Coinwise: a Product Owner case study Northgate Bank has never had a proper app. You've just been hired as Product Owner of Coinwise, its first everyday-banking app. Regulators watch closely, security is non-negotiable, and the sponsor arrives with a list of 50 features.
What this case study tests
Regulation in the DoD Mid-Sprint pressure Outcomes vs output Scaling teams
You're the Product Owner. For each situation, choose your answer and press Check . Every option is then explained, right or wrong.
Team
Alicia (Product Owner) You Aiden (Scrum Master) Coaches the team Ayla (Developer) Backend and integrations Andre (Developer) Security and testing Arlo (Developer) App screens Stakeholders
Arthur (Chief Digital Officer) Sponsor and budget Amira (Compliance Officer) Banking regulation Asher (Support Lead) Hears every customer complaint Agnes (Customer) Retired, banks at the branch today Coinwise
Getting started Your first week at Northgate Bank
Question 1 of 42 Choose 1
Arthur (Chief Digital Officer) Welcome, Alicia! The board wants an app this year. Here's my list of 50 features.
What is your first priority? Turn the 50 features into a detailed 12-month plan for the board Incorrect. A fixed long-term plan ignores what you'll learn. Scrum works empirically.Understand the customers, the stakeholders and the bank's aims Correct. Right. Value comes from understanding the problem and the people before deciding what to build.Ask the Developers to start on login, since every bank app needs it Incorrect. Building before you know the goal risks building the wrong thing.
Learn it on Day 1: You're hired
Check answer
Question 2 of 42 True or false
Arthur (Chief Digital Officer) To keep everyone happy, the heads of Retail, IT and Compliance will act together as Product Owner.
True or false: the Product Owner role can be held by a committee. True Incorrect. The Scrum Guide says the Product Owner is one person, not a committee.False Correct. Correct. One person is accountable. They may represent many stakeholders' needs.
Learn it on Day 12: The CEO has an idea
Check answer
Question 3 of 42 Choose 1
Amira (Compliance Officer) Every feature has regulatory impact. I need to approve the order of the Product Backlog.
How do you respond? Involve her early: her rules become backlog items and quality rules Correct. Right. Compliance is essential input. Regulatory needs can be backlog items or part of the Definition of Done.Let her order the backlog, since regulatory mistakes cost the most Incorrect. Ordering is the Product Owner's accountability and can't be handed over.Leave compliance until just before launch, when features are stable Incorrect. Late compliance surprises are expensive and can block the launch.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 4 of 42 Choose 2
Asher (Support Lead) I'm not sure how stakeholders fit into Scrum. Can you explain?
Which two statements are true? Stakeholders are not members of the Scrum Team Correct. Correct. The Scrum Team is the Product Owner, Scrum Master and Developers.Stakeholders attend the Daily Scrum to check progress Incorrect. The Daily Scrum is for the Developers.Changes to the backlog go through the Product Owner Correct. Correct, straight from the Scrum Guide.Stakeholders sign off every Increment before release Incorrect. There is no sign-off gate. Stakeholders give feedback at the Sprint Review.
Learn it on Day 2: Meet the stakeholders
Check answer
Question 5 of 42 Choose 1
Arthur (Chief Digital Officer) I'll call the app a success if we ship 50 features in year one.
What would be a better measure of success? Features shipped: easy to count, and the board thinks in features Incorrect. That's output. You can ship 50 features nobody uses.Lines of code and story points delivered, as a sign of productivity Incorrect. Code volume says nothing about value.Outcomes: customers banking in the app, fewer branch visits Correct. Right. Value is measured by outcomes for customers and the bank, not by output.
Learn it on Day 3: Shape the vision
Check answer
Question 6 of 42 Choose 1
Alicia (Product Owner) You need a Product Goal for the first months.
Which is the best Product Goal? “Build login, transfers and statements in the first six months.” Incorrect. That's a list of backlog items, not a goal.“Be the best digital bank in the country, as voted by customers.” Incorrect. Too vague to guide decisions about the product.“Customers can do their everyday banking without visiting a branch.” Correct. Right. It describes a future state of the product and guides what to build.
Learn it on Day 3: Shape the vision
Check answer
Question 7 of 42 Choose 2
Aiden (Scrum Master) Let's check the team understands the Product Backlog.
Which two statements are true? The Product Owner is accountable for ordering it Correct. Correct.The Developers who will do the work size the items Correct. Correct. The Product Owner can help them understand trade-offs.Compliance decides which of the items comes first Incorrect. Compliance gives input; the Product Owner orders.Once created, it's frozen until the release Incorrect. The Product Backlog is emergent and keeps changing.
