| Version | 1.0 |
|---|---|
| Date | 15 March |
| Part of the work | Requirements clear? | Cost of late change | Need for user feedback | Approach |
|---|---|---|---|---|
| Building works | LMH | LMH | LMH | PredictiveAgileHybrid |
| Booking system | LMH | LMH | LMH | PredictiveAgileHybrid |
| Hiring and training | LMH | LMH | LMH | PredictiveAgileHybrid |
| Licence | LMH | LMH | LMH | PredictiveAgileHybrid |
Clear requirements and costly change point to predictive; a strong need for user feedback points to agile. Mixed parts make the project hybrid.
| Standard document or control | Kept, combined or dropped | Why |
|---|---|---|
| Risk register, issue log | Combined | One RAID log is enough for this size |
| Benefits plan | Kept | Benefits continue after closure |
| Software design document | Dropped | Vendor's own; the backlog serves us |
| Weekly highlight report | Kept | Sponsor's preferred update |
Letters and symbols: RAID Risks, Assumptions, Issues, Dependencies