Council service desk 43 questions 5 phases
CityDesk: a Scrum Master case study The city council is moving its service desk online: parking permits, bin collections and complaints. The team spends more time in meetings and approval boards than building anything. Every change needs three signatures. You're the council's first Scrum Master, asked to make Scrum work in an organisation built around plans and committees.
What this case study tests
Scrum in a traditional organisation Timeboxes Approval boards Leading adoption
You're the Scrum Master. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Annette (Product Owner) Service manager, 20 years at the council Aurelio (Developer) Backend and integrations Ayla (Developer) Forms and accessibility Anders (Developer) Testing Stakeholders
Agnieszka (Director of Digital Services) Sponsor, chairs the change board Alistair (Head of Procurement) Contracts and purchases Adaline (Councillor) Answers to residents Alfie (Resident) Needs a parking permit for his van CityDesk
Getting started Scrum meets the council
Question 1 of 43 Choose 1
Agnieszka (Director of Digital Services) Before the team starts, I need a 12-month plan with every feature and date, approved by the change board.
What do you explain to Agnieszka (Director of Digital Services)? Scrum never makes long-term plans, so there's nothing to show Incorrect. Scrum plans every Sprint and works toward a Product Goal.Scrum is empirical: set a Product Goal, plan the next Sprints, adapt Correct. Right. Detailed long plans in complex work are mostly guesses.Write the 12-month plan for the board, then quietly ignore it Incorrect. That wastes everyone's time and breaks trust.
Learn it on Day 3: Coach the vision
Check answer
Question 2 of 43 Choose 2
Annette (Product Owner) I've never been a Product Owner. What am I actually accountable for?
Which two statements are true? Maximising the value of the product the team creates Correct. Correct.Assigning tasks to the Developers each morning Incorrect. The Developers decide how they work.Developing the Product Goal and ordering the backlog Correct. Correct.Approving the Scrum Master's work and methods Incorrect. There's no hierarchy in a Scrum Team.
Learn it on Day 4: Transparency first
Check answer
Question 3 of 43 Choose 1
Agnieszka (Director of Digital Services) Annette can be Product Owner, but every backlog change goes through my change board.
What do you explain? The organisation respects her decisions; the board can influence her Correct. Right. A committee can't hold the Product Owner accountability.The change board should order the backlog, since it holds the budget Incorrect. The Product Owner is one person, not a committee.Scrum doesn't allow boards to have any say in the product Incorrect. Stakeholders can give input. The issue is who decides.
Learn it on Day 4: Transparency first
Check answer
Question 4 of 43 Choose 1
Ayla (Developer) Every service has legal accessibility rules. Where do those go?
Where do they belong? In a final accessibility review before launch Incorrect. Late checks hide problems.Nowhere formal: the testers will remember them Incorrect. Quality standards must be shared and transparent.In the Definition of Done, for every Increment Correct. Right. Required quality standards belong in the Definition of Done.
Learn it on Day 5: Team agreements
Check answer
Question 5 of 43 Choose 1
Aurelio (Developer) The council wants us in four status meetings a week on top of Scrum.
What do you do? Attend all of them as well as the Scrum events, to keep peace Incorrect. Then the team has no time to build.Tell the team to skip them all without telling anyone Incorrect. That damages trust. Agree the change openly.Show managers the Review gives them the same, and drop some Correct. Right. The Sprint Review and a visible Sprint Backlog give managers the same information, so some meetings can go.
Learn it on Day 1: A new team
Check answer
Question 6 of 43 Choose 1
Alistair (Head of Procurement) Any tool over 500 euros needs three quotes and six weeks.
The team will need a form-testing tool in Sprint 2. What do you do? Talk to Procurement now about a faster route for small tools Correct. Right. Spot impediments early, before they block the team.Wait until Sprint 2, when the need is actually there Incorrect. It will block the team then.Use a free trial for now, and hope nobody in Procurement notices Incorrect. A workaround that may break rules.
Learn it on Day 2: Who talks to whom
Check answer
Question 7 of 43 Choose 1
Annette (Product Owner) Could you write the Product Goal? You know Scrum.
What do you do? Write the Product Goal yourself, to save Annette time Incorrect. The Product Goal is the Product Owner's accountability.Facilitate a workshop so Annette can shape and own it Correct. Right. You serve the Product Owner with techniques.Let the change board write it, as it approves everything Incorrect. The Product Owner develops and communicates the Product Goal.