Learn it on Day 4: Build and order the backlog
Check answer
Question 8 of 42 Choose 1
Aiden (Scrum Master) Before we start: how long should our Sprints be?
Which statement is true? Sprints have a fixed length of one month or less Correct. Correct. A consistent length creates rhythm and predictability.Sprint length changes each Sprint to fit the work Incorrect. Sprints are fixed-length events to create consistency.Sprints must be exactly two weeks, the standard Incorrect. Two weeks is popular, not a rule. The limit is one month or less.Arthur sets the length, as he owns delivery dates Incorrect. Sprint length is the Scrum Team's concern, not a stakeholder's.
Learn it on Day 5: Agree how the team will work
Check answer
Question 9 of 42 Choose 1
Amira (Compliance Officer) Bank rules require a security test on everything that reaches customers.
Where does this requirement belong? In the Definition of Done, so every Increment meets it Correct. Right. Organisational quality standards belong in the Definition of Done.In one security test phase just before the launch Incorrect. Late testing hides problems and breaks the idea of usable Increments.With each Developer, who knows which changes need it Incorrect. Quality standards must be shared and transparent.
Learn it on Day 5: Agree how the team will work
Check answer
Coinwise
Sprint 1 Goal: customers can log in securely and see their balance
Question 10 of 42 Choose 1
Arlo (Developer) You want five items this Sprint. We think three is realistic.
Who decides how much work is selected for the Sprint? The Product Owner, who is accountable for the value delivered Incorrect. You propose, but the Developers decide what they can deliver.The Developers, after discussing value with the Product Owner Correct. Right. The Developers select what they can get Done; you explain the value.The Scrum Master, who knows the team's velocity and can settle it Incorrect. The Scrum Master facilitates, but doesn't decide the amount of work.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 11 of 42 True or false
Arthur (Chief Digital Officer) Just write the Sprint Goal yourself before Planning, it saves time.
True or false: the Product Owner creates the Sprint Goal alone before Sprint Planning. True Incorrect. The whole Scrum Team crafts the Sprint Goal during Sprint Planning.False Correct. Correct. You propose how the product could increase value; the team defines the Sprint Goal together.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 12 of 42 Choose 2
Aiden (Scrum Master) Quick check after Sprint Planning.
What makes up the Sprint Backlog? Choose two. The Sprint Goal for this Sprint Correct. Correct, the why.A plan for delivering the Increment Correct. Correct, the how. Together with the selected items (the what).The full product roadmap for the year Incorrect. The roadmap is not part of the Sprint Backlog.A sign-off from the Compliance team Incorrect. Not part of the Sprint Backlog.
Learn it on Day 6: Sprint 1 Planning
Check answer
Question 13 of 42 Choose 1
Ayla (Developer) The core banking test system is down. We're blocked for at least two days.
What is the best response? Aiden helps remove the blocker while you check the Sprint Goal Correct. Right. The Scrum Master causes impediments to be removed; you keep an eye on value.Cancel the Sprint, as the team can't work on the goal right now Incorrect. The Sprint Goal is still valid. Cancelling is only for an obsolete goal.Tell the team to wait: it's IT's system, not the team's problem Incorrect. Waiting wastes the Sprint. Impediments need action.
Learn it on Day 7: A blocker on day two
Check answer
Question 14 of 42 Choose 1
Asher (Support Lead) Customers keep calling about forgotten passwords. Put password reset into this Sprint!
How do you handle it? Add it to the current Sprint straight away: fewer calls is real value Incorrect. Changes that endanger the Sprint Goal aren't made during the Sprint.Leave it with support: resets are a service issue, not a product one Incorrect. Support pain is valuable evidence about value.Add it to the Product Backlog and order it, possibly for next Sprint Correct. Right. New requests go to the backlog, protecting the Sprint Goal.
Learn it on Day 8: A request on the go
Check answer
Question 15 of 42 Choose 1
Arthur (Chief Digital Officer) Customers ask for 30 things. How do we know which will really make them stay?
Which technique helps sort basics from delighters? Count how often each feature is asked for, and build the top one Incorrect. The most requested isn't always what keeps customers.The Kano model: basics, performance needs and delighters Correct. Right. Secure login is a basic; instant spending insights could delight. Cover basics first.Copy what the leading competitor's app offers, as customers expect it Incorrect. That tells you nothing about your customers.
Learn it on Day 2: Meet the stakeholders Technique: Kano model
Check answer
Question 16 of 42 Choose 1
Andre (Developer) Login meets its acceptance criteria, but the security test hasn't run. Is it done?
