Hospital booking 41 questions 5 phases
Medibook: a Scrum Master case study Medibook lets patients book hospital appointments online. The team is spread over two cities and three time zones, patient data rules are strict, and half the team never speaks in meetings. You're the Scrum Master, hired to make Scrum work for people who rarely sit in the same room.
What this case study tests
Distributed teams Quiet voices Privacy in the DoD Removing impediments
You're the Scrum Master. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Alvin (Product Owner) Former nurse, knows patients well Anika (Developer) Backend, works from Lisbon Adrien (Developer) App screens, very quiet on calls Akosua (Developer) Testing and accessibility Stakeholders
Abdul (Head of Outpatient Clinics) Sponsor Agatha (Data Protection Officer) Patient privacy Aldo (Head of Hospital IT) Servers and access Aurora (Patient) Books appointments for her father Medibook
Getting started One team, three time zones
Question 1 of 41 Choose 1
Abdul (Head of Outpatient Clinics) Asha, I need you to send me a daily report of what each developer did. I can't see them, so I need to know they're working.
What do you offer instead? A short daily written report from each person, exactly as he asks Incorrect. Reporting on individuals invites micromanagement and works against self-management.The Sprint Backlog for progress, and a seat at the Sprint Review Correct. Right. Scrum makes progress visible through its artifacts and events, not through individual reports.Nothing: the team's progress is none of his business at all Incorrect. Stakeholders have a real need to see progress. Offer the Scrum way of meeting it.
Learn it on Day 1: A new team
Check answer
Question 2 of 41 True or false
Alvin (Product Owner) I was a nurse for 15 years. I know exactly what to build. Do I even need a Product Goal?
True or false: the Product Goal is the commitment for the Product Backlog. True Correct. Correct. The Product Goal is the long-term objective the Product Backlog serves.False Incorrect. Each artifact has a commitment. For the Product Backlog it is the Product Goal.
Learn it on Day 3: Coach the vision
Check answer
Question 3 of 41 Choose 1
Anika (Developer) With three time zones, our Daily Scrum is at 7 a.m. for me and 6 p.m. for Adrien. It's miserable.
What do you do? Help the Developers choose a time and format that suits all Correct. Right. The Daily Scrum is the Developers' event; they can choose the time and structure, as long as it's daily and focused on the Sprint Goal.Cancel the Daily Scrum: it's too hard across time zones Incorrect. That removes the daily chance to inspect and adapt, which a distributed team needs most.Pick the time that suits Abdul, since he's head of the clinics Incorrect. It isn't his event.
Learn it on Day 7: The first impediment
Check answer
Question 4 of 41 Choose 1
Adrien (Developer) (on a call, camera off, silent for 15 minutes)
Adrien never speaks in meetings. What is a good first step? Call on him by name in front of everyone, to draw him in Incorrect. Being put on the spot rarely helps quiet people open up.Assume he has nothing to add, and leave him be Incorrect. Quiet people often see important things.Talk with him one-on-one about what would make it easier Correct. Right. One-on-ones help you understand each person, and you can then shape events so everyone can speak (Common practice).
Learn it on Day 1: A new team
Check answer
Question 5 of 41 Choose 1
Agatha (Data Protection Officer) No patient data may be used in testing. Ever.
Where does this rule belong? In a separate privacy audit at the end of the project Incorrect. Late checks hide problems.In each Developer's own personal testing checklist Incorrect. Quality standards must be shared and transparent.In the Definition of Done that every Increment meets Correct. Right. Organisational quality standards belong in the Definition of Done.
Learn it on Day 5: Team agreements
Check answer
Question 6 of 41 Choose 1
Alvin (Product Owner) Can I get a hand with all these stakeholders? Clinics, IT, privacy, patients. I don't know who to involve when.
How do you serve Alvin (Product Owner)? Offer a technique, like a stakeholder map, and facilitate when asked Correct. Right. You serve the Product Owner with techniques and facilitation.Take over stakeholder management for him, since he's busy in clinics Incorrect. Stakeholder decisions stay with the Product Owner.Tell him stakeholders aren't part of Scrum, so it can wait Incorrect. Stakeholders aren't in the Scrum Team, but collaborating with them is essential.
Learn it on Day 2: Who talks to whom
Check answer
Question 7 of 41 Choose 2
Akosua (Developer) Is it true there are only three accountabilities in a Scrum Team?
