← Pilot plan and results: explanationFilled-in example Blank template
Day in the RolePilot plan and resultsPlan, do, study, act
Version1.0
Date15 March

Plan, do, study, act. Write the prediction before the pilot starts.

Plan: what we're testing

Book up to 2 weeks ahead, text reminders for every booking, protected urgent slots with a system lock, two extra Monday sessions moved from Thursday. Whole clinic, 4 weeks.

Prediction and results: same definitions as the baseline

MeasureBaselinePredic­tionResult
Median wait (days)105 or less4
Within 7 days45%85% or more88%
Missed appointments15.7%10% or less8.5%
Thursday and Friday waits7.1 to 9.0 daysno worseno worse

Risks, and when we'd stop

Study: what we learned

All measures improved significantly (two-proportion and Mann-Whitney tests, p below 0.0001). Adopt; add cover for the two lost sessions to reach 90%.

Act: decision

AdoptAdapt and test againDrop
Project leader
Signature
Date
Sponsor
Signature
Date
Day in the Role · Pilot plan and resultsIllustrative example · not a real project or organisation · dayintherole.com