← Kick-off meeting pack: explanationFilled-in example Blank template
Day in the RoleKick-off meeting packKick-off: agenda and minutes
DateThursday 4 April
Time10:00 to 12:00
PlaceCouncil building, room 2
ChairAnnelise (Project Manager)
Notes byAya (Project Coordinator)
Purpose of the meeting

Start the Riverside Health Centre project together: one goal, clear roles, first actions.

Agenda

10:00
Why this project mattersLed by Atticus (Sponsor)
10:15
Objective, scope and milestonesLed by Annelise (Project Manager)
10:40
Who does what (RACI)Led by Annelise (Project Manager)
11:05
How we work and communicateLed by Aya (Project Coordinator)
11:25
Main risks and assumptionsLed by Annelise (Project Manager)
11:45
Questions and next stepsLed by All

Present

  • Atticus (Sponsor)
  • Amani (Clinical Lead)
  • Abigail (Finance)
  • Aine (IT Lead)
  • Adaugo (HR Lead)
  • Antonia (Compliance Lead)
  • Alfonso (Software Vendor)
  • Azadeh (Community Council)
  • Aya (Project Coordinator)
  • Annelise (Project Manager)

Apologies

  • Arash (contract not yet signed)

Parking lot

  • Hire doctors or nurses first? (Amani (Clinical Lead), Adaugo (HR Lead): resolved 13:30)
  • Pharmacy as a later extension: Azadeh (Community Council)

Decisions

  • Weekly team meeting on Mondays at 09:00; project board monthly
  • Senior doctors and lead nurses hired first, the rest from month 4
  • Purchase delay logged as issue I1

Actions

ActionOwnerDueDone
Re-plan building works for a month 2 purchaseAnnelise (Project Manager)Friday
Book the inspector's design reviewAntonia (Compliance Lead)Next week
First residents' updateAya (Project Coordinator)End of month
Network requirements to the contractorAine (IT Lead)Month 2
Next meetingMonday 8 April, 09:00

Letters and symbols: HR Human resources · IT Information technology · RACI Responsible (does the work), Accountable (owns the result), Consulted (asked before), Informed (told after)

Day in the Role · Kick-off meeting packIllustrative example · not a real project or organisation · dayintherole.com