Day in the RoleRelease plan and forecastWhat's in the release, and when it's likely
Release scope
| Item | Must | Should | Could | Won't this time |
|---|
| Login | ✓ | | | |
| Browse | ✓ | | | |
| Cart | ✓ | | | |
| Checkout | ✓ | | | |
| Card payment | ✓ | | | |
| Delivery slots | | ✓ | | |
| Favourites | | | ✓ | |
| Promo codes | | | | ✓ |
| Ratings | | | | ✓ |
Progress so far (items done)
| Sprint | Done to date | Total scope |
|---|
| Sprint 1 | 3 | 11 |
| Sprint 2 | 6 | 11 |
| Sprint 3 | 8 | 11 |
Forecast: a likely range, from actual progress
Most likely Sprint 5, possibly 6, if scope stays the same. Adding promo codes would move it a Sprint later.
Forecast from what the team has actually finished, as a range. If scope grows, the forecast moves: show both.