Tallybook: a Scrum Master case study

Tallybook makes a bookkeeping app for small businesses. The team has worked for years with an engineering manager who hands out tasks every morning. Now the company wants Scrum, and you've just been hired as their first Scrum Master. Nobody is quite sure what that means, including the manager.

What this case study tests
A manager who assigns tasksDaily Scrum as a status reportRemoving impedimentsCoaching self-management

You're the Scrum Master. For each situation, choose your answer and press Check. Every option is then explained, right or wrong.

Team
Ada (Scrum Master)You
Abbas (Product Owner)New to the role, used to being a business analyst
Alba (Developer)Backend, banking integrations
Ansel (Developer)App screens
Ari (Developer)Testing, quiet in meetings
Stakeholders
Augustin (Engineering Manager)Line manager of the Developers
Aurelia (Head of Product)Sponsor and budget
Amos (Support Lead)Hears every customer complaint
Adele (Customer)Runs a small café, hates paperwork
Tallybook

Getting started

Your first week at Tallybook

Question 1 of 41

Choose 1
Aurelia (Head of Product)
Welcome, Ada! We want Scrum by next month. Where will you start?

What is the best first step?

Learn it on Day 1: A new team

Question 2 of 41

Choose 1
Augustin (Engineering Manager)
So you'll run the team now? Good. I'll send you the task list each morning and you hand it out.

How do you describe your accountability to Augustin (Engineering Manager)?

Learn it on Day 1: A new team

Question 3 of 41

True or false
Aurelia (Head of Product)
We'll keep the morning task meeting and the monthly status report, and add the Sprint Review. That's Scrum, right?

True or false: using only some parts of Scrum is still Scrum.

Learn it on Day 1: A new team

Question 4 of 41

Choose 1
Abbas (Product Owner)
I'm the Product Owner now. Can you write the Product Goal for me? You know Scrum better.

What do you do?

Learn it on Day 3: Coach the vision

Question 5 of 41

Choose 2
Ansel (Developer)
Who's actually in the Scrum Team? Is Augustin (Engineering Manager) in it?

Which two statements are true?

Learn it on Day 1: A new team

Question 6 of 41

Choose 1
Amos (Support Lead)
I want my support tickets fixed. Can I just give them to Alba (Developer) directly?

What do you tell Amos (Support Lead)?

Learn it on Day 2: Who talks to whom

Question 7 of 41

Choose 1
Alba (Developer)
The backlog is in Abbas's spreadsheet on his laptop. We never see it.

What do you help with?

Learn it on Day 4: Transparency first

Question 8 of 41

Choose 1
Ari (Developer)
Augustin (Engineering Manager) says the Sprints should be two weeks because that's the company standard.

Which statement is true?

Learn it on Day 5: Team agreements
Tallybook

Sprint 1

Goal: small businesses can import their bank transactions

Question 9 of 41

Choose 1
Augustin (Engineering Manager)
I'll sit in Sprint Planning and tell them how much they can take. They always underestimate themselves.

Who selects how much work goes into the Sprint?

Learn it on Day 6: Sprint 1 Planning

Question 10 of 41

Choose 1
Ada (Scrum Master)
Sprint Planning is at hour three and they're still debating the database.

What should you do?

Learn it on Day 6: Sprint 1 Planning

Question 11 of 41

True or false
Abbas (Product Owner)
Do we need a Sprint Goal if we already have the list of items?

True or false: every Sprint has a Sprint Goal created by the whole Scrum Team.

Learn it on Day 6: Sprint 1 Planning

Question 12 of 41

Choose 1
Ansel (Developer)
Daily Scrum update for you, Ada: yesterday the import screen, today the same, no blockers.

The Developers report to you every morning. What do you do?

Learn it on Day 7: The first impediment

Question 13 of 41

Choose 1
Augustin (Engineering Manager)
I'll keep attending the Daily Scrum. I need to know who's slacking.

What do you do?

Learn it on Day 7: The first impediment

Question 14 of 41

Choose 2
Alba (Developer)
The bank still hasn't given us test access for the integration. Two days now.

Which two are part of how you serve the team here?

Learn it on Day 7: The first impediment

Question 15 of 41

Choose 1
Aurelia (Head of Product)
Quick one for the team: add a VAT report this week. It's tiny.

What do you suggest?

Learn it on Day 8: Protect the Sprint

Question 16 of 41

Choose 1
Abbas (Product Owner)
If the bank changed its API so our Sprint Goal made no sense, who could cancel the Sprint?

Which statement is true?

Learn it on Day 8: Protect the Sprint

Question 17 of 41

Choose 1
Ari (Developer)
Ansel (Developer) skipped the code review to finish faster. I'm not sure I should say anything.

What do you do?

Learn it on Day 9: Let the team solve it
Tallybook

Sprint 2

Goal: customers can send their first invoice

Question 18 of 41

True or false
Augustin (Engineering Manager)
The Sprint Review is just a demo for me, right? I'll sign off what's acceptable.

True or false: the Sprint Review is a sign-off gate for managers.