Learn it on Day 3: Coach the vision
Check answer
Question 8 of 43 True or false
Anders (Developer) How long should Sprints be? The council plans in quarters.
True or false: a Sprint can last a full quarter if the organisation plans that way. True Incorrect. Sprints are one month or less.False Correct. Correct. Shorter Sprints mean more learning cycles and less risk.
Learn it on Day 5: Team agreements
Check answer
Question 9 of 43 Choose 1
Annette (Product Owner) Every change needs sign-off from IT security, legal and the web team, each with its own queue. Items wait for weeks.
What do you help change? Bring security and legal know-how into the team itself Correct. Right. A more cross-functional team, or standards it can apply itself, finishes most items without queues; fewer hand-offs mean residents get services in weeks.Accept the queues: that's just how the council works Incorrect. Removing barriers like these is part of the Scrum Master's job.Skip the sign-offs quietly, to get the items moving again Incorrect. Security and legal checks still matter; the aim is to build them in.
Learn it on Day 9: Let the team solve it
Check answer
CityDesk
Sprint 1 Goal: residents can apply for a parking permit online
Question 10 of 43 Choose 1
Amir (Scrum Master) Sprint Planning has been going for five hours. People keep waiting for a manager to decide.
What do you do? Name the timebox and help them agree the goal and work Correct. Right. You keep events productive and within the timebox.Keep going until the manager arrives and can decide for them Incorrect. Events are timeboxed, and the Scrum Team decides.End it and plan the Sprint yourself, then share it Incorrect. Then it isn't the team's plan.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 11 of 43 Choose 1
Agnieszka (Director of Digital Services) I'll attend Sprint Planning and approve what the team selects.
Who selects the work for the Sprint? Agnieszka (Director of Digital Services) Incorrect. Stakeholders don't approve the forecast.The Scrum Master, who knows the capacity Incorrect. You facilitate, not decide.The Developers, after the PO explains value Correct. Right. The Developers forecast what they can get Done.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 12 of 43 Choose 1
Aurelio (Developer) Today's Daily Scrum was 50 minutes. Agnieszka asked everyone for a status update.
What do you do? Let her run it today: she's the director, and it's her budget anyway Incorrect. It belongs to the Developers.Explain it's the Developers' event; offer her the Sprint Review Correct. Right. It's for the Developers to inspect progress toward the Sprint Goal.Cancel the Daily Scrum while she's attending, to avoid it Incorrect. The team still needs to plan its day.
Learn it on Day 7: The first impediment
Check answer
Question 13 of 43 Choose 2
Ayla (Developer) We still don't have access to the parking database. The request is with three departments.
Which two actions fit? Go to whoever can grant access and make the impact clear Correct. Correct. You cause the removal of impediments.Wait until all three departments reply to the request Incorrect. The Sprint keeps moving; the impediment doesn't.Help the team see what it can still do toward the goal Correct. Correct. Adapting the plan is the team's call; you can coach it.Copy the database onto a laptop so the team can work Incorrect. That breaks data rules.
Learn it on Day 7: The first impediment
Check answer
Question 14 of 43 Choose 1
Adaline (Councillor) Residents are complaining about bins. Can the team add a bin-complaint form this week?
What do you suggest? Ask Ayla (Developer) to fit the form in quietly this Sprint Incorrect. That bypasses the Product Owner and risks the Sprint Goal.Send it to Annette, who can add it to the backlog and weigh it Correct. Right. New work goes through the Product Owner.Say councillors aren't allowed to make requests to the team Incorrect. They can; it goes through the Product Owner.
Learn it on Day 8: Protect the Sprint
Check answer
Question 15 of 43 Choose 1
Agnieszka (Director of Digital Services) If the budget is cut, can I cancel the team's Sprint?
Which statement is true? Only the Product Owner can cancel, if the goal is obsolete Correct. Correct.The director can cancel any Sprint that her budget funds Incorrect. She can inform the decision, not make it.Sprints can never be cancelled once they have started Incorrect. They can, by the Product Owner.
Learn it on Day 8: Protect the Sprint
Check answer
Question 16 of 43 Choose 1
Anders (Developer) Aurelio wants to skip testing the payment step to finish faster.
What do you do? Agree: the deadline matters more than one missing test Incorrect. Quality doesn't decrease during a Sprint.Test it yourself quickly, so that it can still go out on time Incorrect. You're not the team's tester.Back Anders: it's in the Definition of Done, so it's needed Correct. Right. Developers hold each other to the Definition of Done.
