to agree testing Correct. Right. Organisational barriers often need the decision-makers in one room.Tell the teams to guess how the gate scanners behave for now Incorrect. Guessing leads to failures at the gate.Borrow a scanner from a friend who works at the airport Incorrect. A workaround that may break rules and hides the problem.
Learn it on Day 17: A blocker above the team
Check answer
Question 27 of 42 Choose 1
Anton (Scrum Master) This is the third time the airport has blocked us for weeks.
What do you do after the scanners arrive? Nothing more: the problem is solved for now, so move on Incorrect. It will come back.Complain to Alma (VP Digital) about the airport's delays Incorrect. Blame doesn't change the process.Work with Amadou on a standing, faster route for equipment Correct. Right. Fix the cause, not just the case.
Learn it on Day 17: A blocker above the team
Check answer
Question 28 of 42 Choose 1
Alma (VP Digital) Booking's Product Owner should handle booking, and Adaeze check-in. Two Product Owners are faster.
What do you explain? Two Product Owners are fine as long as they agree Incorrect. Splitting the product splits its value and its backlog.The Scrum Masters should share the Product Owner role Incorrect. That mixes accountabilities.One product, one Product Owner, who can delegate work Correct. Right. The Product Owner is one person, not a committee.
Learn it on Day 4: Transparency first
Check answer
Question 29 of 42 Choose 1
Adaeze (Product Owner) Ansgar's team wants their feature first, your team wants theirs. They both ask you to decide.
What role do you take? Facilitate the talk; Adaeze decides on the value Correct. Right. You facilitate; the Product Owner orders the backlog.Pick the approach you prefer yourself, quickly Incorrect. Ordering is the Product Owner's decision.Let the bigger team's approach win, to keep peace Incorrect. Value, not team size, decides the order.
Learn it on Day 18: Facilitating a clash
Check answer
Question 30 of 42 Choose 2
Ayumi (Developer) We've been working around a messy shared module for months. Every team adds to the mess.
Which two actions fit? Make the debt and its cost visible to Adaeze and all teams Correct. Correct. Transparency lets it be weighed openly.Each team quietly rewrites the parts it happens to touch Incorrect. Three teams rewriting quietly causes conflicts.Ask in the joint Retrospective if Done should be stronger Correct. Correct. The Definition of Done can evolve.Wait until a release fails, then fix what broke Incorrect. By then it's much more expensive.
Learn it on Day 19: Making debt visible
Check answer
Question 31 of 42 Choose 1
Axel (Developer) The Booking team keeps breaking our screens. I'm done being polite with them.
What do you do? Tell Axel (Developer) to complain to Alma (VP Digital) directly Incorrect. Escalating past the teams damages trust.Bring both teams together and agree how shared code changes Correct. Right. Handle conflict openly and about the work (Common practice).Stop working with the Booking team altogether, for now Incorrect. They share one product.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 32 of 42 Choose 1
Annika (Frequent flyer) Scanning at the gate is so fast now. I barely stop walking.
Where does feedback like this best go? Into the Sprint Review, to help decide next steps Correct. Right. Real feedback shapes the Product Backlog.Into each Developer's yearly performance appraisal Incorrect. Scrum isn't about individual rating.Nowhere: the feature is already done and released Incorrect. Feedback guides what comes next.
Learn it on Day 10: Review and Retrospective
Check answer
Question 33 of 42 True or false
Amaya (Developer) Should Adaeze come to our Retrospective? She's barely around.
True or false: the Product Owner is part of the Scrum Team and takes part in its Retrospective. True Correct. Correct.False Incorrect. The Retrospective is for the whole Scrum Team, including the Product Owner.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 34 of 42 Choose 2
Ansgar (Scrum Master) Should all three teams' work be integrated into one Increment each Sprint?
Which two statements are true? Each Increment adds to all prior ones and is verified Correct. Correct, from the Scrum Guide.Each team releases its own part without checking the rest Incorrect. One product: the Increment must be usable as a whole.Work that isn't Done isn't part of the Increment Correct. Correct.Integration can wait until the final release is ready Incorrect. Late integration hides problems until they are expensive.