Which two statements are true? There are three accountabilities: Developers, PO, Scrum Master Correct. Correct.A Scrum Team may have a test lead who approves all work Incorrect. There are no sub-teams or hierarchy in a Scrum Team.Scrum Teams are typically small: 10 or fewer people Correct. Correct. Small teams communicate better.Large products need two Product Owners per Scrum Team Incorrect. One product has one Product Owner.
Learn it on Day 1: A new team
Check answer
Question 8 of 41 Choose 1
Aldo (Head of Hospital IT) Your team needs access to the test servers? Fill in form 7B. It takes about a month.
Sprint 1 starts next week. What do you do? Wait until the team is actually blocked by it, then act fast Incorrect. You can already see it coming.Explain the impact to Aldo (IT) now and agree a faster route Correct. Right. Spotting impediments early and removing barriers with other departments is part of your job.Share your own login with the team, to save them the wait Incorrect. That breaks security rules and hides the real problem.
Learn it on Day 2: Who talks to whom
Check answer
Medibook
Sprint 1 Goal: patients can see available appointment times
Question 9 of 41 Choose 1
Abdul (Head of Outpatient Clinics) Add online payment to this Sprint too. The board meets on Friday.
Who decides how much work the Sprint can hold? The Developers, based on capacity and past performance Correct. Right. Alvin (Product Owner) can bring the request to the backlog for a later Sprint.Abdul (Head of Outpatient Clinics), as the sponsor Incorrect. Stakeholders can share needs, not set the Developers' workload.The Scrum Master, who knows the pace the team works at Incorrect. You help them decide; you don't decide for them.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 10 of 41 Choose 1
Asha (Scrum Master) Sprint Planning on video has dragged on for three hours. Cameras are off and people are drifting.
What helps most? Keep going until everything is planned in detail, however long Incorrect. The plan only needs enough detail to start. Events are timeboxed.Plan it yourself after the call and send the plan round Incorrect. Then it's your plan, not theirs.Hold the timebox, use a shared board, and agree the goal Correct. Right. You keep events productive and within the timebox, and remote teams need the work to be visible.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 11 of 41 Choose 1
Anika (Developer) Yesterday: worked on the slot service. Today: the slot service. No blockers. Next!
Each update is a status report to you. What do you do? Ask everyone for more detail in their updates, so you can follow Incorrect. That deepens the status report habit.Coach the Developers to talk to each other about the goal Correct. Right. The Daily Scrum is for the Developers to inspect and adapt, not to report.Stop attending yourself, so they have to talk to each other Incorrect. Stepping back can help, but coaching them to change the event is the real fix.
Learn it on Day 7: The first impediment
Check answer
Question 12 of 41 Choose 2
Aldo (Head of Hospital IT) The test server access is still in the queue. Maybe next week.
Which two actions fit your accountability? Go to whoever can grant access and agree a next step Correct. Correct. You cause the removal of impediments.Tell the Developers to stop until access arrives Incorrect. Waiting wastes the Sprint.Help them see what they can still do toward the goal Correct. Correct. Adapting the plan is part of their self-management; you can coach it.Copy patient data to a laptop to test it locally Incorrect. That breaks the Definition of Done and the law.
Learn it on Day 7: The first impediment
Check answer
Question 13 of 41 Choose 1
Aurora (Patient) (by email to Akosua) The calendar is hard to read with my screen reader. Can you fix it today?
Akosua (Developer) asks you if she should drop her current task. What do you suggest? Drop everything and fix it today, since it's from the clinics Incorrect. That bypasses the Product Owner and may endanger the Sprint Goal.Bring it to Alvin, who can weigh it against the Sprint Goal Correct. Right. Scope can be clarified and renegotiated with the Product Owner during the Sprint.Ignore it for now: the Sprint's plan is already fixed Incorrect. Feedback from real users is valuable. It goes to the Product Owner.
Learn it on Day 8: Protect the Sprint
Check answer
Question 14 of 41 True or false
Abdul (Head of Outpatient Clinics) If the hospital changes its booking policy mid-Sprint, I'll cancel your Sprint.
True or false: a stakeholder can cancel a Sprint. True Incorrect. Only the Product Owner has the authority to cancel a Sprint.False Correct. Correct. The Product Owner may cancel it if the Sprint Goal becomes obsolete.
Learn it on Day 8: Protect the Sprint
Check answer
Question 15 of 41 Choose 1
Adrien (Developer) (in a private message) I think the slot service has a serious bug, but I didn't want to say it on the call.
What do you do? Encourage him to raise it with the team, and offer to help Correct. Right. Openness about the work and its challenges is a Scrum value. You help make it safe.Fix the bug yourself quietly, to spare him the stress of the call Incorrect. That's not your role, and it hides the issue.Tell Abdul (Head of Outpatient Clinics) straight away Incorrect. The team should handle it first. Escalating past them breaks trust.