Learn it on Day 9: Let the team solve it
Check answer
Question 17 of 43 True or false
Annette (Product Owner) The parking form might not make it. Should I wait for the Review to tell Agnieszka?
True or false: openness about the work and its challenges is a Scrum value. True Correct. Correct. Tell stakeholders early so they can adapt.False Incorrect. Openness is one of the five Scrum values.
Learn it on Day 9: Let the team solve it
Check answer
CityDesk
Sprint 2 Goal: residents can report and track a complaint
Question 18 of 43 Choose 1
Agnieszka (Director of Digital Services) The Sprint Review is where my board approves or rejects the work, yes?
What do you explain? Yes: the board signs off each item at the Review Incorrect. That turns the Review into a gate.Stakeholders aren't allowed at the Review, only the team Incorrect. Key stakeholders are invited.It's a working session to inspect and decide next steps Correct. Right. The Review is not a gate.
Learn it on Day 10: Review and Retrospective
Check answer
Question 19 of 43 Choose 1
Alfie (Resident) (at the Review) I tried the permit form. I gave up at step 9.
What should happen with this feedback? Annette and the team use it to adapt the backlog Correct. Right. That's what the Review is for.Note it for the council's next annual service review Incorrect. Feedback is most useful right away.Defend the form's design to the residents who tried it Incorrect. The Review is for inspecting, not defending.
Learn it on Day 10: Review and Retrospective
Check answer
Question 20 of 43 Choose 1
Amir (Scrum Master) In the Retrospective, people only say “it was fine”. Nobody wants to criticise in front of a manager.
What helps? Invite more managers along, to encourage honesty Incorrect. That usually does the opposite.Keep it for the Scrum Team only, and make it safe Correct. Right. The Retrospective is the Scrum Team's event.Draft the improvements yourself and share them afterwards Incorrect. Then they aren't the team's.
Learn it on Day 10: Review and Retrospective
Check answer
Question 21 of 43 Choose 1
Aurelio (Developer) Nobody in the team knows the old complaints system. Only one person in IT does.
What do you encourage? Arrange openly for that person to pair with them Correct. Right. Bring the skill into the team, with the dependency agreed.Hand the integration work to IT and wait for it Incorrect. The team stays dependent.Skip the integration for this release and add it later Incorrect. That's a product decision for Annette (Product Owner).
Learn it on Day 11: A skill the team lacks
Check answer
Question 22 of 43 Choose 1
Adaline (Councillor) (to Ayla) Put my name on the complaints page. Residents should know I care.
What do you do? Let Ayla (Developer) do it: councillors are important Incorrect. That bypasses the Product Owner.Tell her politics has no place in a council app, firmly Incorrect. Not your call, and not respectful.Thank the councillor and suggest raising it with Annette Correct. Right. Redirect politely.
Learn it on Day 12: The CEO at the desk
Check answer
Question 23 of 43 Choose 1
Anders (Developer) The complaint stories say “handle complaints”. What does handled mean?
How do you help? Define the items yourself, to save Annette and the team time Incorrect. Not your accountability.Help the team and Annette make the items clear together Correct. Right. You help the team understand the need for clear and concise Product Backlog items.Tell Anders (Developer) to decide what's meant himself Incorrect. The Product Owner and team clarify it together.
Learn it on Day 13: Waiting for answers
Check answer
Question 24 of 43 Choose 1
Adaline (Councillor) The election is in six months. Will all services be online by then? Yes or no.
How do you help Annette (Product Owner) answer? Say yes, to keep the director happy and calm Incorrect. A promise without evidence becomes a broken promise.Help her forecast a range from real progress Correct. Right. Evidence, not promises.Say Scrum doesn't do dates or deadlines at all Incorrect. Forecasting is fine; it stays empirical.
Learn it on Day 14: Dates and promises
Check answer
Question 25 of 43 Choose 2
Anders (Developer) Complaint tracking meets the Definition of Done on Wednesday. Can it go live Thursday?
Which two statements are true? An Increment can be delivered before the Sprint ends Correct. Correct.The Sprint Review is never a gate to releasing value Correct. Correct, from the Scrum Guide.Releases must wait for the director's board to approve Incorrect. Not in Scrum; the Product Owner decides when to release.Only one release per quarter is allowed by the council Incorrect. There's no such rule.
