Work-in-progress (WIP) limits
A maximum number of items allowed in a column at once, so the team finishes work before starting more.
What it is
A maximum number of items allowed in a column (or in progress overall) at one time. New work only starts when something finishes.
When to use it
When many items are started and few are finished.
Why it works
Starting too much slows everything down. Limits force people to finish work, expose bottlenecks and shorten delivery times.
Do
- Limits will feel uncomfortable at first; that discomfort shows where flow is blocked.
Don't
- Ignoring the limit when under pressure.
Step by step
- Measure today's work in progress Count cards per column.
- Set limits a little below today For example, people × 1.5.
- Write limits on the board Above each column.
- When a column is full, help finish Instead of starting something new.
- Adjust Lower limits until flow improves, raise them if people are idle.