Learn it on Day 10: Review and Retrospective

Question 19 of 41

Choose 1
Ari (Developer)
The invoice feature has no tests yet. Ansel (Developer) wants to show it as done.

What should happen?

Learn it on Day 10: Review and Retrospective

Question 20 of 41

Choose 1
Ada (Scrum Master)
In the first Retrospective, nobody speaks. Augustin (Engineering Manager) is sitting in the corner.

What do you do?

Learn it on Day 10: Review and Retrospective

Question 21 of 41

Choose 1
Alba (Developer)
None of us has built invoicing with tax rules. Augustin (Engineering Manager) says just give it to an outside contractor.

What do you encourage?

Learn it on Day 11: A skill the team lacks

Question 22 of 41

Choose 1
Aurelia (Head of Product)
Ansel, while you're on invoices, add a logo upload too. Shouldn't take long.

Ansel (Developer) looks at you. What do you do?

Learn it on Day 12: The CEO at the desk

Question 23 of 41

Choose 2
Aurelia (Head of Product)
Why can't I decide what's built? I'm Head of Product.

Which two statements help her understand?

Learn it on Day 12: The CEO at the desk

Question 24 of 41

Choose 1
Ansel (Developer)
Our Daily Scrum went 40 minutes again. We got into invoice code details.

What do you suggest?

Learn it on Day 13: Waiting for answers

Question 25 of 41

Choose 1
Ari (Developer)
The stories have no acceptance criteria. I don't know what to test.

How do you help?

Learn it on Day 13: Waiting for answers

Question 26 of 41

Choose 1
Ansel (Developer)
We spend the first two hours of every Sprint Planning arguing about what the items even mean.

What do you help the team set up?

Learn it on Day 4: Transparency first
Tallybook

Sprint 3

Goal: customers see a simple profit and loss summary

Question 27 of 41

Choose 1
Aurelia (Head of Product)
The investors want an exact launch date for the mobile app. Ada, just give me one.

What do you do?

Learn it on Day 14: Dates and promises

Question 28 of 41

True or false
Abbas (Product Owner)
Can burn-up charts tell me exactly when we'll finish?

True or false: forecasting tools like burn-ups replace the need for empiricism.

Learn it on Day 14: Dates and promises

Question 29 of 41

Choose 1
Aurelia (Head of Product)
Let's report the team's velocity to the board. And let's ask them to raise it every Sprint.

What do you advise?

Learn it on Day 16: Learning from real users

Question 30 of 41

Choose 1
Alba (Developer)
We need a paid bank-data service. IT says finance must approve; finance says it's IT's job. It's been a week.

What do you do?

Learn it on Day 17: A blocker above the team

Question 31 of 41

Choose 1
Amos (Support Lead)
Abbas (Product Owner) said no to my dark-mode request in front of everyone. Back me up, Ada.

What role do you take?

Learn it on Day 18: Facilitating a clash

Question 32 of 41

Choose 1
Ansel (Developer)
We took shortcuts to hit the invoice Sprint. Now every change takes twice as long. Should we fix it quietly?

What do you advise?

Learn it on Day 19: Making debt visible

Question 33 of 41

Choose 2
Ari (Developer)
Maybe we should add “no new known shortcuts” to our Definition of Done.

Which two statements are true?

Learn it on Day 19: Making debt visible

Question 34 of 41

Choose 1
Alba (Developer)
Every time I merge, Ansel (Developer) rewrites my code without asking.

The Retrospective gets tense. What do you do?

Learn it on Day 20: Conflict in the Retro
Tallybook

Sprint 4 and beyond

Goal: customers get paid faster with payment links

Question 35 of 41

True or false
Abbas (Product Owner)
Should I even be in the Retrospective? It's the team's meeting.

True or false: the Product Owner takes part in the Sprint Retrospective.

Learn it on Day 20: Conflict in the Retro

Question 36 of 41

Choose 1
Ari (Developer)
We're doing the same Retrospective every time. People are bored.

What do you try?

Learn it on Day 15: Is it really done?

Technique: 4Ls: Liked, Learned, Lacked, Longed for

Question 37 of 41

Choose 1
Aurelia (Head of Product)
Scrum works! Let's switch every department to it on Monday. Send them your templates.

What do you advise?

Learn it on Day 23: Scrum beyond the team

Question 38 of 41

Choose 1
Augustin (Engineering Manager)
Fine. Then I'll be the Scrum Master for the next team. I'm their manager anyway.

What do you explain?

Learn it on Day 23: Scrum beyond the team

Question 39 of 41

Choose 1
Ari (Developer)
Payment links work, but there's a bug with one bank. Launch is tomorrow.

What happens to that part?

Learn it on Day 24: Hold the line on Done

Question 40 of 41

Choose 1
Augustin (Engineering Manager)
Fine, the team can decide some things. But which?

Which technique makes this clear?

Learn it on Day 25: A team that runs itself

Technique: Delegation levels

Question 41 of 41

Choose 1
Ansel (Developer)
Customers keep finding the same kind of bank-import bug. We fix one, another appears.

How do you help the team find the cause?

Learn it on Day 17: A blocker above the team

Technique: 5 Whys