Organisation and impediments · cheat sheet

Scrum of Scrums

A short regular meeting where people from several teams coordinate shared work and dependencies.

Common practice
4 steps
Used by Scrum Master

What it is

A short, regular meeting where representatives of several teams working on one product coordinate dependencies and blockers.

When to use it

When several teams work on one product or depend on each other.

Why it works

It keeps several teams aligned without everyone attending everything.

Do

  • Keep it about the teams' coordination, not individual status.

Don't

  • A long status meeting nobody needs.

Step by step

  1. Each team sends a representative Often someone who knows the work.
  2. Meet briefly and regularly Two or three times a week, 15 minutes.
  3. Focus on cross-team issues What we need from you, what might affect you.
  4. Record and follow up Blockers get owners.
Also called: Cross-team syncPrint the blank template ↗

Worked example

The situation. Three teams building one app.

  1. Team A's change to logins would break Team B's tests.
  2. Spotted at the meeting; changes timed together.

The result. No broken release.

Cross-team sync Print blank
TeamDone since last timeNextNeeds from othersBlockers

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

When Basketly grows to several teams on Day 25, Aaron (Scrum Master) suggests a short twice-weekly cross-team sync, with the dependency board.

Questions people ask

Is it part of Scrum?

No. It's a common practice for scaling.