Flow and visual management · cheat sheet

Work-in-progress (WIP) limits

A maximum number of items allowed in a column at once, so the team finishes work before starting more.

Common practice
5 steps
Used by Scrum Master

What it is

A maximum number of items allowed in a column (or in progress overall) at one time. New work only starts when something finishes.

When to use it

When many items are started and few are finished.

Why it works

Starting too much slows everything down. Limits force people to finish work, expose bottlenecks and shorten delivery times.

Do

  • Limits will feel uncomfortable at first; that discomfort shows where flow is blocked.

Don't

  • Ignoring the limit when under pressure.

Step by step

  1. Measure today's work in progress Count cards per column.
  2. Set limits a little below today For example, people × 1.5.
  3. Write limits on the board Above each column.
  4. When a column is full, help finish Instead of starting something new.
  5. Adjust Lower limits until flow improves, raise them if people are idle.

Worked example

The situation. A five-person team had 18 items in progress.

  1. Limit set to 7.
  2. People paired on blocked items instead of starting new ones.

The result. Average delivery time halved within a month.

WIP limits Print blank
ColumnItems todayLimitBot­tleneck notes

Copy this structure, or print the blank version and fill it in by hand.

In the roles

How a Scrum Master uses it

Mid-Sprint 2, six items are “in progress” and none Done. The Developers set a limit of three. Two days later, three items are Done.

Questions people ask

What if urgent work arrives?

Agree an expedite lane with its own small limit.