Day 8 of 25Week 1 · Sprint 1WednesdayStakeholders

A request on the go

Marketing wants something added right now, in the middle of the Sprint.

Sprint Goal: Shoppers can sign in, find products and fill a cart.
Team
Aaron (Scrum Master)
Stakeholders
Amelia (Marketing Lead)
Same day, other role: see Day 8 as the Scrum Master (Protect the Sprint) →
Documents today Product Backlog
How the day goes
  1. 09:00Daily Scrum
  2. 11:00Amelia (Marketing) drops by
  3. 15:00Backlog refinement

Situation 1 of 2

11:00 · Amelia (Marketing) drops by
Amelia (Marketing Lead)
Quick one: can the team add a summer campaign banner this week? It's small!

How do you handle it?

New requests go to the Product Backlog, not straight into the Sprint.

Situation 2 of 2

15:00 · Backlog refinement
Aaron (Scrum Master)
Quick coaching question: what if Adam (CEO) dropped grocery delivery tomorrow, and our Sprint Goal made no sense any more?

What would happen to the Sprint?

Only the Product Owner may cancel a Sprint, and only if the Sprint Goal becomes obsolete. It should be rare.

Rules and common practice

The rules behind today. Scrum Guide official rules · Agile Manifesto the values behind them · EBM Guide measuring value · Common practice not in the Guide, but widely used.

Scrum Guide

During the Sprint

  • No changes are made that would endanger the Sprint Goal.
  • Scope may be clarified and renegotiated with the Product Owner as more is learned.
  • The Product Backlog is refined as needed.
Scrum Guide

Cancelling a Sprint

  • A Sprint could be cancelled if its Sprint Goal becomes obsolete.
  • Only the Product Owner has the authority to cancel it.
Common practice

New requests

  • Capture them in the Product Backlog and order them against everything else.
  • Explain when and why, so the stakeholder knows what happens next.
Agile Manifesto

Agile value: respond to change

  • The Manifesto values responding to change over following a plan, and welcomes changing requirements.
  • Scrum channels change through the Product Backlog, so the Sprint Goal stays protected.

Sources: The Scrum Guide (November 2020), Ken Schwaber & Jeff Sutherland, CC BY-SA 4.0 · Manifesto for Agile Software Development (2001), paraphrased · All sources

Day 8 complete

2 situations today.

Your responsibility todayProtecting the Sprint Goal
Technique you usedCapturing requests in the backlog
Key points to remember
  • New requests go to the Product Backlog, not straight into the Sprint.
  • Only the Product Owner may cancel a Sprint, and only if the Sprint Goal becomes obsolete. It should be rare.
Documents today Product Backlog