T-shirt sizing
Rough sizes like S, M and L for early or large items where numbers would pretend to be precise.
What it is
A quick, rough way to size work using shirt sizes: XS, S, M, L, XL. It's used early, when detail is low and many items need a first sorting.
When to use it
Early in a product, for big items far down the backlog, or for roadmap conversations with stakeholders.
Why it works
Words like “medium” invite less false precision than numbers, so it's fast and keeps conversations at the right level for early planning.
Do
- Use it early; switch to finer estimates when you plan the near term in detail.
Don't
- Treating an L as a commitment.
- Never refining big items into smaller ones.
Step by step
- Agree what each size roughly means For example S ≈ a few days, M ≈ a couple of weeks, L ≈ a month, XL ≈ too big, split it.
- Lay out the items Cards on a table or a board with size columns.
- Sort quickly together Place each item in a column; move it if someone disagrees, and discuss only real disagreements.
- Split the XLs Anything XL is too uncertain to plan; break it down.
- Convert only when needed For budgets or roadmaps, map sizes to ranges, never to exact numbers.