Learn it on Day 15: Is it really done?
Check answer
Question 26 of 43 Choose 1
Ayla (Developer) Items reach Sprint Planning as 30-page council documents.
What do you suggest? Read all 30 pages together in Sprint Planning Incorrect. Planning would take days.Help turn each document into small, clear items Correct. Right. Refinement of each document into short items with acceptance criteria, keeping the document as background, makes them easier to plan, build and check.Refuse any item that's longer than a single page Incorrect. Refusing doesn't help; refining together does.
Learn it on Day 4: Transparency first
Check answer
CityDesk
Sprint 3 Goal: residents book bulky waste collection online
Question 27 of 43 Choose 1
Agnieszka (Director of Digital Services) My board wants to see the team's velocity every week.
What do you suggest? Outcomes for residents, like requests made online Correct. Right. Value and outcomes, not output (Common practice).Velocity for each individual developer, monthly Incorrect. That targets individuals and says nothing about value.Hide all of the team's numbers from the board Incorrect. Transparency matters; show the right numbers.
Learn it on Day 16: Learning from real users
Check answer
Question 28 of 43 Choose 1
Alistair (Head of Procurement) The text-message supplier contract is stuck between Procurement and Legal.
What do you do? Wait for the next quarterly review to raise it with them Incorrect. The barrier stays for months.Sign up with a supplier yourself, to save time Incorrect. That breaks procurement rules.Bring Procurement, Legal and Annette together briefly Correct. Right. Remove barriers between stakeholders and the team.
Learn it on Day 17: A blocker above the team
Check answer
Question 29 of 43 Choose 1
Amir (Scrum Master) Every purchase takes six weeks. This will keep happening.
What do you do? Accept it: that's just how councils buy things, sadly Incorrect. It will block every team.Complain to the councillor about the procurement team Incorrect. Blame doesn't fix the process.Work with Procurement on a fast path for small purchases Correct. Right. Fix the cause, not just the case.
Learn it on Day 17: A blocker above the team
Check answer
Question 30 of 43 Choose 1
Adaline (Councillor) Amir, you're neutral. Tell Annette my feature should go first.
What do you do? Stay neutral and help the councillor explain the value to Annette Correct. Right. You facilitate; the Product Owner decides.Agree with the councillor, since they represent residents Incorrect. Taking sides undermines the Product Owner.Refuse to talk about product decisions with councillors at all Incorrect. Facilitating stakeholder collaboration is part of your job.
Learn it on Day 18: Facilitating a clash
Check answer
Question 31 of 43 Choose 1
Aurelio (Developer) We built quick fixes to get through the approval board. The code is a maze now.
What do you advise? Hide it from the board to avoid awkward questions Incorrect. Hidden debt grows and breaks transparency.Make the debt and its cost visible to Annette Correct. Right. Weigh it openly in the Product Backlog.Rewrite everything over a weekend to clear it Incorrect. Big secret rewrites rarely end well.
Learn it on Day 19: Making debt visible
Check answer
Question 32 of 43 True or false
Ayla (Developer) Let's add “tested with a screen reader” to the Definition of Done.
True or false: the Definition of Done can be strengthened over time. True Correct. Correct. Maturing teams make it more stringent.False Incorrect. It's expected to evolve.
Learn it on Day 19: Making debt visible
Check answer
Question 33 of 43 Choose 1
Anders (Developer) Aurelio keeps changing my test scripts without telling me.
The Retrospective gets tense. What do you do? Keep it about the scripts, and help them agree a rule Correct. Right. Handle conflict openly (Common practice).Tell them to stop complaining and just get on with the work Incorrect. That buries the conflict.Report both of them to Agnieszka, the director, afterwards Incorrect. Escalating to management undermines self-management.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 34 of 43 Choose 1
Annette (Product Owner) Is it OK that I join the Retrospective? It's my team's meeting.
What do you tell her? No: it's only for the Developers, not the PO Incorrect. The whole Scrum Team takes part.Only if the director agrees to it first, in writing Incorrect. It's the Scrum Team's event.Yes: it's for the whole Scrum Team, PO included Correct. Right.
Learn it on Day 20: Conflict in the Retro
Check answer
Question 35 of 43 True or false
Agnieszka (Director of Digital Services) Shouldn't the Scrum Master report on the team's performance to my board?
