Flow and visual management · cheat sheet

Cycle time and throughput

How long items take from start to Done, and how many get Done per week.

Common practice
5 steps
Used by Scrum Master

What it is

The time an item takes from when work starts until it's finished. Tracking it shows how fast work really flows.

When to use it

To see whether work flows well and to forecast without estimates.

Why it works

It helps forecast (“items usually take 3 to 7 days”) and shows whether changes speed things up.

Do

  • Use it for forecasting single items: “within 7 days, 85% of the time”.

Don't

  • Using the numbers to compare or rank people.

Step by step

  1. Record start and finish dates For each item.
  2. Calculate cycle time Finish minus start.
  3. Plot it A dot per item over time.
  4. Use percentiles “85% of items finish within 7 days.”
  5. Investigate outliers Why did some take much longer?
Also called: Flow metricsPrint the blank template ↗

Worked example

The situation. A support team's tickets.

  1. 85% finish within 4 days.
  2. Outliers all waited for one external system.

The result. A direct contact with that system's team cut the outliers by half.

Cycle time log Print blank
ItemStartedFinishedDaysWhy long (if outlier)

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

Items wait three days for answers from Anna (Product Owner). Cycle time drops once she sits with the team two afternoons a week.

Questions people ask

Lead time or cycle time?

Lead time runs from request to delivery; cycle time from start of work to finish.