Data and statistics · cheat sheetC chart
A control chart for the number of defects found when the same amount is inspected every period.
Common practice
5 steps
Used by Process Improvement Specialist
What it is
A C chart plots the number of defects in a fixed amount of work each period, with limits c̄ ± 3√c̄.
When to use it
For counts of errors, faults or complaints in a fixed amount of work: per batch, per 1,000 lines, per day of a fixed volume.
Why it works
It shows whether the defect count is stable, and flags unusual periods, when the amount checked never changes.
Do
- Keep the amount inspected exactly the same; otherwise use a U chart.
Don't
- Using it when the amount inspected varies (use a U chart).
- Counting defective items instead of defects (use a P or NP chart).
Step by step
Fixed amount
Count defects
Centre c̄
Limits
Investigate
Worked example
The situation. Errors found in 100 checked forms a day; average 4.
- Limits: 4 ± 3 × 2.
The result. A day with 12 errors was investigated: a new member of staff without training.
| Line | Calculation | Value |
|---|
| Centre | average count | 4 |
| Upper limit | 4 + 3 × √4 | 10 |
| Lower limit | 4 − 6 | 0 (none) |
Filled in for: Errors found in 100 checked forms a day; average 4.
| Period | Amount checked (same each time) | Defects |
|---|
| | |
| | |
| | |
| | |
Copy this structure, or print the blank version and fill it in by hand. c̄ ______ upper limit c̄ + 3√c̄ ______
Before you use it: check these
| Check | If it fails |
|---|
| The same amount inspected every period | Use a U chart |
In the roles
How a Process Improvement Specialist uses it
Errors in 2,000 audited order lines a day: the U chart page shows the varying-volume version of the same idea.
Questions people ask
C or U chart?
C when the amount checked is fixed; U when it varies.
← All techniques and tools