Don't overcommit
Promo codes are finally in. Everyone is excited, and that's exactly when teams take on too much.
Sprint Goal: Shoppers are rewarded and can rate their delivery.
Team
Anna (Product Owner) Ava (Developer)
Stakeholders
Ali (Sales Director)
Techniques today Sailboat Fist of five
Documents today Sprint Backlog Release plan and forecast
How the day goes
- 09:00Facilitate Sprint 4 Planning
- 10:30Check the forecast is realistic
- 14:00Look back at the Sprint 1 promises with Ali (Sales)
Situation 1 of 3
14:00 · Look back at the Sprint 1 promises with Ali (Sales)Ali (Sales Director)
Promo codes are in this Sprint? Finally! And ratings and rewards too, right? Let's do it all!
The Developers are nodding along, but their forecast looks too big. What do you do?
Help the Developers forecast from past performance and capacity, especially when there's pressure to please.
Situation 2 of 3
14:00 · Look back at the Sprint 1 promises with Ali (Sales)Anna (Product Owner)
Ali (Sales) is thrilled. But he still thinks it only happened because he kept pushing.
What do you help Anna (Product Owner) show him?
Trust grows when the Product Backlog is transparent and decisions are explained by value, not by who shouts loudest.
Situation 3 of 3
14:00 · Look back at the Sprint 1 promises with Ali (Sales)Ava (Developer)
Last Sprint of the project. Should we skip the Retrospective on Friday, since there's nothing to improve for?
What do you say?
Every Sprint ends with a Retrospective. The end of a milestone is a good time for a bigger look back.
Rules and common practice
The rules behind today. Scrum Guide official rules · Agile Manifesto the values behind them · EBM Guide measuring value · Common practice not in the Guide, but widely used.
Scrum Guide
Selecting the work
- The Developers select how much can be completed. The more they know about their past performance, capacity and Definition of Done, the more confident their forecasts.
Scrum Guide
The Product Backlog is ordered
- The Product Owner's decisions are visible in the content and ordering of the Product Backlog.
Scrum Guide
Every Sprint has a Retrospective
- The Sprint Retrospective concludes the Sprint, every Sprint.
Common practice
Milestone Retrospectives
- After a release or a few Sprints, many teams take a longer look back to capture what to keep doing.
- Common practice.
Sources: The Scrum Guide (November 2020), Ken Schwaber & Jeff Sutherland, CC BY-SA 4.0 · All sources
Day 21 complete
3 situations today.
Your responsibility todayHelping the team forecast realistically
Technique you usedEvidence-based forecasts, milestone Retrospectives
Key points to remember
- Help the Developers forecast from past performance and capacity, especially when there's pressure to please.
- Trust grows when the Product Backlog is transparent and decisions are explained by value, not by who shouts loudest.
- Every Sprint ends with a Retrospective. The end of a milestone is a good time for a bigger look back.
Techniques today Sailboat Fist of five
Documents today Sprint Backlog Release plan and forecast