Day in the RoleFeasibility studyCan it be done? Under what conditions?
Version1.0
Date15 March

The idea

A community health clinic in the empty Riverside warehouse, opening next autumn.

Feasibility by area

Legal
FeasibleConditionsNot feasible

Health licence possible; planning permission for change of use needed

Technical
FeasibleConditionsNot feasible

Building can be converted if a structural survey confirms the roof and floors

Financial
FeasibleConditionsNot feasible

About €4M build, within the capital budget; running costs largely covered by regional funding

Practical
FeasibleConditionsNot feasible

Doctors and nurses can be hired regionally with a 3-month lead time

Overall

FeasibleFeasible with conditionsNot feasible

Conditions:

Sponsor
Signature
Date

Letters and symbols: €M Millions of euros (€4.2M = €4,200,000)

Day in the Role · Feasibility studyIllustrative example · not a real project or organisation · dayintherole.com