What do you decide? Done: acceptance criteria met; security can test later Incorrect. Acceptance criteria and the Definition of Done must both be met.Not done: it doesn't yet meet the Definition of Done Correct. Right. Only work meeting the Definition of Done is part of the Increment.Show it as done, and run the security test afterwards Incorrect. Undone work can't be presented as done.
Learn it on Day 10: Review and Retrospective
Check answer
Question 17 of 42 Choose 2
Arthur (Chief Digital Officer) What happens at Friday's Sprint Review?
Which two statements are true? A working session where stakeholders inspect the Increment Correct. Correct.The Product Backlog may change based on what's learned Correct. Correct.Only the Product Owner and Arthur attend the Review Incorrect. The Scrum Team and key stakeholders attend.It's the formal approval needed before any release Incorrect. The Sprint Review is never a gate to releasing value.
Learn it on Day 10: Review and Retrospective
Check answer
Coinwise
Sprint 2 Goal: customers can move money between their own accounts
Question 18 of 42 Choose 1
Arthur (Chief Digital Officer) The board meets next week. Cancel this Sprint and build my dashboards instead.
The Sprint Goal is still valid. What do you do? Explain the goal still stands; add the dashboards to the backlog Correct. Right. Only the Product Owner can cancel, and only for an obsolete Sprint Goal.Cancel it: the sponsor funds the app, and the board is a real need Incorrect. A valid Sprint Goal isn't cancelled because of pressure.Ask Aiden (Scrum Master) to cancel it, as he protects the process Incorrect. Only the Product Owner has that authority.
Learn it on Day 8: A request on the go
Check answer
Question 19 of 42 Choose 1
Ayla (Developer) Transfers turned out bigger than we thought. We can't finish all the selected items.
What should happen? Ask the team to work this weekend, so everything selected is done Incorrect. That isn't sustainable and risks quality.Skip the security test for this Sprint only, and add it back later Incorrect. Quality does not decrease during the Sprint.Renegotiate the scope with the Developers, keeping the Sprint Goal Correct. Right. Scope can be clarified and renegotiated with the Product Owner.
Learn it on Day 13: Questions from the team
Check answer
Question 20 of 42 True or false
Arlo (Developer) If we're late, could we relax our quality rules just this once?
True or false: quality goals may be lowered during a Sprint to meet the Sprint Goal. True Incorrect. The Scrum Guide is explicit: quality does not decrease.False Correct. Correct. Scope is negotiable, quality is not.
Learn it on Day 9: A tool problem
Check answer
Question 21 of 42 Choose 1
Amira (Compliance Officer) New regulation: from next month, transfers over €1,000 need extra verification.
What do you do? Wait until the auditors ask, as the details may still change Incorrect. Missing a legal deadline is a serious product risk.Interrupt the Sprint and force it in: legal work comes first Incorrect. Only if the Sprint Goal is obsolete would you consider cancelling. Otherwise it goes into the backlog.Add it to the Product Backlog, ordered high for the deadline Correct. Right. A real deadline is part of value and risk.
Learn it on Day 4: Build and order the backlog
Check answer
Question 22 of 42 Choose 1
Ayla (Developer) Biometric login is next, but nobody here has built it.
What's the best way forward? Aiden helps find training or pairing; the team decides how; scope can adjust Correct. Right. The team grows its cross-functional skills, supported by the Scrum Master.Hire a contractor and assign them biometric login, so the team isn't slowed Incorrect. The team self-manages who does what.Drop biometric login: if nobody here can build it, it isn't realistic for us Incorrect. A skill gap is solvable, not a reason to give up value.
Learn it on Day 11: Sprint 2 Planning
Check answer
Question 23 of 42 Choose 1
Arthur (Chief Digital Officer) Transfers and statements are Done. Shall we release now or wait for the full app?
What do you decide? Wait until every feature is finished, for one complete launch Incorrect. Waiting delays value and learning.Release now: a Done Increment can be released whenever valuable Correct. Right. Early releases deliver value and feedback sooner.Release at the next Sprint Review, the event for releases Incorrect. The Sprint Review is not a release gate.
Learn it on Day 15: Release decision
Check answer
Question 24 of 42 Choose 2
Aiden (Scrum Master) Time for the Sprint Retrospective.
Which two statements are true? It inspects people, interactions, processes, tools and the Definition of Done Correct. Correct.The most helpful improvements can go into the next Sprint Backlog Correct. Correct.The Product Owner shouldn't attend, so the Developers can talk freely Incorrect. The whole Scrum Team takes part.It's where each team member's performance is rated and discussed Incorrect. It's about improving how the team works, not appraisals.
Learn it on Day 20: Release v1.1
Check answer
Question 25 of 42 Choose 1
Asher (Support Lead) Customers ask when card freezing will arrive. Can you give me an exact date?