Learn it on Day 9: Let the team solve it
Check answer
Question 16 of 41 Choose 1
Alvin (Product Owner) What exactly is the Sprint Goal for? The list of items says it all.
Which statement about the Sprint Goal is true? It's set by the sponsor before Sprint Planning starts Incorrect. The whole Scrum Team crafts it in Sprint Planning.Anyone can change it during the Sprint if they need to Incorrect. No changes are made that would endanger the Sprint Goal.It's the Sprint's single objective, leaving the work flexible Correct. Correct. It's the commitment for the Sprint Backlog.
Learn it on Day 6: Sprint 1 Planning
Check answer
Medibook
Sprint 2 Goal: patients can book and cancel an appointment
Question 17 of 41 Choose 1
Abdul (Head of Outpatient Clinics) I'll present at the Sprint Review. I prefer slides, the team can listen.
How do you set up the Sprint Review? As a slideshow for Abdul and the board, with a summary Incorrect. Then nobody inspects the real product.Skip it this time, since everyone is remote this week Incorrect. Remote teams need the Review just as much.As a working session where stakeholders try the product Correct. Right. The Sprint Review is a working session, not a presentation.
Learn it on Day 10: Review and Retrospective
Check answer
Question 18 of 41 Choose 1
Akosua (Developer) Cancelling doesn't pass accessibility tests yet. Should we show it as done?
What happens to it? It isn't Done, so it isn't in the Increment; it goes back Correct. Right.Show it as done: it works for nearly every patient Incorrect. That breaks transparency.Relax the accessibility rule for now, and restore it later Incorrect. Quality doesn't decrease. The rule stays.
Learn it on Day 10: Review and Retrospective
Check answer
Question 19 of 41 Choose 2
Asha (Scrum Master) In the remote Retrospective, people type in the chat but won't speak.
Which two ideas fit a good Retrospective here? Use a shared board for notes, then discuss the top items Correct. Correct. Formats that let everyone contribute help quiet and remote teams (Common practice).Tell the team what went wrong, to save everyone time Incorrect. Then the improvements are yours, not theirs.End with a few improvements the team chooses to act on Correct. Correct. The Retrospective identifies the most helpful changes.Skip it until the team can meet together in person Incorrect. Every Sprint ends with a Retrospective.
Learn it on Day 10: Review and Retrospective
Check answer
Question 20 of 41 Choose 1
Anika (Developer) None of us has worked with the hospital's calendar system before.
What do you encourage? Assign the work to Anika alone, as she learns fastest Incorrect. You don't assign work, and one person carrying it is a risk.Help the team find someone experienced to pair with Correct. Right. You coach cross-functionality.Outsource it to an agency and wait for delivery Incorrect. The team stays dependent.
Learn it on Day 11: A skill the team lacks
Check answer
Question 21 of 41 Choose 1
Abdul (Head of Outpatient Clinics) (in the team chat) Adrien, add an SMS reminder while you're on booking. Shouldn't take long.
What do you do? Thank Abdul and point him to Alvin, who can weigh it Correct. Right. You redirect politely, every time.Let Adrien (Developer) decide alone what to do about it Incorrect. He may feel he can't say no to the sponsor.Remove Abdul from the team chat, to stop it happening Incorrect. Collaboration matters; the issue is who decides the work.
Learn it on Day 12: The CEO at the desk
Check answer
Question 22 of 41 True or false
Abdul (Head of Outpatient Clinics) Why do I have to go through Alvin? I'm his boss in the hospital.
True or false: the organisation must respect the Product Owner's decisions. True Correct. Correct. Those who want to change the Product Backlog do so by convincing the Product Owner.False Incorrect. For the Product Owner to succeed, the entire organisation must respect their decisions.
Learn it on Day 12: The CEO at the desk
Check answer
Question 23 of 41 Choose 1
Akosua (Developer) Alvin (Product Owner) is in clinics all day. We wait two days for answers.
What do you help them do? Answer the questions yourself, to keep things moving Incorrect. Product decisions are the Product Owner's.Tell the team to guess, and fix it later if the guess is wrong Incorrect. Guessing leads to rework.Agree a faster way to get answers, like Alvin's fixed hours Correct. Right. Short feedback loops keep the team moving.
Learn it on Day 13: Waiting for answers
Check answer
Question 24 of 41 Choose 1
Anika (Developer) Our Daily Scrum on video is 40 minutes now. We end up debugging together.
