← RACI chart: explanationFilled-in example Blank template
Day in the RoleRACI chartWho does what, who owns it
Version1.0
Date15 March
RResponsible: does the work
AAccountable: owns the result. Exactly one per row
CConsulted: asked before
IInformed: told after
Deliverable or decisionAtticus (Sponsor)Annelise (Project Manager)Amani (Clinical Lead)Aine (IT Lead)Adaugo (HR Lead)Antonia (Compliance Lead)Alfonso (Software Vendor)Abigail (Finance)One A?
Building designARCCCI✓
Building worksIAICCI✓
Equipment purchaseIACCR✓
Booking system setupICAR✓
Hiring and trainingICARI✓
Licence applicationICCR✗
Opening dateARCIICII✓
Spending above €25kARC✓

Write a person's name at the top of each column. Check that each row has one A, and that no column is overloaded with R's.

Gaps and follow-ups

Licence application: Antonia (Compliance Lead) is responsible, but nobody is accountable yet. Atticus (Sponsor) to decide by Friday.

Agreed by the sponsor
Signature
Date

Letters and symbols: HR Human resources · IT Information technology · RACI Responsible (does the work), Accountable (owns the result), Consulted (asked before), Informed (told after) · €k Thousands of euros (€150k = €150,000)

Day in the Role · RACI chartIllustrative example · not a real project or organisation · dayintherole.com