True or false: the Scrum Master serves the organisation by helping employees and stakeholders understand an empirical approach. True Correct. Correct. Helping people understand and use empiricism is part of how the Scrum Master serves the organisation.False Incorrect. It's one of the ways the Scrum Master serves the organisation, rather than reporting on people.
Learn it on Day 16: Learning from real users
Check answer
Question 36 of 43 Choose 1
Anders (Developer) The committee wants us to promise all four online services by spring. We know we can't.
What should the team say? Promise it, and hope the team somehow manages by spring Incorrect. False promises fail publicly later.Refuse to give the committee any forecast at all Incorrect. The committee needs an honest picture to plan.Give an honest forecast and commit to the Sprint Goal Correct. Right. Commitment in Scrum means doing your best toward the goal, not guaranteeing everything; a promise the team can't keep damages trust more than an honest forecast.
Learn it on Day 12: The CEO at the desk
Check answer
CityDesk
Sprint 4 and beyond Goal: residents get one account for every service
Question 37 of 43 Choose 1
Agnieszka (Director of Digital Services) The minister visits next week. The team works overtime until then.
What do you and Annette (Product Owner) say? Overtime is fine when a minister is visiting the team Incorrect. Tired teams make mistakes.Keep a sustainable pace, and Annette adjusts scope Correct. Right. Scope is the lever.Ask the council to cancel or move the minister's visit Incorrect. Not yours to cancel.
Learn it on Day 22: Sustainable pace
Check answer
Question 38 of 43 Choose 1
Agnieszka (Director of Digital Services) Housing and Planning want Scrum next. Roll it out to all departments in January.
What do you advise? Mandate Scrum for every department from January onwards Incorrect. Forced adoption usually gives the forms without the results.Start with willing departments and teach them the why Correct. Right. You serve the organisation by advising Scrum implementations.Refuse: Scrum isn't really meant for local councils Incorrect. Scrum is for complex work, wherever it is.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 39 of 43 Choose 1
Agnieszka (Director of Digital Services) Fine. I'll be Housing's Scrum Master myself, to keep control.
What do you explain? A Scrum Master serves a self-managing team, not control Correct. Right. No hierarchy in a Scrum Team.Great idea: directors make good Scrum Masters for their teams Incorrect. Control and coaching pull in different directions.Only certified staff are allowed to take the role Incorrect. The Guide doesn't require certificates.
Learn it on Day 23: Scrum beyond the team
Check answer
Question 40 of 43 Choose 1
Anders (Developer) The single account works, except for residents with two addresses. Launch is tomorrow.
What happens to that part? Release it anyway: it's only a rare edge case Incorrect. Undone work isn't released.Delay the whole launch until it's completely ready Incorrect. The rest is Done and valuable.It waits, since it isn't Done; Annette decides Correct. Right.
Learn it on Day 24: Hold the line on Done
Check answer
Question 41 of 43 Choose 1
Agnieszka (Director of Digital Services) Your Daily Scrum keeps drifting into long debates about council rules.
What keeps it focused without losing the topics? Ban all off-topic discussion from the Daily Scrum from now on Incorrect. Some topics matter; they just belong elsewhere.Extend the Daily Scrum to an hour so it can fit it all in Incorrect. It's a 15-minute event.A parking lot: note off-topic items for after the event Correct. Right. The event stays focused; nothing is lost.
Learn it on Day 13: Waiting for answers Technique: Parking lot
Check answer
Question 42 of 43 Choose 1
Annette (Product Owner) Approvals vanish into email. Nobody knows what's blocked or for how long.
What do you set up? A visible impediment board: blocker, impact and owner Correct. Right. Visible blockers get removed; patterns show root causes.A weekly email listing every current blocker to everyone Incorrect. Emails get lost and nobody sees patterns.Nothing: blockers are normal in councils, so live with it Incorrect. Removing impediments is your job.
Learn it on Day 7: The first impediment Technique: Impediment board
Check answer
Question 43 of 43 Choose 1
Aurelio (Developer) Approval board meetings go on for three hours with no decision.
What do you agree before the next one? Keep talking until everyone in the room fully agrees Incorrect. Full consensus may never come.Agree the decision rule: who decides, and how Correct. Right. Knowing how the decision is made stops endless debate.Vote on everything, and the majority always wins Incorrect. Some decisions belong to one accountable person.
Learn it on Day 18: Facilitating a clash Technique: Consent vs consensus
Check answer