What do you suggest? Make it an hour: debugging together is useful for everyone Incorrect. Useful, but not the Daily Scrum's purpose.Keep it to 15 minutes; those debugging stay on after Correct. Right. The Daily Scrum is 15 minutes.Only meet twice a week, to save everyone's time Incorrect. The Daily Scrum is daily.
Learn it on Day 13: Waiting for answers
Check answer
Question 25 of 41 Choose 1
Adrien (Developer) Refinement happens at 8 am in my time zone, before I'm online. I never get a say on items I then have to build.
What do you suggest? Rotate the time, and let people comment on items in writing Correct. Right. Refinement only works when all the Developers can shape the items; rotating times and refining in writing lets every time zone take part.Adrien can read the refinement notes afterwards each time Incorrect. Reading notes isn't the same as shaping the work.Drop refinement, since it doesn't suit distributed teams well Incorrect. Unrefined items make Sprint Planning longer and harder for everyone.
Learn it on Day 4: Transparency first
Check answer
Medibook
Sprint 3 Goal: clinics can manage their own appointment slots
Question 26 of 41 Choose 1
Abdul (Head of Outpatient Clinics) The board wants to know exactly when all clinics will be online.
How do you help Alvin (Product Owner) answer? Promise a firm date, to keep the board calm and on side Incorrect. A promise without evidence becomes a broken promise.Help him forecast a range from what's actually finished Correct. Right. Forecasting uses evidence and stays empirical.Refuse to give any forecast at all, to avoid promises Incorrect. The board needs to plan.
Learn it on Day 14: Dates and promises
Check answer
Question 27 of 41 Choose 1
Abdul (Head of Outpatient Clinics) Let's measure success by how many story points the team finishes.
What do you suggest instead? Outcomes like the share of bookings online Correct. Right. Measure value for patients and clinics, not output (Common practice).Lines of code written by the team each Sprint Incorrect. That says nothing about value.Hours worked by each developer every week Incorrect. That invites micromanagement and says nothing about value.
Learn it on Day 16: Learning from real users
Check answer
Question 28 of 41 Choose 1
Aldo (Head of Hospital IT) The new SMS service needs a contract. IT says Legal, Legal says IT. Three weeks now.
What do you do? Wait for IT and Legal to sort it out between themselves Incorrect. The barrier stays.Sign up for an SMS service with your own card, to unblock Incorrect. A workaround that hides the problem and may break rules.Bring IT, Legal and Alvin together briefly on the impact Correct. Right. Removing barriers often means getting the decision-makers in one room.
Learn it on Day 17: A blocker above the team
Check answer
Question 29 of 41 Choose 1
Agatha (Data Protection Officer) Asha, tell Alvin to drop the reminder feature. It's a privacy risk.
What role do you take? Decide for Alvin yourself, to avoid the conflict between them Incorrect. Product decisions are the Product Owner's.Tell Agatha the product's features aren't her concern Incorrect. Privacy is essential input.Facilitate a talk between them, staying neutral yourself Correct. Right. You facilitate stakeholder collaboration; the Product Owner decides.
Learn it on Day 18: Facilitating a clash
Check answer
Question 30 of 41 Choose 1
Adrien (Developer) We copied a lot of code to go faster. Now every change breaks something.
What do you advise? Make the debt and its cost visible to Alvin in the backlog Correct. Right. Transparency lets the team and Product Owner balance it openly.Fix it secretly over the weekend with the Developers Incorrect. Hidden work breaks transparency and sustainable pace.Leave it until launch is done; refactoring can wait until then Incorrect. It slows the team more every Sprint.
Learn it on Day 19: Making debt visible
Check answer
Question 31 of 41 Choose 2
Akosua (Developer) Can we add “accessibility tested with a screen reader” to the Definition of Done?
Which two statements are true? The Scrum Team can strengthen the Definition of Done as it learns Correct. Correct.The Definition of Done can only be changed by the Scrum Master Incorrect. It belongs to the Scrum Team.The Sprint Retrospective is a good place to decide on it Correct. Correct.Once set, it is fixed until the whole product is finished Incorrect. It should evolve.
Learn it on Day 19: Making debt visible
Check answer
Question 32 of 41 Choose 1
Anika (Developer) Adrien never answers my messages in time. I'm tired of waiting on him.