How do you answer? Share a forecast range based on progress so far, and say it may change Correct. Right. Forecasts help, but never replace empiricism.Give a fixed date so support can plan, and ask the team to make sure they hit it Incorrect. False certainty damages trust when things change.Say nothing until it's finished, to avoid disappointing customers if plans change Incorrect. Transparency helps stakeholders plan.
Learn it on Day 14: Where are my promo codes?
Check answer
Question 26 of 42 Choose 1
Andre (Developer) “Move money between accounts” is one line in the Product Backlog. Amira (Compliance Officer) says it hides daily limits, fraud checks and audit rules.
What do you do before Sprint Planning? Keep it as one item and let the Developers discover the rules while they build it Incorrect. Compliance rules found halfway through the Sprint put the Sprint Goal at risk.Ask Amira for a full specification of every rule first, so nothing is missed Incorrect. A long specification delays learning; refining together finds what matters first.Refine it with the Developers and Amira into small items with acceptance criteria Correct. Right. Refinement brings hidden rules to light early and turns one vague line into work the team can finish.
Learn it on Day 13: Questions from the team
Check answer
Coinwise
Sprint 3 Goal: customers can freeze their card and get payment alerts
Question 27 of 42 Choose 1
Alicia (Product Owner) App data: 60% of users only check their balance. Transfers are rarely used.
What do you do? Continue the roadmap: transfers are in the goal, and use will grow Incorrect. Ignoring evidence wastes effort.Remove transfers, since the data shows people don't want them Incorrect. The data shows what people do, not why. Find out first: they may not trust it, or not find it.Investigate why, and reorder the backlog on what you learn Correct. Right. Inspect the evidence and adapt.
Learn it on Day 16: Learning from real users
Check answer
Question 28 of 42 Choose 2
Arthur (Chief Digital Officer) The board wants a value report.
Which two are Key Value Areas in Evidence-Based Management? Current Value: what users get today Correct. Correct. The value delivered today.Ability to Innovate: room for new value Correct. Correct. How effectively new value can be delivered.Velocity: how much the team finishes Incorrect. Velocity is a team planning aid, not a value area.Lines of Code: the size of the app Incorrect. Not a measure of value.
Learn it on Day 16: Learning from real users
Check answer
Question 29 of 42 Choose 1
Andre (Developer) Quick fixes made the statements module fragile. Every change now breaks something.
What do you do? Keep quiet: customers can't see the code, and want features Incorrect. They feel it through bugs and slow delivery.Make the debt visible in the backlog, balanced with features Correct. Right. Debt reduces your ability to innovate.Stop all feature work for three months and fix everything Incorrect. Balance is better, decided transparently.
Learn it on Day 19: The team wants to refactor
Check answer
Question 30 of 42 Choose 1
Andre (Developer) Nobody knows if the bank's old payment system can handle instant transfers. We can't estimate it.
What do you agree with the team? Guess a rough estimate and start; the team will learn as it goes Incorrect. You'd commit to something nobody understands.A one-day spike to answer the question, then estimate the item Correct. Right. A timeboxed spike reduces uncertainty; its result is an answer, not a feature.Drop instant transfers: if nobody can estimate them, they're risky Incorrect. Not until you know whether it's possible and valuable.
Learn it on Day 11: Sprint 2 Planning Technique: Spikes
Check answer
Question 31 of 42 True or false
Aiden (Scrum Master) You're overloaded. Could Ayla (Developer) write some backlog items?
True or false: the Product Owner may delegate backlog work but remains accountable. True Correct. Correct, straight from the Scrum Guide.False Incorrect. Delegation is allowed; accountability stays with you.
Learn it on Day 13: Questions from the team
Check answer
Question 32 of 42 Choose 1
Asher (Support Lead) Crypto trading is trendy. Let's add it!
How do you respond? Check it against the Product Goal; if it doesn't fit, say not now, with reasons Correct. Right. The Product Goal is your filter.Put it at the top: trends move fast, and being first wins young customers Incorrect. Trends aren't value by themselves.Agree, because the support lead hears from customers every single day Incorrect. Requests are input, not orders.
Learn it on Day 18: Does it fit the vision?
Check answer
Question 33 of 42 Choose 1
Aiden (Scrum Master) Ayla (Developer) and Andre (Developer) disagree about how to build alerts, and it's getting heated.
What's the best response? Decide the technical approach yourself, so the argument stops quickly Incorrect. That's not the Product Owner's accountability.Escalate it to their line managers before the conflict damages the team Incorrect. Teams first try to resolve conflict themselves.Let the team resolve it, with Aiden facilitating; you stay out of the how Correct. Right. How to build is the Developers' call; the Scrum Master helps.
