Day in the RoleIncident reportSafety incident: record, causes, actions
IncidentPeople first. Make the area safe. Preserve evidence. Report as the law requires.
WhenWeek 18, 10:05
WhereEast scaffold, level 2
WhoA contractor's worker
SeverityInjury, hospital treatment
What happened
A worker fell about two metres from the east scaffold while moving materials. Injured arm; conscious throughout.
Immediate actions
First aid given and ambulance called
Scaffold closed and scene kept unchanged
Reported to the authorities by the contractor
Sponsor informed
Causes (blameless investigation)
A guard rail was removed for a delivery and not replaced. No step in the process checked guard rails before the scaffold was used again.
Corrective actions
| Action | Owner | By when |
|---|
| Sign-off of every scaffold before reuse | Arash (Contractor) | Immediately |
| Toolbox talk for all crews | Arash (Contractor) | This week |
| Add to the lessons log | Annelise (Project Manager) | Today |