The Retrospective gets tense. What do you do? Take Anika's side, since she's more senior and was waiting Incorrect. Taking sides makes you a referee.Keep it about the messages, and help them agree response times Correct. Right. Handle conflict openly and respectfully, about the work (Common practice).Let it go, and move to the next topic on the Retrospective board Incorrect. Avoided conflict grows.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 33 of 41 Choose 1
Abdul (Head of Outpatient Clinics) Let's compare your team's velocity with the Radiology team's. Whoever is lower works harder.
What do you explain? Velocity is a planning aid; comparing teams inflates it Correct. Right. Velocity isn't in the Scrum Guide and isn't a performance measure (Common practice).Good idea: a bit of competition between teams helps Incorrect. It mostly encourages gaming the numbers.Velocity targets should be set by the sponsor, Abdul, instead Incorrect. Velocity, if a team uses it at all, comes from the team's own work.
Learn it on Day 16: Learning from real users
Check answer
Medibook
Sprint 4 and beyond Goal: patients get reminders they can trust
Question 34 of 41 True or false
Alvin (Product Owner) Should I join the Retrospective? It feels like the developers' meeting.
True or false: the whole Scrum Team takes part in the Sprint Retrospective. True Correct. Correct. Product Owner, Scrum Master and Developers improve together.False Incorrect. The Retrospective is for the whole Scrum Team.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 35 of 41 Choose 1
Adrien (Developer) (one-on-one) I don't think anyone would back me if I said the release isn't ready.
What is this telling you? Adrien needs more confidence in himself and his work Incorrect. It's about the team climate, not one person.Nothing to do: he's just a naturally quiet person Incorrect. Quiet people often see the real risks.Psychological safety is low; welcome bad news openly Correct. Right. Without safety, transparency is only for show.
Learn it on Day 20: Conflict in the Retro Technique: Psychological safety
Check answer
Question 36 of 41 Choose 1
Adrien (Developer) (one-on-one) I've been working until midnight to keep up with Lisbon.
What do you do? Thank him for the commitment he shows to the team Incorrect. Praising hidden overtime encourages more of it.Help him make the load visible so the team adapts Correct. Right. Hidden overtime is an impediment.Tell Anika (Developer) to slow down and rest more Incorrect. The team decides together how to share the work.
Learn it on Day 22: Sustainable pace
Check answer
Question 37 of 41 Choose 1
Abdul (Head of Outpatient Clinics) Radiology wants to work like you. Send them your Scrum templates.
What do you advise? Send them the templates and let them begin on Monday Incorrect. Copying forms without understanding gives the forms without the results.Meet Radiology, explain the why, and go step by step Correct. Right. Planning and advising Scrum implementations is part of serving the organisation.Say Scrum only works for software teams, not radiology Incorrect. Scrum is used for many kinds of complex work.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 38 of 41 Choose 1
Akosua (Developer) Reminders work, but Android users sometimes get them twice. Launch is tomorrow.
What happens to the reminder feature? It isn't Done, so it waits; Alvin decides the rest Correct. Right. Only Done work is part of the Increment.Release it anyway: the missing part is minor Incorrect. Undone work isn't released.Delay the whole release until it's all ready Incorrect. The rest of the Increment is Done and valuable.
Learn it on Day 24: Hold the line on Done
Check answer
Question 39 of 41 Choose 2
Abdul (Head of Outpatient Clinics) We're adding nine more developers. One big team is simpler.
Which two statements are true? A Scrum Team usually has 10 or fewer people in it Correct. Correct.Teams on one product share one Product Owner and backlog Correct. Correct.Each new team gets its own backlog for the same product Incorrect. One product has one Product Backlog.Bigger teams always deliver faster overall, with less effort Incorrect. Large teams communicate worse.
Learn it on Day 25: A team that runs itself
Check answer
Question 40 of 41 Choose 1
Anika (Developer) Six items in progress across three time zones, and nothing Done for a week.
What do you coach the Developers to try? Start more work at once so nobody is ever waiting Incorrect. More started work means less finished.Assign one item to each person so ownership is clear Incorrect. The Developers decide who does what.A work-in-progress limit: finish before you start Correct. Right. With a limit of three, items start reaching Done again.
Learn it on Day 13: Waiting for answers Technique: Work-in-progress (WIP) limits
Check answer
Question 41 of 41 Choose 1
Akosua (Developer) Can we look back over all four Sprints, not just the last one?
Which format fits? Start, Stop, Continue for the last Sprint only Incorrect. Useful, but it misses the bigger picture asked for.A survey sent out to everyone after the project ends Incorrect. You lose the shared conversation.A timeline of key events across all four Sprints Correct. Right. It shows patterns a single-Sprint look misses.
Learn it on Day 25: A team that runs itself Technique: Timeline Retrospective
Check answer