Learn it on Day 22: Overtime pressure
Check answer
Question 34 of 42 True or false
Arlo (Developer) We finished card freezing on Tuesday and alerts on Thursday.
True or false: several Increments can be created within one Sprint. True Correct. Correct. Each can even be released before the Sprint ends.False Incorrect. The Scrum Guide allows multiple Increments per Sprint.
Learn it on Day 15: Release decision
Check answer
Question 35 of 42 Choose 1
Arlo (Developer) Arthur (Chief Digital Officer) wants card freezing shown to the board on Friday. The payment alerts aren't secure yet, and he's asked us to “just make it look finished”.
How should the team handle the demo? Show what is really done, and say openly what isn't Correct. Right. Openness and courage: in a bank, a demo that hides a security gap misleads the people deciding on risk. The team's commitment is to the Definition of Done, and the board will respect it.Show the alerts with test data, and secure them next Sprint Incorrect. Showing unfinished work as done gives the board a false picture of progress and risk.Postpone the demo until all of it is secure and finished Incorrect. Hiding all the work also removes the chance to inspect it and get feedback. Keep the focus on learning early.
Learn it on Day 22: Overtime pressure
Check answer
Coinwise
Sprint 4 and beyond Goal: customers can pay bills in the app
Question 36 of 42 Choose 1
Arthur (Chief Digital Officer) Marketing wants an earlier launch. Can the team work this weekend?
What do you do? Agree to weekend work, just this once, for the launch Incorrect. Crunch damages quality and morale.Run lighter security tests now, full ones after launch Incorrect. Quality doesn't decrease.Keep a sustainable pace, and adjust the scope instead Correct. Right. Scope is the lever, not people's health.
Learn it on Day 22: Overtime pressure
Check answer
Question 37 of 42 Choose 1
Amira (Compliance Officer) I need a progress report for the regulator.
What's the most transparent option? Write a separate report that quietly leaves out the problems Incorrect. Hiding issues destroys trust and leads to bad decisions.Show the Product Backlog, the Done Increments and a forecast Correct. Right. Scrum artifacts are designed for transparency.
Learn it on Day 14: Where are my promo codes?
Check answer
Question 38 of 42 Choose 1
Arthur (Chief Digital Officer) Coinwise is a success! Let's add 15 developers to your team.
How should this be organised? One big team of 18 Developers, so nobody has to coordinate Incorrect. Scrum Teams are typically 10 or fewer people.Several Scrum Teams sharing one Product Owner and backlog Correct. Right. Teams stay small; the product stays one.A Product Owner and backlog for each team, so each is independent Incorrect. One product has one Product Owner and one Product Backlog.
Learn it on Day 25: Product complete
Check answer
Question 39 of 42 Choose 2
Aiden (Scrum Master) Now three teams work on Coinwise.
Which two statements are true? They share the same Product Backlog Correct. Correct.They share the same Definition of Done Correct. Correct. Teams on one product must comply with the same Definition of Done.Each team has its own Product Goal Incorrect. One product, one Product Goal.Each team has its own Product Owner Incorrect. One Product Owner for the product.
Learn it on Day 11: Sprint 2 Planning
Check answer
Question 40 of 42 Choose 1
Agnes (Customer) I'd love to pay my paper bills by just taking a photo of them.
What does this request represent? Unrealised value: a need users have that the product doesn't meet yet Correct. Right. Validate it; it may shape the next Product Goal.Noise: one customer's idea isn't evidence of what most customers want Incorrect. Customer needs are evidence worth exploring.A reason to build it straight away, before a competitor does Incorrect. Validate first, then order it against everything else.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 41 of 42 Choose 1
Arthur (Chief Digital Officer) Bill payments are live. The Product Goal is achieved. What now?
What's next? Stop using Scrum and move to maintenance, as the goal is met Incorrect. The product keeps evolving.Pursue three Product Goals at once, to keep up the momentum Incorrect. One Product Goal at a time.Set the next Product Goal: one goal is pursued at a time Correct. Right. Fulfil or abandon one goal before taking on the next.
Learn it on Day 23: Thinking beyond v2
Check answer
Question 42 of 42 True or false
Arthur (Chief Digital Officer) Some banks only use Sprints and Daily Scrums, without a Product Owner or Retrospectives.
True or false: that is still Scrum. True Incorrect. Scrum is immutable. Using only parts of it is not Scrum.False Correct. Correct. Each element serves a purpose; only the whole framework is Scrum.
Learn it on Day 1: You're hired
Check answer