Learn it on Day 15: Is it really done?
Check answer
Question 35 of 42 True or false
Amadou (Airport Operations Manager) Can I come to your Daily Scrum to see where scanning stands?
True or false: the Daily Scrum is an event for the Developers. True Correct. Correct. Stakeholders can see progress in the Sprint Backlog and at the Sprint Review.False Incorrect. The Daily Scrum is the Developers' event to plan their next day.
Learn it on Day 7: The first impediment
Check answer
Question 36 of 42 Choose 1
Ayumi (Developer) The Boarding team blames us whenever passes fail at the gate. In the joint review everyone just defends their own team.
How do you help? Gather data proving it's the other team's fault, then share it Incorrect. Winning the argument doesn't fix the gate.Help both teams focus on the travellers' problem, not blame Correct. Right. Share the data with openness, respect each team's view, and agree a shared commitment to passes that work: focus on the problem, not the blame.Stop the joint reviews for now, to reduce the conflict Incorrect. Problems between teams need both teams to solve them.
Learn it on Day 12: The CEO at the desk
Check answer
Skylane
Sprint 4 and beyond Goal: travellers can change seats in the app
Question 37 of 42 Choose 1
Ansgar (Scrum Master) Three teams, one app. How do we coordinate without long meetings?
What do you suggest? A daily one-hour meeting with all 15 people from every team Incorrect. Long, crowded meetings waste everyone's time.No coordination: teams just integrate at the end Incorrect. Late integration hides problems.A short cross-team sync with people who know the work Correct. Right. Keep it short and about what affects other teams; drop it if it stops helping.
Learn it on Day 25: A team that runs itself Technique: Scrum of Scrums
Check answer
Question 38 of 42 Choose 1
Alma (VP Digital) Loyalty and Payments want to “do it like Skylane”. Send them your process document.
What do you suggest? Send them the document and let them start right away Incorrect. Copying a process doesn't copy the understanding behind it.Start with willing teams and teach them the why Correct. Right. You serve the organisation by planning and advising Scrum implementations.Say Scrum doesn't scale beyond a few teams Incorrect. Scrum scales through multiple teams on one product.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 39 of 42 Choose 1
Ayumi (Developer) Seat change works, but not for group bookings. Launch is tomorrow.
What happens to seat change for groups? Release it anyway: group bookings are rare Incorrect. Undone work isn't released.It isn't Done; Adaeze decides what launches Correct. Right. Only Done work is part of the Increment.Lower the Definition of Done just this once Incorrect. Quality doesn't decrease.
Learn it on Day 24: Hold the line on Done
Check answer
Question 40 of 42 Choose 2
Alma (VP Digital) We're adding two more teams. Should we split the app into five products?
Which two statements are true? Teams on one product share one PO, backlog and goal Correct. Correct.Each Scrum Team stays at 10 or fewer people Correct. Correct.Each team owns a separate backlog, to avoid blocking Incorrect. That splits the product's value.The Scrum Masters become the teams' line managers Incorrect. There's no hierarchy in a Scrum Team.
Learn it on Day 25: A team that runs itself
Check answer
Question 41 of 42 Choose 1
Amaya (Developer) Check-in items take nine days on average. Booking's take three.
What does this tell the team? Look at where check-in items wait, and fix the waiting Correct. Right. Cycle time shows where work waits; use it to improve flow, not to compare teams.Booking's team is simply better and faster at the work Incorrect. Comparing teams with flow numbers misses the cause.The check-in team needs to work faster to catch up Incorrect. Speed isn't the problem; waiting is.
Learn it on Day 13: Waiting for answers Technique: Cycle time and throughput
Check answer
Question 42 of 42 Choose 1
Axel (Developer) Booking keeps breaking our screens and I'm about to explode.
Before the joint meeting, what do you do? Decide which team is right yourself, before the meeting Incorrect. Judging blocks resolution.Avoid the topic: it will calm down by itself Incorrect. Avoided conflict grows.Keep the talk about the work and each side's needs Correct. Right. They agree that shared code changes go through a joint review.
Learn it on Day 20: Conflict in the Retro Technique: Conflict styles
Check answer