Day in the RoleImpediment logWhat blocks the team, and who's removing it
Version1.0
Date15 March
RaisedImpedimentImpactOwnerActionResolved
Day 2No API keys for loginLogin blockedAaron (Scrum Master)Chased IT with the impactDay 3
Day 8No phone testing toolCart can't be testedAaron (Scrum Master)Free trial, then a licenceDay 10
Week 6Map service licence for trackingTracking blockedAdam (CEO)Licence approved: value outweighs costWeek 7

Patterns worth fixing at the root

An impediment is anything the team can't solve by itself that slows progress. Record when it was raised: waiting time is the cost.

Letters and symbols: API Application programming interface: a way for two systems to exchange data · CEO Chief executive officer · IT Information technology