| Version | 1.0 |
|---|---|
| Date | 15 March |
Everyday health care within 15 minutes of home for 18,000 Riverside residents.
| Criterion | Weight | A | B | C | D |
|---|---|---|---|---|---|
| Option | Do nothing | Renovate the old clinic (12 rooms) | Convert the warehouse (24 rooms) | Build new on a green site | |
| Fits the €4.5M budget | 3 | 5×3 = 15 | 4×3 = 12 | 4×3 = 12 | 1×3 = 3 |
| Time to open | 2 | 5×2 = 10 | 4×2 = 8 | 3×2 = 6 | 1×2 = 2 |
| Capacity for demand | 3 | 1×3 = 3 | 2×3 = 6 | 5×3 = 15 | 5×3 = 15 |
| Risk (5 = low risk) | 2 | 2×2 = 4 | 4×2 = 8 | 3×2 = 6 | 3×2 = 6 |
| Community access | 1 | 1×1 = 1 | 3×1 = 3 | 4×1 = 4 | 4×1 = 4 |
| Weighted total | 33 | 37 | 43 | 30 | |
| Rank | 3 | 2 | 1 | 4 |
Scoring key: 1 = poor · 2 = weak · 3 = acceptable · 4 = good · 5 = excellent. Weight: how much the criterion matters (1 to 3). Always keep “Do nothing” as option A.
Letters and symbols: ÷ × Divided by, multiplied by · €M Millions of euros (€4.2M = €4,200,000)